Level 2 - Risk Management Flashcards

1
Q

Define Risk

A
  • Likelihood of an event occurring and its consequential impact
  • Uncertain events
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Issue

A
  • Relevant event that has happened, was not planned and required immediate attention
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the stages of risk management?

A
  1. Identify
  2. Analyse
  3. Respond
  4. Monitor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the risk response strategies?

A
  • Sharing
  • Transfer
  • Avoidance
  • Reduction
  • Retention
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Risk management categories?

A
  • External – uncontrollable
  • External – Influenceable
  • Internal – Controllable (client)
  • Internal – Controllable (user)
  • Internal – Controllable (project)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a risk register and what is its purpose?

A
  • Document highlighting all known project risks
  • Qualitative and quantitative
  • Used to monitor and track risks at regular intervals to enable best possible chance of mitigation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What actions can be taken to minimise risk at project outset?

A
  • Detailed client brief
  • Procurement route selection
  • Surveys
  • Correct project team and contractor selection
  • TDD studies
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a qualitative assessment?

A
  • Prioritise risks for importance
  • Don’t cost them
  • Likelihood of occurrence and magnitude (high, low, medium)
  • Severity rating = likelihood of occurrence x impact
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What quantification methods are you aware of?

A

Monte Carlo

  • Computer simulation used to model outcomes
  • Models a number of potential risks occurring in a number of different combinations, looks at the most likely outcome based on this and the most appropriate risk allowance which should be included for the project on that’s basis
  • 90% certainty of completion for less than £xxx

Central limit theorem

  • Mathematical method to provide 90% confidence on contingency allowance

Simple method

  • Cost assigned to risks in register along with probability
  • Cost x probability

Probabilistic

  • Best / likely / worst case (probabilities =100%)
  • More detailed version of simple method
  • Expected value per assumption

Fault tree analysis

  • Deductive approach to determining causes of risk
  • Start with top undesired event and work back

Event tree analysis

  • Possible outcome from initial event

Percentage addition

  • OCE
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How can you advise a client in terms of protection should a contractor become insolvent?

A
  • Collateral warranties
  • Bonds
  • PCG
  • Insurance
  • Termination
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What were the key risks you advised on MatchesFashion?

A
  • Inflated labour costs (OOH working)
  • Site coordination issues with PC resulting in delays
  • Fast flowing request for change by wider business
  • Contingency levels
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What should be included on a monthly risk report?

A
  • Most serious risks
  • Planned responses
  • Pans to reduce, transfer, risks where undesirable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the factors affecting procurement route choice?

A
  • Client type
  • Risk appetite
  • Time available
  • Cost certainty
  • Design development
  • Specialist input
  • BIM
  • Complexity of works
  • Change accommodation
  • Contract administration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly