Review Quiz 1 basic construction management Flashcards

1
Q

what does CM do as a specific delivery method?

A
  • Management services are provided to owner before construction or contractor hired
  • CM becomes part of team early design phase, assists owner throughout entire design process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the two types of CM delivery

A
  • Agency CM (without risk)
  • At risk CM
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is an Agency CM

A
  • CM hired by owner to oversee construction process but “does not use his own crews for labour and not financially responsible for construction costs”
  • hired early in the process to provide expertise
  • At completion of design CM co-ordinates hiring of separate GC who will complete physical work/hire subs
  • CM manages GC
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Advantages of Agency CM

A
  • Construction expertise early in process
  • Allows for fast tracking / or sequential
  • Cost benefit of competitive bidding for construction work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Disadvantages of Agency CM

A
  • Requires high owner input & level of sophistication
  • Only suitable for commercial or large projects that would benefit from increased levels of management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is at risk CM?

A
  • Similar to Agency CM acting as a consultant to the owner early in process but then acts as equivalent of the GC during construction process
  • CM carries some risk bc he provides owner with price guarantee for construction work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is fast track: Concurrent design & construction?

A
  • Construction begins without owner having a complete design & detailed and complete estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the risk of fast track

A
  • If construction begins and design problems occur at later stage of project, forcing budget change, the owner at that point is committed to more than simple redesign
  • good communication between designer and CM is essential as often working on concurrent tasks that must be coordinated
  • Designer’s design schedule must be precisely tied to the bid and award of each work package & the detailed construction schedule
  • difficult for owner to know real cost of project before construction begins
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the project chronology

A
  • precon
  • procurement
  • construction
  • project closeout
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

stages of preconstruction

A
  • conceptual planning
  • schematic design
  • design development
  • contract documents
    Bidding & award also preconstruction but are discussed under procurement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what is the general role of CM during preconstruction

A
  • requires continuous owner involvement and interaction as ideas and requires of owner must be clearly translated into contract documents
  • supports design process, judges design for constructability, look for ways of reducing cost, prepares for construction & provides competent cost and schedule information
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

owners role in conceptual planning?

A
  • hires designer and CM
  • selects project site
  • establishes conceptual estimate, schedule and program
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what is schematic design

A
  • completion of this phase represents approx. 30% design completion
  • design team investigates alternate design solutions and alternate materials and systems, as well as supporting value engineering
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what happens to schematic design if the CM team decides to tighten schedule?

A

it impacts the designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what happens during schematic design of the designer specifies a specific material?

A

impacts the CM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what happens during the design development?

A
  • design team evaluates and selects all major systems and components of the project
  • evaluate and finalization of all the arch components and project systems
  • concurrently project budget and schedule continue to be monitored
  • CM evaluates potential contractors and prepares to secure necessary permits
  • design firm recommends project systems
  • owner decides whether system is acceptable to end user
  • CM evaluates cost and schedule implications
  • continued estimating and scheduling critical to detecting a design in excess of bidget and to ensure schedule continuity
  • preferable to forced redesign when bids have been received and they all exceed budgets
  • forced redesign and rebid leads to higher cost and longer duration
17
Q

what happens at the end of the design phase?

A
  • design 60% complete and should have good system definition
  • most of the project should be quantified and actual unit prices developed
  • a detailed network schedule should be in progress and necessary permits identified and scheduled
  • all key subcontractors should be identified and involved in the estimating, scheduling, and design process as necessary
18
Q

what happens during contract documents phase?

A
  • final prep of documents necessary to define each of the bid packages
  • preparation of the technical documents. drawings and specifications and all other necessary supporting documentation
  • Fast - track - coordination required between designer and CM as bid packages go out to bid
  • Master schedule for the project becomes important during this phase, since designers completion of technical requirements for each bid package needs to be coordinated with advertising/bidding out of the work packages to qualified contractors followed by start of construction
  • before going out to bid, contract documents need to be reviewed by CM last chance to catch/correct any discrepancies
  • as contract documents near completion, CM prepares complete/detailed estimate (owners estimate, fair cost estimate)
19
Q

How can a project be put out to bid?

A
  • bid package by bid package (phased construction)
  • done in total with a single contractor bidding on entire project
  • final estimate and schedule & an integrated cash flow analysis are completed & used to manage the remainder of the project.
19
Q

What are some important things regarding the owners estimate?

A
  • defines the fair cost giving owner a yardstick with which to compare contractor bids
  • carefully reviewing the estimate provides an excellent opportunity for the owner/CM team to prepare for the construction phase. Review may lead to addenda being published
  • provides owners with final accurate cost info - projects owners cash needs on day to day basis when integrated with the finalized network schedule