Questions based on core concepts Flashcards
What is PV?
Planned value - planned work cost
What is EV?
Earned value - earned work cost
What is AC?
Actual cost thus far
What is BAC?
Budget at completion
When is BAC calculated?
At the beginning of a project
Was is EAC?
Estimated cost at completion
What is ETC
Estimated cost to complete
What is VAC?
Variance of cost at completion
What is the cost variance formula?
CV = EV - AC
What is the schedule variance formula?
SV = EV - PV
What is the CPI formula?
CPI = EV / AC
What is a good CPI?
CPI > 1 means under budget
What is the SPI formula?
SPI = EV / PV
What is a good SPI?
SPI > 1 means you are ahead of schedule.
Assuming the rate of spending will be the same now as it is in the future, what is the EAC formula?
EAC = BAC / CPI
Assuming from now on, the spending rate will be as it was planned in the beginning, what is the EAC formula?
EAC = AC + (BAC - EV)
Assuming from now on, future spending will be affected by both schedule and cost performances, what is the EAC formula?
EAC = AC + (BAC-EV)/(SPIxCPI)
Assuming you re-estimate the future cost from now until completion, what is the EAC formula?
EAC = AC + new estimation
If we want to complete the project with the cost equal to the budgeted cost, what formula should we use?
To complete performance index
TCPI = (BAC-EV) / (BAC - AC)
What is ETC?
Estimate to complete
What is the formula for ETC?
ETC = EAC - AC
What is the variance at completion formula?
VAC = BAC - EAC
What does it mean when an activity in a Gantt has a lead?
The work of the successor is accelerated. Example, starting the successor before the predecessor is completed.
What does it mean when an activity in a Gantt has a lag?
Successor activity is delayed.