Review Quiz 1 Contractor compensation Flashcards

1
Q

what are the three types of contractor compensation?

A
  • lump sum
  • unit price
  • negotiated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what kind of projects is lump sum good for and some advantages?

A
  • projects where scope is well defined (building construction)
    advantages:
  • owner has price certainty
  • owner knows what the end of the project will be
  • contractor and realize profit if completes project below fixed price
  • contractor receives monthly progress payments based on estimated % of job completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what are some disadvantages to lump sum?

A
  • flexibility to incorporate design changes is limited, deviation from original plan must be dealt with through change orders/directives, can be expensive and lead to adversarial relationship
  • complete set of plans and specification required before bidding and construction can begin
  • can be risky to contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what kind of projects is unit price good for?

A
  • well defied project scopes but uncertainty in material quantities (excavations)
  • project can be predominantly broken into work items that can be characterized by units
  • almost always used on heavy and highway construction contracts where earthwork and foundation work predominate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what are some advantages and disadvantages to unit price?

A

advantages:
- allows some flexibility in meeting variations in the quantity of work encountered during construction
- contractors dont need to be precise in their quantity takeoffs - generally roughly verify owners bid quantity
disadvantages:
- owner does not have a precise overall cost for the work until it is complete
- measured field quantities are pay quantities - owners quantity measurement teams must be more careful and precise
- can be manipulated by contractors - unbalancing the bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what happens if a small or large quantity is specified for unit price?

A

unit price will be higher to offset mob in and de mob costs (small)
larger quantities lead to economies of scale - reducing price per unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is the percentage of deviation in unit price contract that results in renegotiation?

A

if the deviation exceeds 15% (CCDC -4) then unit price is normally renegotiated
- if deviation is on the high side +15%, owner will request unit price reduction on basis of economies of scale
- if deviation is on low side -15% the contractor will request that unit price be increased so they can recover mob in/de mob costs based on smaller quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what is negotiated contractor compensation?

A
  • owner has flexibility to select the contractor on basis other than low bid
  • owner invites selected contractors to review project documents available at time of negotiation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

how does a negotiated contract work?

A
  • based on documentation provided the contractor is invited to present their qualification to perform the work and to indicate his projected cost and fee for completing the work
  • depending on level of documentation provided to the contractors the cost projections will vary widely
  • in addition to considering cost, the owner will evaluate experience, reputation, facilities, staff available, charge rates, and fee structure to narrow down field to 1, 2, 3 contractors with whom they will negotiate the actual contract form and method of reimbursement
  • most cases the design documents are incomplete, most common form of compensation is cost + fee
  • contractor reimbursed for expenses incurred in construction
  • contract describes in detail the nature of the expenses that are reimbursable
  • normally all direct expenses from labour, equipment, and material as well as overhead to properly manage the project are reimbursable
  • in addition, contractor receives a fee for his expertise and use of his plant in support of the job
  • both parties must agree and clearly define the items that are reimbursable and must agree on the accounting procedures to be used
  • particular attention must be paid to what home office overhead charges will be reimbursed
  • the level of the fee in addition to the charge schedule to be used in reimbursement are major items of discussion during negotiation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what are the four common fee structures to negotiated contracts?

A
  • cost + percentage of cost
  • cost + fixed fee
  • cost + fixed fee plus profit-sharing clause
  • cost + sliding fee
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what are some advantages and disadvantages to cost + percentage of cost

A
  • most lucrative to contractor but subject to abuse
  • little incentive to be efficient and economical
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what are some advantages and disadvantages to cost + fixed fee

A
  • fee usually set percentage of previously estimated total cost
  • contractor has incentive to recover their fee over the shortest time frame
  • drawback - contractor may use expensive reimbursable materials and methods to expedite the completion of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what are some advantages and disadvantages to cost + fixed fee + profit sharing clause

A
  • rewards contractor who controls costs, keeping them to a minimum
  • target price for contract is agreed upon
  • if contractor brings job in under target price, the owner shares the savings ( commonly 25%) with the contractor
  • if the contractor exceeds the target price, no savings to be shared
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what is a GMP for negotiated contract

A

in some case the target is used to define a Guaranteed Maximum Price (GMP), a price the contractor guarantees will not be exceeded
- if the GMP is exceeded, the contractor must absorb the overrun
- for a contractor to agree to a GMP, the plans and concept drawings must be sufficiently detailed to allow determination of a reasonable target

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Advantages of a GMP

A
  • with GMP, incentive exists to save money below target
  • owner is also more likely to accept the project as complete if it is under target
  • each additional dollar paid for work on the punch lust costs the contractor 25 cents but costs the owner 75 cents
  • this reduces the amount of quibbling over the punch list
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what are some advantages and disadvantages to cost + sliding fee

A
  • provides a bonus for underrun but also a penalty for overrunning the target
  • the amount of the fee increases as the contractor falls below the target and decreases as they overrun the target
17
Q

random negotiated contract facts

A
  • used most commonly in the private sector and only seldom in the public sector due to the potential for abuse through favoritism
  • private owners prefer due to opportunity to phased construction
  • used almost exclusively for complex long-duration projects where accurate cost forecasts are impossible