beese cherger Flashcards

1
Q

Progress Curves

A

Cumulative estimated job costs VS construction time
a) One Early Start Curve
b) One Late Start Curve
Total Cost & Budgeted cost Plotted Monthly
Cost Envelop is created from present to end of job

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value Management System (EVMS)

A

Compared the physical work accomplished to date with the actual cost expenditure and planned work
yet to be accomplished. This 3-Dimensional comparison determines the earned value on a project and
forms the basis for a more accurate projection of final project cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Benefit

A

An Earned Value Management System combines the actual cost of work completed with the planned
value of that work to generate a projection and determine whether a project is on track and on budget.
This provides project managers with a more accurate and comprehensive view of the project’s progress
over using a simple progress curve, which only shows the amount of work completed over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The Three Variables BCWP, BCWS, and ACWP

A

Budgeted Cost of Work Performed (BCWP)
Cumulative budgeted value of all work activities performed to date.
Budget Cost of Work Scheduled (BCWS)
Cumulative planned value of all the work activities to be accomplished in the baseline
schedule to date.
Actual Cost of Work Performed (ACWP)
Cumulative cost for work completed to date OR current cost of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV)

A

CV = BCWP - ACWP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Variance (S)

A

SV = BCWP - BCWS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Performance Index (CPI)

A

CPI = BCWP / ACWP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Performance Index (SPI)

A

SPI = BCWP / BCWS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CPI of 0.8 Means

A

20% Cost overrun (only 80 cents of every dollar value achieved)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

SPI of 1.2 Means

A

120% work done per budgeted dollar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Three Variables BAC, EAC, and TCPI

A

Budget at Completion BAC
Estimate at Completion EAC
Total Completed Performance Index TCPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EAC1 =

A

ACWP + (BAC – BCWP) / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EAC2 =

A

ACWP + (BAC – BCWP) / (CPI * SPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

TCPI =

A

(BAC – BCWP) / (EAC – ACWP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly