QUIZ: Pre-scheduling Ops - Manual 10 Flashcards
1
Q
- With regards to the PJM contingency reserve requirement, PJM schedules reserves based on what percentage of the largest single contingency?
a. 100%
b. 150%
c. 50%
d. 75%
A
b. 150%
2
Q
- The weekend period with regards to maintenance outages is defined as?
a. Friday at 2300 to Sunday at 1800
b. Saturday at 0000 to Monday at 0000
c. Saturday at 0600 to Sunday at 2300
d. Friday at 2200 to Monday at 0800
A
d. Friday at 2200 to Monday at 0800
3
Q
- Which of the following is NOT a valid generation outage?
a. Maintenance
b. Optional
c. Planned
d. Unplanned (forced)
A
b. Optional
4
Q
- Planned outages are typically scheduled to occur during?
a. Capacity Emergencies
b. EEAs
c. High Peak Months
d. During low peak seasons
A
d. During low peak seasons
5
Q
- AGC stands for?
a. Automatic Gross Cost
b. Automated Gear Cost
c. Automatic Generation Control
d. Automatic Generation Calibration
A
c. Automatic Generation Control
6
Q
- According to PJM, operating reserves are considered those reserves that can be obtained in what time frame?
a. 15 minutes or less
b. 30 minutes or less
c. 5 minutes or less
d. 10 minutes or less
A
b. 30 minutes or less
7
Q
- PJM schedules reserves on a week-ahead basis?
a. True
b. False
A
b. False
8
Q
- Marker seller inputs design data for new generation resources are required by PJM to give how much notice prior to commercial operation?
a. 21 days
b. 30 days
c. 7 days
d. 10 days
A
b. 30 days
9
Q
- What order requires that the TSPs within the PJM RTO provide the ancillary services for regulation and frequency response?
a. NERC order 888
b. NERC order 800
c. FERC order 800
d. FERC order 888
A
d. FERC order 888
10
Q
- Nuclear refueling is considered a typical planned outage
a. True
b. False
A
a. True
11
Q
- Contingency reserves need to be made available within what time frame?
a. 15 minutes or less
b. 30 minutes or less
c. 5 minutes or less
d. 10 minutes or less
A
a. 15 minutes or less
12
Q
- A black start unit is defined as?
a. A Generating unit that can start with the assistance of off-site power
b. The least expensive unit
c. A Generating unit that can start without the assistance of off-site power
d. The most expensive unit
A
c. A Generating unit that can start without the assistance of off-site power
13
Q
- What is the maximum amount of days allowed for an outage during PJM peak period maintenance season?
a. 7 days
b. 9 days
c. 3 days
d. 5 days
A
b. 9 days
14
Q
- PJM is an RTO during which of the following time frames?
a. 6 hours a day / 1 day a week
b. 3 hours a day / 5 days a week
c. 24 hours a day/ 7 days a week
d. 12 hours a day/ 3 days a week
A
c. 24 hours a day/ 7 days a week
15
Q
- What are the peak load period months?
a. September and October
b. November and December
c. March, April and May
d. January, February, June, July and August
A
d. January, February, June, July and August