Rankin Flashcards

1
Q

How many trenches were used? Which systems were being replaced?

A

5 trenches for storm and sanitary pipe replacements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what were type material types/sizes of the new pipes?

A

For Storm - 300mm to 525mm reinforced concrete pipes
For Sanitary - 150mm vitrified clay pipes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What were the soil conditions?

A

Stiff clay and rocks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What were the reasons for the pipe failures?

A
  • Insufficient Bedding materials
  • Inadequate design (design error) considerations for trench widths
  • cracks in the pipes may lead to washout and bending failure in other locations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Elaborate on the insufficient bedding material failure

A

-doesn’t provide adequate uniform support
-capacity could be increased by more than double (from 1.1 to 2.5)
-May have contributed to uneven settlement issues and bending failure
-importance of bedding not conveyed to construction team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Elaborate on the inadequate design of the trench width

A

-If trench widths have been specified, more reliable calculations could be done
-Pipe spacing not specified
Pipes too close may have imposed unexpected load distributions on pipes below beside
Too much additional load may have led to exceeding cracking limit
-Crushing failure of pipes indicate cracking load was exceeded
-Bending failure of pipes due to unequal load distributions
-Proper construction techniques used according to experts retained by MHLP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cracks in the pipe may have led to washouts and bending failures in other locations - caused by????

A

-Washout failure of pipes due to crushing
-Removal of support, and increased bending in shallower areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What was the issue with the drawings?

A

-Pipe elevations shown
-location of pipe in trenches not clear
-trench widths not identified
-physical limitations on widths in some locations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does failure differ in deep pipes vs shallow pipes

A

Deep pipes - longitudinal cracks from crushing
Shallow pipes - transverse cracks from bending

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are some solutions to avoid pipe failure?

A

-designers should clearly define the pipe installation and trench specifications on the construction drawings. If the drawings are unclear, the contractor should clarify the information with the designer
-The designer should ensure that the trench is widen enough for compaction equipment to fit into the trench.
-contractor should use jumper jack to compact trench fill
-compact in lifts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what were some causes of the listowel collapse?

A
  • lamination thicknesses were found to be nonuniform throughout their length decreasing the effectiveness of the glue bonding process
  • faulty glue bonds due to improper fabricating and glue bonds
  • laminated sections contained 10 laminations instead of designed 11
How well did you know this?
1
Not at all
2
3
4
5
Perfectly