Quantification and Costing Flashcards
How much would it cost to lay 100m of cable in a footway (with and without duct)?
£5.5k w/ duct
£2k without
How much would it cost to lay 100m of cable in a carriageway (with and without duct)?
£12k w/ duct
£4k without
What are some of the items that would be included in a BoQ for this sort of work? (LFFN)
Ducting, cabling, chamber, coring, lateral connection, fibre splicing
enclosures and kopex, termination boxes, associated documents - method statement and TM
How did the AFP process work under LFFN?
Each site has its own BoQ and were typically finished within one day. C provides evidence of completed site and is verified by the PM in approvals which allows me to validate which costs are due.