Quantification and Costing Flashcards

1
Q

Name the 3 NRM documents?

A

NRM1 - Order of Cost Estimating and Cost Planning for Capital Building Works.

NRM2 - Detailed Measurement for Building Works.

NRM3 - Order of Cost Estimating and Cost Planning for Building Maintenance Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name the 3 RMM documents?

A

RMM1 - Order of Cost Estimating, Cost Planning and Detailed Measurement for Rail Infrastructure Works.

RMM2 - Rail Activity Based Cost Models for Rail Infrastructure Works.

RMM3 - Order of Cost Estimating, Cost Planning and Detailed Measurement for Rail Maintenance Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What’s the strucutre of NRM1?

A
  1. General
  2. Measurement rules for order of cost estimating
  3. Measurement rules for cost planning
  4. Tabulated rules of measurement for elemental cost planning

Split into 14 Group Elements

E.g. Group Element 2: Superstructure

Group Element > Element > Sub-element > Component

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s the structure of NRM2?

A
  1. General
  2. Detailed measurement of building works
  3. Rules of measurement for building works

Tables of measurement split into 41 work sections.

E.g. Work Section 7: Piling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What’s the strucutre of RMM1?

A
  1. RMM Suite of Documents in Context
  2. General
  3. Cost Estimating and Cost Planning
  4. Detailed Measurement (includes tabulated rules of measurement)

Cost Category > Group Element > Element > Sub-element > Component > Sub-component

Cost Categories:

1.0 - Direct Construction Work
2.0 - Indirect Construction Work
3.0 - Design, Project Management and Other Project Costs
4.0 - Risk
5.0 - Inflation
6.0 - Taxation and Grants

Group Element E.g. 1.03 - Electric Power and Plant.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What’s the structure of RMM2?

A
  1. RMM Suite of Documents in Context
  2. General
  3. Primary Rail Activity Cost Model.

Benchmarking process:

  1. Data Collection
  2. Data Comparison
  3. Data Analysis
  4. Action
  5. Repeat
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What benefits do standard methods of measure offer?

A

Provides a standard set of measuring rules for construction works understood across the industry.

Consistent format allows the data to be used to benchmark similar schemes.

Provides a consistent Work Breakdown Structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List the different types of cost plans and when they would be produced?

A

Order of Cost Estimate - RIBA 1

Formal Cost Plan 1 - RIBA 2

Formal Cost Plan 2 - RIBA 3

Formal Cost Plan 3 - RIBA 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What outliers did you discover on the M621 final estimate?

A
  • Length on the piles
  • Formwork quantities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What format was the cost plans you produced for Network Rail?

A

Based on the RMM Cost Plan format.

Cost captured against all the Cost Category’s.

Direct construction cost was built up from labour, plant and materials basis.

Cost from other cost categories such as possession cost and PM cost were also included in the estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What standard method of measure did you base your NR cost plans on?

A

Rail Method of Measure 1 - Order of Cost Estimating, Cost Planning and Detailed Measurement for Rail Infrastructure Works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How was contingency on the cost plans calculated?

A

Risk Analysis was conducted and benchmarked against similar historical schemes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a schedule of rates?

A

List of rates for provision of labour, plant, material or completing specific types of works.

Used to price works, such as for framework contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Explain the price reduction you achieved in assuring the subcontractor’s quote on the South UPS project?

A

Price from suppllier was £59K.

Utilising SPONS Mechnical and Electrical price book and adjuting their rates for inflation and region I calculated a rate of £28.

Rate was reduced by £32 to £26.5K

Misunderstanding as to required UPS size.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How did you go about challenging the UPS rate with the supplier?

A
  • Prepared all my calculations and backup for the price range I developed.
  • Arranged a meeting with the subcontractor’s QS.
  • Explained my position and findings and sort to work with the subcontractor’s QS collaboratively.
  • Subcontractor’s QS did some investigation and accepted my challenge and provided an updated. quote.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the pounds in the ground metric?

A

This is a metric used by NR to monitor how much of project expenditure is spent on direct construction cost v other cost categories.

RVC = Direct + Design + Prelims
IP CoE = Direct

17
Q

What was your data source for the RRV rates library?

A

NR had a large number of RRV suppliers on a framework with an agreed schedule of rates.

I brought all these schedules together into a central library with clear descriptions and easy filtering options.

18
Q

What information was included in this rates library?

A
  • Item Description
  • Supplier
  • Rate
  • Unit
  • Copy of supplier quote
  • Rate Base Date
19
Q

Surely with an organisation such as NR, a rate library already existed?

A

NR have large libraries of Unit Rate data, but the rates library I established was more granular covering cost of supply for specific materials aiding in the production of detailed cost estimates.

20
Q

What changes did you make to the template?

A

Requirement to define requirements for RRV, and then the rate for the RRV was automatically calculated based on the RRV rates library data. This meant a lump sum figure was no longer being used.

Allowances for materials had to be based on supplier quotes, or data from historical projects with adjustments.

Greater accuracy and accountability.

21
Q

What was the inflation tool you integrated?

A

Choose project start date, completion date and desired inflation index such as RPI, CPI and BCIS construction index. This automatically provided the inflation % adjustment required.

22
Q

How did the forecasting model work?

A

Forecasting based on a S - curve that:

1/3 = 1/4
2/3 = 1/2
3/3 = 1/4

23
Q

What are the benefits of a pricing document based on the standard methods of measure being included the ITT?

A
  • It saves the cost and time of several contractors measuring the same design to calculate their bids for competition.
  • It provides a consistent basis for obtaining competitive bids.
  • It provides an extensive and clear statement of the work to be executed.
  • It provides a strong basis for budgetary control and accurate cost reporting of the contract
  • When BQ items are codified, it allows reconciliation and any necessary transfers and
    adjustments to be made to the cost plan.
  • It provides one of the best sources of real-time cost data, which can be used for estimating the cost of future building projects as it provides a cost model in a single document.
24
Q

What sections will you find in a BoQ?

A
  • form of tender (including certificate of bona fide tender)
  • summary
  • preliminaries
  • measured works
  • non-measurable works
  • provisional sums
  • contractor-designed works
  • risks
  • credits (for materials arising from the works)
  • dayworks (provisional) and
  • annexes.
25
Q

What’s the structure of a cost plan?

A
  1. Facilitating Works
  2. Building Works
  3. Main Contractor’s Prelims
  4. Main Contractor’s OH&P
  5. Design Team Fees:
    - Consultant fee’s
    - Main Contractor’s pre-construction fee
    - Main Contractor’s design fee
  6. Other Project Cost
  7. Risk Allowances:
    - Employer’s Change Risk
    - Employer’s Other Risk
    - Design Development Risk
    - Construction Risk
  8. Tender Inflation
  9. Construction Inflation
  10. VAT
26
Q

What is the difference between tender inflation and construction inflation?

A

Tender inflation: the period from the estimate base date to the date of tender return.

Construction inflation: the period from the date of tender return to the mid-point of the construction period.

27
Q

What is the difference between an Activity Schedule and a Bill of Quantities?

A

AS is far less granular than a BoQ, it provides a lump sum against an activity or task.

BoQ is in far great detail providing rates, quantities and units all the way down to componenet level.

28
Q

Provide an example of how you used RMM?

A

9 Sections under Direct Construction Costs Group Element.

Examples:
- Railway Control Systems
- Electric Power and Plant
- Civil Engineering

For Cantilevers meaursed as a numerated item:

1.00 Cost Catergory - Direct Construction Cost
1.02 Group Element - Train Power Systems
1.02.02 Element - Overhead Line Equipment
1.02.02.01 Sub-element - Support Structures
1.02.02.01.03 Component - Support Structures: Single Track Cantilever
1.02.02.01.03.02 Sub-component - Cantilever