JCT Sections Flashcards
1
Q
What is the Format and Structure of a JCT Contract?
A
Articles of Agreement
Contract Particulars
Conditions of Contract
Schedules
The schedules cover some of the more commonly used ‘add-ons’ to a construction contract, such as insurance options, a design submission procedure and fluctuations.
2
Q
What is Section 1?
A
Definitions and Interpretation
3
Q
What is Section 2?
A
Carrying Out the Works
4
Q
What is Section 3?
A
Control of the Works
5
Q
What is Section 4?
A
Payment
6
Q
What is Section 5?
A
Variations
7
Q
What is Section 6?
A
Injury, Damage and Insurance
8
Q
What is Section 7?
A
Assignment, Third Party Rights and Collateral Warranties
9
Q
What is Section 8?
A
Termination
10
Q
What is Section 9?
A
Settlement of Disputes