questions on case study Flashcards
what does employer need to provide for jct minor works
provide drawings, a specification, or work schedules to define the quantity and quality of work, as well as the requirements for the Contractor’s Designed Portion.
why did you use minor works for demolition works and why was it separate contract?
The JCT Minor Works Building Contract is designed for smaller, basic construction projects where the work is of a simple nature which demolition was and there was no design needed. less than 500k. Scope as per contract particulars. we had 2 contracts due to main contract t&c’s were not agreed on. So to meet programme we had to issue a mw contract.
what is sectional completion?
Sectional completion refers to a provision within the contract which allows different completion dates to be set for different sections of the works. Common on larger projects where completing the works in sections allows the client to take possession of the completed parts whilst construction continues on others.
where are the dates for sectional completion kept?
they are noted in the contract paticulars with seperate lads.
what happens if sectional completion isn’t on time.
Generally contracts containing sectional completion will also
have liquidated damages applicable to each
section, however the liability on each section will
cease once the relevant sectional completion is
certified
what are lads
Liquidated damages are a predefined sum to be
payable in the event of delay beyond the
completion date and are thus recoverable without
proof of loss.
what happens if no completion date is written in contract?
If nocompletion date is set by the contract, time is ‘at
large’ and damages cannot be deducted.
what standard terms did symphony not agree with?
They didn’t agree with the LADS amount, alongside cross contract set off. If we started this negotiation route this would have further prolonged the time to get the kitchen’s onto site.
define cross contract set off
whether a party can look to reduce its liability on one contract by setting off that liability against debts due under another contract
why was the brickwork sum a prov sum?
Due to PCSA stage being so quick we had to finalise a lot of the final orders on stage three drawings which were not very detailed in terms of elevation perceptions. Now detailed design has come through it was raised as a VO.
What are the punishments for not complying with section 106
Within our contract subcontractors are fined a define sum within the scope of works. So for our contract it was £7K. SC needs to actively work with the local authority to source local labour. This could be an apprentice/work experience.
why mend relations
Mend relations due to the local community not being in favour of the two new blocks being built. So in order to mend this we did a lot of social value for the community- we did new flooring for local community/sourcing local labour/school visits.
how did external stakeholders influence design and delivery of scheme
Due to planning we had to make the windows the same finish as the school across the road which was white this impacted design. We had deliveries only being made after 9am when children were in school which impacted delivery of each trade. Design of community hall was contributed to by the local community i.e paint/flooring.
what does PCSA stand for
Pre-Construction Services Agreement
What is PCSA
Typically, a PCSA is used during the second stage of a two-stage tendering process to enable a design and build contractor to commence design work before the main contract has been agreed and executed by the parties. This early contractor involvement is seen in design and build projects.
WHAT IS letter of intent
an agreement to carry out works prior to the formal building contract being entered into.
what does a letter of intent contain
contain legal rights or obligations such as:
-an end date on which the letter will expire (explaining how the parties will progress if the end date is reached and the building contract is not signed);
-specification of the amount of work to be carried out under the LOI;
-payment provisions limiting the amount of money the contractor can be paid under the LOI
with the prov sum who did the risk lie with?
defined prov sum risk lies with the contractor
who does undefined prov sum lie with?
Contractor cannot be expected to include programme and prelim allowances for undefined provisional sums so the risk will remain with the Employer.
does nec have prov sums?
Nec does not have prov sum. This is due to the uncertainty and risks associated with provisional sums.
JCT how do you issue prov sum
Under the JCT forms of contract, an instruction needs to be issued to carry out works defined in the provisional sum schedule.
what mitigation strategies for the brickwork subbie
any long lead times on the materials we derisked by putting other products forward to the architect for approval. labour issues from one plot having low
difference between defined and undefined
rics defines prov sum as -the nature of construction is understood, that quantities can or will be provided based on the indicated scope and that any restrictions are understood.