3.1-3.4 Real Time Operational Considerations Flashcards

1
Q

When must a GO notify PJM before it brings a unit online?

A

20 min

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

GO’s must also notify PJM when : (2)

A
  • Any change in MW output (if not following SCED)

- Coming offine

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How often is the IRC conducted?

A

Min. once before daily peak (30-45 min prior)

could be more depending on system conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What reserve types are validated during IRC?

A
  • Operating
  • Synchronized
  • Quick Start (hydro + other)
  • Supplemental
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How to calculate Operating Reserves (online)

A

Lesser of:

  • ramp rate x 30 min
  • spin max - current MW output
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How to calculate Operating Reserves (offline)

A

Lesser of:

  • offline spin max
  • spin ramp rate x (30 min - TSS)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How to calculate synchronous reserve

A

Lesser of:

  • spin ramp rate * 10 min
  • Spin max - current MW output
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How to calculate quick start non-synchronous reserve

A

Lesser of:

  • spin ramp rate * (10 min - TSS)
  • Spin max
How well did you know this?
1
Not at all
2
3
4
5
Perfectly