Contract Practice - Level 3 Flashcards
What delay had the contractor caused on the South UPS project?
Behind schedule in the issuing of various designs delaying the programme.
What were the key contributing factors to the two year programme slip?
A large part had occured prior to my involvement on the scheme, key factors include:
- UPS procurement delays.
- Engineering assurance resourcing issues
- Cancelled possessions delaying surveys.
- RAM instructing work to be paused to see if additoinal works could be included alongisde the UPS installation.
Orignal Completion - 31/03/2022
Final Completion - 30/06/2025
What are liquidated damages?
Geniue pre-estimate of the likely lost to be incurred for late completion.
What alternatives to liquidated damages are there?
Performance Bonds.
Incentives for timely completion.
Under NEC4 there is clause X6 which provides a bonus for early completion mechanism.
Why were liquidated damages not being used on the project?
The works were not time critical when the contract was awarded, therefore paying the premium for liquidated damages wasn’t justified.
How are liquidated damages calculated?
Prior to the formation of the contract an assessment will need to be carried out to determine cost impact for late completion.
A rate will be stated in the contract data that is payable for each day after the Completion Date until Completion is actually achieved.
What is sectional completion?
As opossed to waiting for the completion of the enitre works, the Client may split the works into sections.
This will result in multiple completion dates being written into the contract for the different sections.
This will also have an impact on liquidated damages, retention and defects period.
What is the contractual mechanism under the NR04 contract for deducting liquidated damages?
Clause 14.4 - Liquidated Damages
Practical Completion not achieved by the Completion Date.
Contractor liable to pay liquidated damages based on the rate stated in the contract order up until Completion is achieved.
What is the contractual mechanism under the NEC4 contract for deducting liquidated damages?
Liquidated Damages are refered to as delay damages under NEC and fall under clause X7.
If clause X5 for sectional completion is in place then delay damages will be split out with a rate being provided for each section.
Each day after the Completion Date where the contractor hasn’t completed the works, the PM will deduct delay damages based on the rate in the contract data from the next payment assessment, making this clear in the Payment Certificate. This continues until Practical Completion is achieved.
What did the manufactures warranty for the UPSs cover?
2 Services of the UPS within 12 months of their purchase and repair for any issues caused by manufacturing faults.
What is vesting?
Vesting is where the Title of materials or plant transfers from the contractor or supplier to the Cliet.
Transfer of title could occur when:
- Materials are paid for.
- Materials are delivered to site.
What was the vesting clause under the NR04 contract and how did it work?
Clause 7.9 - property in goods and materials.
Title transfers when materials have been incorporated into the works or the supplier has received payment.
A vesting certificate was also provided, reaffirms Network Rail’s position in relation to the title of materials and protects in case of supplier insolvency.
How do you protect materials paid for that are stored off-site?
- Ensure they are stored in a secure environment.
- Clearly marked name of the owner to protect incase of contractor insolvency.
- Insurance.
- Materials off-site bond.
What are collateral warranties?
A collateral warranty is a contract between a contractor, suppplier or consultant and an interested third party.
What is the third party rights act?
Contracts are doctrine of privity, meaning a third party to a contract can not enforce the obligations under a contract.
However, the introduction of the Rights of Third parties Act 1999 enables a third party to enforce rights of a contract based on one of the following conditions:
- Contract confers a right to the third party.
- Third party is specifically mentioned.