Level 2 - Risk Management Flashcards
1
Q
Define Risk
A
- Likelihood of an event occurring and its consequential impact
- Uncertain events
2
Q
Define Issue
A
- Relevant event that has happened, was not planned and required immediate attention
3
Q
What are the stages of risk management?
A
- Identify
- Analyse
- Respond
- Monitor
4
Q
What are the risk response strategies?
A
- Sharing
- Transfer
- Avoidance
- Reduction
- Retention
5
Q
Risk management categories?
A
- External – uncontrollable
- External – Influenceable
- Internal – Controllable (client)
- Internal – Controllable (user)
- Internal – Controllable (project)
6
Q
What is a risk register and what is its purpose?
A
- Document highlighting all known project risks
- Qualitative and quantitative
- Used to monitor and track risks at regular intervals to enable best possible chance of mitigation
7
Q
What actions can be taken to minimise risk at project outset?
A
- Detailed client brief
- Procurement route selection
- Surveys
- Correct project team and contractor selection
- TDD studies
8
Q
What is a qualitative assessment?
A
- Prioritise risks for importance
- Don’t cost them
- Likelihood of occurrence and magnitude (high, low, medium)
- Severity rating = likelihood of occurrence x impact
9
Q
What quantification methods are you aware of?
A
Monte Carlo
- Computer simulation used to model outcomes
- Models a number of potential risks occurring in a number of different combinations, looks at the most likely outcome based on this and the most appropriate risk allowance which should be included for the project on that’s basis
- 90% certainty of completion for less than £xxx
Central limit theorem
- Mathematical method to provide 90% confidence on contingency allowance
Simple method
- Cost assigned to risks in register along with probability
- Cost x probability
Probabilistic
- Best / likely / worst case (probabilities =100%)
- More detailed version of simple method
- Expected value per assumption
Fault tree analysis
- Deductive approach to determining causes of risk
- Start with top undesired event and work back
Event tree analysis
- Possible outcome from initial event
Percentage addition
- OCE
10
Q
How can you advise a client in terms of protection should a contractor become insolvent?
A
- Collateral warranties
- Bonds
- PCG
- Insurance
- Termination
11
Q
What were the key risks you advised on MatchesFashion?
A
- Inflated labour costs (OOH working)
- Site coordination issues with PC resulting in delays
- Fast flowing request for change by wider business
- Contingency levels
12
Q
What should be included on a monthly risk report?
A
- Most serious risks
- Planned responses
- Pans to reduce, transfer, risks where undesirable
13
Q
What are the factors affecting procurement route choice?
A
- Client type
- Risk appetite
- Time available
- Cost certainty
- Design development
- Specialist input
- BIM
- Complexity of works
- Change accommodation
- Contract administration