Review - Chapter 6 Flashcards
Define Project Schedule Management
Involves the processes required to ensure timely completion of a project
What are the six main processes involved in Project Schedule Management?
- Planning schedule management
- Defining activities
- Sequencing activities
- Estimating activity durations
- Developing the schedule
- Controlling the schedule
What information is included in a schedule management plan?
Project schedule model development Level of accuracy Control thresholds Rules of performance Reporting formats Process descriptions
What are outputs of the Defining Activities process?
Activity list, activity attributes, a milestone list, change requests, and project management plan updates.
What is the Activity List?
A tabulation of activities to be included on a project schedule. Should include the activity name, ID or number, and a brief description of the activity.
What are Activity Attributes?
They provide schedule-related information about each activity (logical relationships, resource requirements, assumptions related to the activity, etc.)
What is a Milestone?
A significant event that normally has no duration which often takes several activities and a lot of work to complete.
Dependency/Relationship
Pertains to the sequencing of project activities or tasks.
Types of Dependencies
Mandatory dependencies
Discretionary dependencies
External dependencies
Internal dependencies
What are network diagrams?
A schematic display of the logical relationships among project activities and their sequencing and is the preferred technique for showing activity sequencing.
What is the AOA or ADM?
The Activity-on-Arrow approach or Arrow Diagramming Method is a network diagramming technique in which activities are represented by arrows and connected at points called nodes to illustrate the sequence of activities.
Node
The starting and ending point of an activity
Bursts
Occur when two or more activities follow a single node
Merge
Occurs when two or more nodes precede a single node
What is the Precedence Diagramming Method (PDM)?
A network diagramming technique in which boxes represent activities and is particularly useful for visualizing certain types of time relationships.
Types of Relationships Between Activities
Finish-to-start
Start-to-start
Finish-to-finish
Start-to-finish
What are Dummy Activities?
Activities that have no duration and no resources, but are occasionally needed on AOA network diagrams to show logical relationships between activities.
Duration
Includes the actual amount of time worked on an activity plus elapsed time.
What is Effort?
The number of workdays or work hours required to complete a task.