Review Quiz 1 basic construction management Flashcards
1
Q
what does CM do as a specific delivery method?
A
- Management services are provided to owner before construction or contractor hired
- CM becomes part of team early design phase, assists owner throughout entire design process
2
Q
What are the two types of CM delivery
A
- Agency CM (without risk)
- At risk CM
3
Q
What is an Agency CM
A
- CM hired by owner to oversee construction process but “does not use his own crews for labour and not financially responsible for construction costs”
- hired early in the process to provide expertise
- At completion of design CM co-ordinates hiring of separate GC who will complete physical work/hire subs
- CM manages GC
4
Q
Advantages of Agency CM
A
- Construction expertise early in process
- Allows for fast tracking / or sequential
- Cost benefit of competitive bidding for construction work
5
Q
Disadvantages of Agency CM
A
- Requires high owner input & level of sophistication
- Only suitable for commercial or large projects that would benefit from increased levels of management
6
Q
What is at risk CM?
A
- Similar to Agency CM acting as a consultant to the owner early in process but then acts as equivalent of the GC during construction process
- CM carries some risk bc he provides owner with price guarantee for construction work
7
Q
What is fast track: Concurrent design & construction?
A
- Construction begins without owner having a complete design & detailed and complete estimate
8
Q
What is the risk of fast track
A
- If construction begins and design problems occur at later stage of project, forcing budget change, the owner at that point is committed to more than simple redesign
- good communication between designer and CM is essential as often working on concurrent tasks that must be coordinated
- Designer’s design schedule must be precisely tied to the bid and award of each work package & the detailed construction schedule
- difficult for owner to know real cost of project before construction begins
9
Q
What is the project chronology
A
- precon
- procurement
- construction
- project closeout
10
Q
stages of preconstruction
A
- conceptual planning
- schematic design
- design development
- contract documents
Bidding & award also preconstruction but are discussed under procurement
11
Q
what is the general role of CM during preconstruction
A
- requires continuous owner involvement and interaction as ideas and requires of owner must be clearly translated into contract documents
- supports design process, judges design for constructability, look for ways of reducing cost, prepares for construction & provides competent cost and schedule information
12
Q
owners role in conceptual planning?
A
- hires designer and CM
- selects project site
- establishes conceptual estimate, schedule and program
13
Q
what is schematic design
A
- completion of this phase represents approx. 30% design completion
- design team investigates alternate design solutions and alternate materials and systems, as well as supporting value engineering
14
Q
what happens to schematic design if the CM team decides to tighten schedule?
A
it impacts the designer
15
Q
what happens during schematic design of the designer specifies a specific material?
A
impacts the CM