Employers agent Flashcards

1
Q

what are employers agent duties

A

to recieve and issue applications, consents from employer, instructions, notices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

when is EA employed?

A

they should be identified in the PCSA document, they will assit employer in selection and appointment of design team and principal contractor/designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

define right of suspension

A

under housing grants, construction act the right of suspenion extends to all or any of the contractors obligations under his or her contract with employer.gives a party to a construction contract the right to suspend performance of his obligations if he is not paid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

if contractor fails to complete works by completion date

A

the ea will issue a non completion notice to that effect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

termination by employer

A

employer to give notice specifying each default. if it continues for 14 days after recipt of notice, the employer may within the 21 days of expiry of that period terminate contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

once pc cert is issued by ea

A

rectification period commences and half of the retention is released

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EA responsibility to contractor

A

ea not to hinder or obstruct contractors work. they’re responsible for checking that contractor has complied with contractors obligations to complete contract in accordance with ER’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

EA’s responsibiltiy to employer

A

not to divulge any information of confidential matter given by employer//warning employer of possible breaches in contract and provide advice on his/her knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

where is EA role defined

A

defined in their appointment document, introduction of PID(project initiation doc) or pep (project execution plan)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what are contractors proposals

A

this is in response to ER’s these proposals prevail under JCT. if employer requires something not in the contractors proposals then its defined as a change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

it is responsibility of ea to check er’s cover the following:

A

details of site, its boundaries, purpose of the building, specific requirements as to finishes, access restrictions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

who is PCG prepared by? and how is it executed

A

by employer and executed as a deed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

if a performance bond is being provided is a PCG required as well?

A

depending on the project often in complex projects both will be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

difference between bonds and pcg

A

bonds provide access to a pot of money to cover the cost of appointing a substitute contractor if the original contractor becomes insolvent. PCG guarantees attempt to ensure that the parent will see to it that their subsidiary performs in a default situation. If contractor doesn’t have a pcg then a bond can be sought.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

purpose of bond

A

bonds are issued by specialist surety companies, banks, insurance comapnies. employer will wish to have sufficient secrutiy in place in case of insolvency. bons provides short term cover for a contractor default.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

who is a bond executed by?

A

by both bondsman and contractor executed as a deed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

dis for contractor on collateral warranty

A

issue can arise where contractor has to procure subcontractor warranties. this is due to agreement of subcontract terms only takes place following completion of building contract. as a result contractor is agrreing to procure subc warranties which they have not agreed with subbies yet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

what is collateral warranty limiting clause

A

most cw’s include clause limiting the period during which the beneficary may make a claim against the warrantor. often it is 12 years from pc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

cw clause for professional indemnity

A

warrantor to obtain pi insurance cover often for 12 years from pc. provided that the warrantor has a design obligation. level of insurance stated in underlying contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

step in right meaning

A

step in right allows a funder to take over the employers role in a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

difference between warranties executed under hand vs warranties executed as a deed

A

warranties under hand are subject to a 6 year period of limitation of action (i.e. legal proceedings have to be instituted within 6 yrs of the breach complained) whereas as a deed are subject to a 12 year limitation period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

define third party rights

A

rights provided under the TPR act( third parties act 1999) which allows an interested third party beneficiary to enforce the terms of a building contract, sub-contract-subconsultant. such rights can create a contractual relationship in the same manner as cw.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

ads and dis of 3rd party rights

A

may help reduce paperwork, save time on construction projects. dis party may still be reluctant to accept third party rights instead of receiving hard copy, signed and dated cw.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

define latents defects insurance policy

A

is a non-cancellable policy covering the cost of rectifying certain types of defects that may arise in a building during a 10 or 12 year period. covers owners tenants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

why would a budget evolve?

A

=tender addendums: depending on procruement route client may issue changes to a contract after contract has been signed.
=variations: throughout the contract there will be changes to manage
=value eng: detailed estimate may have been priced a certain way but during the job its had to be delivered another way i.e. concrete pumps might be used to save on labour and reduce time on site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

how is company overheads calculated

A

determined by expressing the budgeted annual overheads as a percentage of budgeted turnover and applied as a proportion of the cost of indivudal contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

what is reverse of value engineering

A

design growth which is the reverse and is effectively scope creep. Without a proactive discipline in the commercial team, additional costs resulting from design
growth may not be picked up and affect the profitability of the project for the contracting
organisation. This, in turn, may result in disputes with the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

how does supply chain insurance effect mc

A

when the supply chain has insurance at a particular level, this effectively indemnifies the main contractor for this
amount for the works undertaken in the wider project, subject to the terms of the policy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

define contractural indemnity

A

is an agreement by one party to reimburse another party for any
loss suffered as a result of specified items that the indemnity covers, thereby transferring the risk to the party providing the indemnity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

define insurance

A

Insurance is a separate contract (usually called a policy), taken out with a third-party insurer
after the payment of a premium, to provide a party with certain costs and expenses to cover
a legal liability that the party may owe to another party, or to cover the party’s own costs and
expenses suffered as a result of a particular event. The risk in this case is transferred to the
insurer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

what to consider when procuring with subbies

A

The programme: it is worth stressing that programme requirements and dates should be documented and accepted prior to finalising any further agreement.
Attendances: it is worth reconfirming and checking attendances, as not only will there be a cost implication if there is any confusion, but also a potential impact on the programme, if the attendance items are not readily available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

common forms of security requested by employer.accrual define

A

pcg and performance bonds.n to represent the difference between the total liability assessed as owed to a subcontractor and the amount already paid to that subcontractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

how does cvr help commercially

A

CVR data allows the commercial manager to make decisions on people and equipment resource levels, construction methods, programme and preliminaries, as well as to develop
recovery strategies in terms of contractual claims or procurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

how to retain cashflor

A

Any advance, mobilisation or other pre-contract payments for contract set-up or mobilisation will improve cash flow.extend the payment terms to their supply chain.: it is certainly not best practice. RICS’ construction policy calls for prompt
payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

cost mitigation strategies

A

=consider a change of construction methodology (such as subcontract or self-deliver)
=carry out a review of material specification (for example, is masonry or steel cheaper than concrete).
=consider re-tendering subcontract and material packages, looking for economies of scale by using suppliers company-wide, rather than just per project

36
Q

cost report should always include VAT?

A

report costs but exclude VAT(value added tax). The liability to pay VAT is determined by customer VAT registration/corporate entity/nature of construction/prevailing tax rules

37
Q

define direct works and prime cost sums

A

direct= work undertaken by client
prime cost= quantities of work whose extent is known but whose specification has yet to be determined.

38
Q

what is PC

A

In commercial contracts- performance under the contract is not complete until all obligations imposed by contract have been satisfied, can include o&m’s to be provided. Normally done by Contract administrator, if contractor disagrees can go to adjudication.

39
Q

test for pc

A

de minimis principle limited test of reasonableness means pc should not be refused if there are only minor defects in the works. Neville vs william press contractor had fulfilled obligation where very minor de minimis had been carried out, but if there was patent defects the architect would not have given pc.

40
Q

why would a building control officer not give pc vs CA

A

building= due to desing issues imposed by client or design team
ca= defects in finishing trades may cause refusal of PC cert.

41
Q

why would a final account have to be settled in the middle of a project?

A

10 contractor/employer going into liquidation/administration
20 contract being terminated due to performance or other reasons in accordance with the contract by the employer
30 contract being terminated by the contractor

42
Q

risk of fluctuating prices can be dealt by

A

1) contractor to price the risk (a fixed or firm price contract)
2) allow provision for contractor to recover full or limited fluctuations on certain prices

43
Q

indices to help with pricing fluctuations

A

-tender price indices (TPI) which reflect changes in tenders submitted for similar types of work
- resource cost indices (rci) which measure changes in the cost of certain materials or labour
-output cost indices which measure the changes in contract final accounts

44
Q

define retention

A

retention is a sum deducted at each monthly payment notice to ensure the contractor returns to correct defects during defect correction period. if the contractor doesn’t return then that retention money is kept for others to correct defects

45
Q

when is retention awarded

A

portion is released upon completion of works the remainder is released when rectification period or defects liability period has expired certificate of making good awarded.

46
Q

does jct db do retention bond which jct doesnt

A

db yes but not for local authority or public . held at 3% typically. jct minor works no retention bond, retention held at 5% typically.

47
Q

where is % of retention bond written?diff between retention bond and performan bond

A

in contract particulars. performance bond provides surety for non performance rather than failure to rectify defects.

48
Q

what VAT notice works in construction?

A

to this. Information about these exceptions can be found in VAT Notice 708 (Buildings and Construction),issued by HMRC, which is continually updated.
This notice explains:
* When building work can be zero-rated or reduced rated.
* When building materials can be zero-rated or reduced-rated.
* When the sale, or long lease, in a building is zero rated.

49
Q

purpose of lads

A

The genuine purpose must be to compensate the employer rather than punish the contractor

50
Q

roles of employer contractor qs and ea

A

employer= payer
contractor- payee
employers agent- certifier
quantity surveyor= valuer

51
Q

if subcontractor lives abroad what law do you follow?

A

JCT DB Sub 2016 states that the governing law is the law of England (clause 1.10) and that the English courts have jurisdiction (article 6), although this jurisdiction is subject to any rights the parties may have to refer a dispute to adjudication or arbitration

52
Q

The types of damages that the main contractor may suffer if the subcontractor fails to complete the subcontract works on time may include:

A

=time-related damages for which the main contractor is liable to the employer under the main contract (e.g. general damages or, perhaps more often, liquidated damages)
=time-related site running/administration costs (e.g. preliminaries)
=additional time-related costs of retention being withheld under the main contract

53
Q

what happens in interview if you don’t know the answer?

A

I would check with a senior collegaue or refer to the relevant contract document or rics guidance note.
sorry i don’t know the answer today, but i know i can find out by looking

54
Q

what is LCC and what is it used for. what are the sources for this?

A

life cycle costing= carried out to predict a cash flow or carry out an option appraisal, happens during design development. LCC costs include construction costs, maintenance costs and operation costs.sources include estate managers or bcis

55
Q

what are wlc and what are these costs?

A

wlc= whole life costing= non construction costs(land acquistion fees, rental costs) or income

56
Q

ads and dis of BOQs how will bim

A

dis= they can promote a us and them mentality as the bills can only be carried out at the end of the design process and reduce the chances for contractor input. but can be argued boq production required project design to be analysed for accuracy this results in a more competent and complete set of tender information. In the future bim will assist in the production of the bill

57
Q

does two stage tendering promote collaboration?

A

for 2 stage to work it has to allow time for the contractor to sit with the design team and go through significant amount of design to show their influence. if first stage is carried out too late in the process there will not be enough design time to let contractor have an influence on design.

58
Q

dis of 2 stage tendering

A

there is the risk that contractors see a 2 stage tendering process as the opportunity to become ingrained in a project and then negotiate the price of the project higher than market value. so its important that instructions to tender make it clear what is expected from the second stage contractor.

59
Q

what happens in the 2nd stage of two stage tendering?

A

there are many ways of carrying out the second stage of the tender. it varies on the amount of contractor input thats required. if the reason for the 2 stage is a simple pricing exercise to use for a quicker start date then the contractors input on design will be minimal. on the other hand the contractor may become the lead designer and fully responsible for design and package tendering. the responsibilites should be set out in the PCSA.

60
Q

How to avoid contractor negotiating a price in second stage?

A

introduce target cost as part of the tender. this is similar to management contracting but can be applied to 2 stage tendering. where the contractor is rewarded for beating the target cost which incentivises them to work to target cost.

61
Q

how to agree contract conditions

A

its worth trying to agree contract conditions as part of the pre-qaulification questionnaire. similarly repeat clients contracts conditions may be similar to previous projects so if these can be agreed beforehand this can reduce tender analysis period.

62
Q

what impact does bim have on tendering?

A

as bim begins to extract quantities it will provide more detailed and accurate bills of quantities for tenderers to price. At level 3 promises a fully integrated and collaborative prcoess.

63
Q

in insolvency contract situation main contractor/subcontractor should consider the following

A

withhold retention monies and payments/ secure the site and make it safe/write and issue a completion final account/obtain legal advice on termination of the contract/make an inspection of site and record progress accurately

64
Q

define notional final account

A

this is an account which assess the party’s liability to the insolvent company. it may be that the as a result of the insolvency the notional final will be higher than the anticipated final account before insolvency. this is because the cost incurred by the party at the time of insolvency and will build on that cost to show the cost to complete.

65
Q

how can a surveyor help a company that is insolvent

A

may be able to assist in the administration process in recording, scheduling and valuing individual assets.

66
Q

what happens if no lads or completion date is in contract?

A

time is at large and damages cannot be deducted. if contract is left blank unliquidated damages will apply. the employer and representative will collate records and prove actual loss.

67
Q

case law for lads

A

triple point vs PTT public company supreme court confirmed that the right to liquidated damages for non completion continues until the termination of the contract, and afterwards general damages may be sought.

68
Q

how to calculate lads

A

persons calculating damages is advised to consider issues such as occupany levels, likely room charges, income from rent, utility costs. employer cannot revisit and increase level of damages.

69
Q

jct minor works vs jct db for lads

A

minor works= non completion is not required no cap for delay damages.
jct db= non completion notice must be isued as must appropriate payment notices. method of payment of damages varies but normally deducted from sums due to the contractor through a payless notice.

70
Q

what are some relevant events in jct and what clause refers to delay avoidance

A

variations/instructions/deferment of possession of the site. 2.28.6.1 the contractor is required to constantly use his best endeavours to prevent delay- sc have similar obligations. When delays occur first thing to do is always check the contract.

71
Q

good method of delay analysis

A

simple method is to compare actual progress achieved with the planned progress shown. the use of critical path analysis works well on a new build where links between programme activities are likely to reflect works being done. but less likely to work on a refurb project where delays to work in one part of an existing building may well have little or no direct impact on the rest of the building.

72
Q

how to use bim for delay assesements

A

by linking 3d model of a building to the programming software it is possible to create a model comparing planned and actual progress of works. helps to understand the consequences of a delay event.

73
Q

delay assessments must identify

A

the cause of the delay, the period of the delay, and whether the delay event will have an impact on overall completion date.

74
Q

if the valuation for a particular month is significantly lower than the cashflow forecast

A

this could be due to site conditions or adverse weather, materials being stored off site and not being claimed for. project progressing slower than anticipated

75
Q

reasons for a contractor to be ahead of cashflow

A

front end loading/being ahead of programme by working faster or by sequencing or the inclusion of variations

76
Q

risk factors on cash flow forecasting

A

circumstances can change, there could be an effect of changes in design specification (may change sequencing works) effect of inflation (value of money may be different at the time of payment to the time of production)effect of interest and exchange rate (where supplies or labourer being sourced from overseas.

77
Q

effect of VAT on cashflow forecast

A

in most cases vat is added to the invoice and paid by the employer but may then be claimed back from hmrc at a later date. the effect on the cashflow is therefore considerable as the employer will be without funds for a period of time. this may cause a dip in the cashflow near the end of the project where the vat is paid back to the employer from hmrc.

78
Q

what if no defects rectification period in contract

A

if no period is stated the default period is six months from pc of works

79
Q

breach of contract must be brought within

A

6 years from the date of the breach

80
Q

what consitutes as pc

A

in JCT pc is when works are in a state which are complete in all aspects and free from defects.

81
Q

certifying completion why is biased when you have jct

A

we had Kevin from Silva as the architect was novated over the client wanted to ensure no biased occured so had to have an impartial third party to come in and inspect

82
Q

what is DPA

A

Defective premises act, a claim under this accrues from the time when the dwelling is completed. The limitation period is 6 years.

83
Q

how else to cover costs of rectifying defects

A

latent defects insurance is increasingly available to cover the cost of rectifying defects that emerge post completion. such insurance covers defects arising from workmanship or design

84
Q

summary of limitation period for defects to be recitifed by

A

simple contract/deed/tort/dpa= from date of breach 6 years.
building safety act= 15 years from completion of the building

85
Q
A