interview mock questions Flashcards

1
Q

Name prelims for cost of running a site

A

staff salaries, travel costs i.e. fuel, temp accomadation, site canteen, gas water electricity, office consumables and stationery, hoists/pumps/cranes, scaffolding, insurances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

how to measure labour for loss and expense

A

loss and expense could be associated with becoming familiar with an unexpected or unplanned task or something not envisaged in the planned programme. can be measured by mile approach where you compare the value of work output. produced in a non impacted period to that of an impacted period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

is interest charged on loss and expense claims

A

yes 5% under JCT db per annum above the dealing rate of bank of england

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

how did you find out what operation and maintenance costs were for the ve elements

A

on my project I undertook this by asking subcontractors for costs and predictions but that’s the limitation of life cycle costing its based on projections of what these costs could be. Also asking the client if they have previously used the product and its implications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

how did you cost programme savings with VE.

A

so we looked at typical possession of labour cost materials and we estimated the difference in initial cost (construction costs), including any changes in construction methods and if we needed to work on weekends.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

why would a qs use cashflow and what does it mean if interim valuations are ahead/behind cashflow

A

QS uses cashflow to monitor the progress of the works on site against the agreed programme. if interim valuations are ahead this signifies works are ahead of programme. if behind then works are behind. contractor can use cashflow forecast to support claim of loss and expense, it will show they were on there intended programme up until a relevant event caused them to slip behind

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

who else would want to view cashflow?

A

banks. local authority and other guarantors often fund construction. Any errors in the cashflow forecast could leave the client in a situation where they are unable to meet their liabilities for a certain period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

why is it a s curve

A

represents the lower level of periodic expenditure at the beginning of a contract (due to site set up and relatively inexpensive enabling works) and the lower level of expenditure at the end of a contract (due to vast majority of materials being on site)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

how do you produce values of cashflow

A

based on programme its important to understand the subcontractors trades and how their package value is spread. i.e looing at big critical activies for example installing first fix m&e and drylining.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

an accurate cashflow forecast will have to take account of retention

A

an accurate cashflow forecast will have to take into account retention. it will mean that there will be a long period between pc and the final cert where the cashflow is static with a final jump at the end which signals the return of the final part of retention

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

reasons for cashflow being behind?

A

site conditions/adverse weather resequencing of works/ cashflow not being accurate in the first place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what potential risks are there to a planned cashflow forecast?

A

effect of changes in design specifications//effect of inflation//effect of interest and exchange rate (where supplied or labour are being sourced from overseas)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

typically why would you need to resequencing works.

A

recover time due to previous slow progress, late procurement of sc’s , site conditions encountered, adverse weather.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly