Cost Management Flashcards
What are the 4 main inputs to the Determine Budget Process?
Cost Estimate
Project Schedule
Agreements
Scope Baseline
What are the 3 main inputs to the Control Costs Process?
Project Management Plan (Cost Baseline)
Project Funding Requirements
Work Performance Datar
What are the 4 main tools of the Control Costs Process?
Earned Value Analysis
Variance Analysis
Reserve Analysis
To-complete Performance Index
What are the 2 main outputs of the Control Costs Process?
Cost Forecasts
Work Performance Information (CV, SV, CPI, SPI)
What are the 3 main tools used in the Determine Budget Process?
Funding Limit Reconciliation
Cost Aggregation
Reserve Analysis
What are the 2 main outputs of the Determine Budget Process?
Cost Baseline
Project Funding Requirements
What are the 4 main tools of the Estimate Costs Process?
Analogous (top down) Estimating
Parametric Estimating
3 point estimating
Bottom-up Estimating
What is the main output of the Estimate Costs Process?
Cost Estimates
What is the main output of the Plan Cost Management Process?
Cost Management Plan
What is Life-Cycle Costing?
Total cost of ownership from purchase to disposal.
What is Value Engineering?
Maximizing project value in cost, quality, schedule and benefit without sacrificing scope.
What is cost aggregation?
Rolling up Activity costs to accounting periods or the WBS node.
What does the S-Curve represent?
The cumulative sum of the budgeted costs.
What is Funding Limit Reconciliation?
Adjusting project costs and timeframes to fit within funding availability timeframes.
What is the range of a rough order of magnitude (ROM)?
-25% - +75%
What is the range of a preliminary estimate?
-20% to +30%
What is the range of a definitive estimate?
-5% to +10%
Which Process group does the Plan Cost Management Process belong to?
Planning