RIBA (2020) Plan of work Flashcards

To memorise the RIBA stages 0-7

1
Q

How many RIBA stages are there?

A

8 Stages 0 - 7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the latest RIBA plan of work?

A

RIBA 2020 Plan of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What changes did the 2020 plan of work bring?

A

Sustainability

Includes a Sustainability Project Strategy providing actions and tasks aligned with the RIBA Sustainable Outcomes Guide for each project stage.

Planning

Now includes, guidance on submission of a planning application is recommended at the end of stage three. Aims to reduce the risks of designers continuing on to the next stage without fully co-ordinating information.

Stage Three

Name changed from ‘Developed Design’ to ‘Spatial Co-ordination’ to emphasise that stage three is not about changing design concept. Instead, it is about the lead designer managing information until the building is spatially co-ordinated and either ready to be sent to planning or ready for stage four (Technical Design) to start.

Post-occupancy evaluation

Another main driver behind the 2020 Plan of Work updates is post-occupancy evaluation. The plan recommends that facilities management and asset management teams are brought into the process at stage seven. It also encourages light touch evaluation to take place as early as the start of stage six – even before the work of the project team finishes.

Plan for use

In addition to the Plan of Work updates, RIBA is publishing a separate document encouraging a more in-use approach to design. Essentially an interpretation of BSRIA’s 2014 Soft Landings Framework, this guide aims to help designers check earlier on whether what they have designed actually works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What changes did the 2013 plan of work bring?

A

The previous version, published in 2013 has moved online and has undergone a radical overhaul. It is now more flexible, with stages such as planning permission and procurement being moveable, it reflects increasing requirements for sustainability and Building Information Modelling (BIM) and it allows simple, project-specific plans to be created. In addition, the work stages have been re-structured and re-named.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 8 RIBA stages?

A

0 - Strategic definition

1 - Preparation and brief

2 - Concept design

3 - Spatial Coordination

4 - Technical design

5 - Manufacturing and Construction

6 - Handover

7 - Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can you describe what the RIBA plan of work is?

A

The RIBA Plan of Work provides a shared framework for design and construction that offers both a process map and a management tool split into a number of key project stages.

The work stages have been used as a means of designating stage payments and identifying team members responsibilities when assessing insurance liabilities, and they commonly appear in contracts and appointment documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is stage 0?

A

0 - Strategic Definition

Identify clients business case and strategic brief and other core project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is stage 1?

A

1 - Preparation and brief

Develop Project Objectives, including Quality Objectives and Project Outcomes, Sustainability Aspirations, Project Budget, other parameters or constraints and develop Initial Project Brief. Undertake Feasibility Studies and review of Site Information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is stage 2?

A

2 - Concept design

Prepare Concept Design, including outline proposals for structural design, building services systems, outline specifications and preliminary Cost Information along with relevant Project Strategies in accordance with Design Programme. Agree alterations to brief and issue Final Project Brief.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is stage 3?

A

3 - Developed design

Prepare Developed Design, including coordinated and updated proposals for structural design, building services systems, outline specifications, Cost Information and Project Strategies in accordance with Design Programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is stage 4?

A

4 - Spatial Coordination

Prepare Technical Design in accordance with Design Responsibility Matrix and Project Strategies to include all architectural, structural and building services information, specialist subcontractor design and specifications, in accordance with Design Programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is stage 5?

A

5 - Manufacturing and Construction

Offsite manufacturing and onsite Construction in accordance with Construction Programme and resolution of Design Queries from site as they arise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is stage 6?

A

6 - Handover

Handover of building and conclusion of Building Contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is stage 7?

A

7 - Use

Undertake In Use services in accordance with Schedule of Services.