Case Study Flashcards
What is the role of the Employers Agent?
Acts on behalf of the employer on all matters, unless the employer expressly states (in writing to the contractor) that he or she wishes to act themself, or to appoint others to act for him or her on certain aspects of the contract.
The employer’s agent’s duties are summarised within the contract, i.e. to receive and issue:
• applications
• consents
• instructions
• notices
• requests or
• statements
and otherwise to act for the employer under any of the conditions.
What responsibilities does the employer retain?
- Providing possession of the site – as the site belongs to the employer
- Making payment to the contractor in compliance with payment notices – as the employer and the contractor are the contracting parties – no-one else can pay the contractor and
- Issuing a notice to the contractor following the issue of a non-completion notice stating that the employer may require payment of, or may withhold or deduct liquidated damages. The role of the employer’s agent is to issue payment notices without deduction for liquidated damages, though the employer’s agent must advise the employer of his or her rights and responsibilities in this respect.
Whar are the features of Employers Agent Appointment Documents/Service Agreement?
- Project Brief - in broad terms
- The Service - Split into pre-con, construction and post-con
- Responsibilities - Inspection and Testing of Compliance
- Fiduciary - What authorities are passed to the EA;
- Agreement of consultant fees, costs, claims, instructions/variations resulting in cost/programme/specification/design change
- Authority to act on behalf of employer to avoid employer contractual brief
Should be provided to all parties to avoid ambiguity
When may an EA be appointed?
- Can be appointed at any stage prior to execution of contract.
- Concept/Design Stage
- Tender Stage
- Contract Stage
What are the differences between Contract Administrator, Project Manager and Employer’s Agent?
Contract administrator - Identified within the contract. Solely responsible for administering the contract for the employer. It is an impartial role and only exists at the point the contract is entered into, i.e. when a contract exists.
Project manager - Identified within the contract and manages a team to develop and deliver a project for an employer, often from the project inception stage, making decisions on behalf of the employer and giving instructions to the contractor. The project manager provides information, controls and manages communications from the team to the employer so that the employer can act as required. The project manager is impartial in respect of the contract.
Employer’s agent - Identified within the contract and who acts on behalf of the employer in all matters, effectively as if the employer’s agent was the employer. In carrying out its certification and decision-making functions under the contract, employer’s agent should act impartially.
What is the EA’s role with respect to Design?
It is not the responsibility of the employer’s agent to tell the contractor what to design or how to design it, but he or she has to check that the contractor complies with his or her contractual obligations.
What is the EA’s role with respect to Construction?
Once the Design and Build Contract is in place, any employer authority over the contractor may only come through the employer’s agent.
Other parties, for example, quantity surveyors to be able to have contractual powers. In these instances they will normally be appointed to act either directly on behalf of the employer, in which case the contract would have to be amended to provide for that, or through the employer’s agent under the contract. Note that there can only be one employer’s agent under the contract.
Under the contract, the contractor is responsible for management and control of the design team. The employer’s agent could possibly be an architect by profession, but it is critical to state that he or she is not acting in that capacity under the contract.
What is the EA’s role with respect to Insurance?
Check that the relevant insurances to be provided by the contractor are in place in terms of coverage, indemnity limits and timescales in accordance with the contract.
As insurance is a specialist element of construction contracts, the role of the employer’s agent is to check, when assessing the tenders and recommending the appointment of the contractor, that the contractor is able to provide the required policies, certificates and premium receipts for inspection by the employer and his or her insurance advisors.
What are other responsibilities of the EA through the project?
- Project Control Documents - Draft with input of PM/Employer
- Meetings - Chair Progress/Employer Meetings
- Project Status Reports - Provide confidentially to employer
- Issuing Instructions - Properly issued in writing
- Quality Inspections - Carry out regularly
- Patent & Latent Defects - Issue relevant instructions (removal from site of works, change instructions, opening up/testing instructions)
- Change - Vary work as set out in the contract
- Payment - Issue Certificates
- Claims - receive notices from Contractor for EoT/L+E, issue notices on Non-Completion (LADs)
What are the implications of the Law of Agency fo EA’s?
- Confidentiality: EA must hold any information received from the employer as confidential, and may only divulge this information with their express permission.
- Duty of care: unlike a normal commission where the duty of care falls to the company first and the employer second, the role of employer’s agent in effect is the same as a director of the employer. The employer’s agent, therefore, has an obligation that may exceed or conflict with their employment duties. In summary, the employer’s agent has a duty not to allow the employer to fail in their contractual obligations, not to cause damage or loss to the employer, and to act in the employer’s best interests.
Employer can pursue the employer’s agent directly. While this route would provide no limitation on a legal judgement, the courts have been reluctant to exceed any agreed limitations stipulated for professional indemnity.
What other practical considerations are their for appointing an EA?
- Competence, technical ability and experience. EA should be able to demonstrate that they have the experience and technical ability to carry out the employer’s brief.
- Conflicts of Interest. EA cannot act in any role where it could be seen that confidential information or communication between the employer’s agent and the employer could be provided to the contractor.
What is the Contractor’s responsibility to the EA?
- Check information and works carried out are compliant with the contractor’s obligations and employer’s requirements, and that any requested changes identify all changes required to the employer’s requirements and the contractor’s proposals.
- Early Warning. Inform EA as soon as they becomes aware of any work that has been carried out in contradiction to the employer’s requirements or contractor’s proposals.
- Change Requests. identify any and all elements of the employer’s requirements and contractor’s proposals which require change, any change submitted must remain compliant with the remaining unchanged employer’s requirements and contractor’s proposals.
- Comply with Contract and Prompt responses. Not act in a manner that would create a breach in the contract by either the employer or the employer’s agent. All requests for change, information issue, inspections of work, requests for information etc. should be provided in sufficient time to act within the contract or programme timescale.
What is the EA’s responsibility to the Contractor?
- Hindrance. Not to hinder or obstruct the contractor in the execution of his or her contractual obligations.
- Not Interfere. Action must not be construed as managing the contractor’s team, or interfering in the contractor’s attempts to act diligently in carrying out the works.
- Warn. Warn the contractor of any non-compliance observed as soon as it is noticed.
- Acknowledge. That the contractor has complied with his or her obligations when issuing the practical completion statement.
- Impartiality. Remain impartial with regard to the valuation of the works, processing of claims, and duties relating to certification.
- No breach. EA should not act in a manner that would create a breach of the contract by the contractor.
What are the EA’s responsibilities to the Employer?
Act as if they were one and the same as the employer. As a result, the employer’s agent has the following obligations to the employer:
- Confidentiality. Not to divulge any information of a confidential or private nature given by the employer where the employer has specifically requested.
- Warning. the employer of any potential breaches in the contract, and endeavour to enable the employer to fulfil their contractual obligations in a timely fashion.
- Advise. Based on his or her knowledge and experience to assist the employer in making informed decisions (unless expressly stated, the employer has appointed a qualified construction professional).
What are the Employer’s responsibilities to the EA?
- Timely Decisions and Payments. In compliance with the contract, and therefore should check that he or she has the means to do this.
- Give EA suitable authority. As required to fulfil the role and responsibilities identified in the employer’s agent’s appointment.
- Not impede or interfere. With the work of the EA once that authority is given.
- Information. Provide EA with all information relevant to the project so as to allow the employer’s agent the ability to offer good advice.
What may be included in the Employer’s Requirements?
In general, matters likely to affect the preparation of the contractor’s proposals.
- Site Details
- Project description including any drawings/specifications already prepared
- Building Purpose for use
- Functional requirements
- Specific requirements for finishes/elements
- Bills of quantities (if supplemental provisions apply)
- Drawing Submission & As-Builts requirements
- Team Functions (EA and others in Employers Team)
- Payments confirmation. Alternative A (stage) or B (periodic)
- Details of any provisional sums
- Planning restraints, e.g. restrictive covenants, and any permissions already granted
- Access restrictions
- Utilities availability
- Contract form and any amendments, and any legal documents
- CP’s presentation method
- Contract Info e.g. project control requirements and templates
How may acceleration be achived?
In order to improve the rate of progress the
contractor may be able to change:
- Site working hours
- Level of resources deployed
- Programme
- Temporary works (weather protection etc)
- Methods of working.
The employer may be able to make changes to:
- Specification
- Design
- Work scope.
What factors should be considered when suggesting/agreeing acceleration measures?
- Focus on Critical Path/s
- Efficiency losses from resource changes
- Extended Working Hours - Cost, Productivity increase not linear, potential restrictions, quality, H&S
- Increased Resources - Keep correct balance between resources, labour/plant etc. Sufficient area/space limitations/welfare capacity
- Alterations to the programme - Least effective, already optimistic, re-sequencing risks to quality/damage/H&S.
- Introduction of Temporary Works - Weather protection etc.
- Working Methods - Quality risk
- Changes to specification/Design - Employer may end up with something they didn’t want. Potential additional design fees.
- Work Scope Changes - Omitting rarely possible or practical. Delaying to post PC isn’t acceleration and incurrs QA/H&S risk/disturbance etc. If work omitted, contractor may claim for Loss of Profit.
What parts should be outlined in an Acceleration quotation?
- What can be achieved?
- How it will be achieved?
- What it will cost?
- Basic Costs
- Allowance for Risk
- Lump sum or Itemised
- Assessments based on actual cost
What do decisions regarding acceleration come down to, and what are the risks?
- Cost-Benefit Analysis
- Measures conducted and costs incurred, but works not completed early
- Other action specific risks
- Difficult to make a decision under time pressure.
What Relevant Events allow for EoTs under JCT?
- variations
- instructions
- deferment of possession of the site
- suspension
- works by statutory undertakers
- exceptionally adverse weather
- civil commotion
- terrorism and strikes
- ‘any impediment, prevention or default … by the Employer’.