Quantification and Costing Flashcards

1
Q

If you are producing estimates and cost plans, which measurement rules represent industry best practice?

A

New Rules of Measurment (NRM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Can you name the 3 documents in the NRM suite?

A

NRM1 - Order of cost estimating and cost planning for capital building works

NRM2 - Detailed measurement for building works

NRM3 - Order of cost estimating and cost planning for building maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Provide a brief overview of NRM1

A

Provides guidance on quantification of building works for the purpose of preparing cost estimates and cost plans.

It is the ‘cornerstone’ of good cost management of construction projects, enabling more effective and accurate cost advice to be given to clients

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Provide a brief overview of NRM2

A

Written mainly for preparing BoQ and quantified schedule of works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Provide a brief overview of NRM3

A

Guidance on quantification and description of maintenance works for the purpose of preparing initial order of cost estimates.

Rules also aid procurement and cost control of maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the structure of NRM 1

A

Part 1 - General introduction
Part 2 - Measurement rules for order of cost estimate
Part 3 - Measurement rules for cost planning
Part 4 - Tabulated rules of measurement for elemental cost planning
Appendices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the structure of NRM 2

A

Part 1 - General introduction
Part 2 - Rules for detailed measurement of building works
Part 3 - Tabulated rules of measurement for building works
Appendices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the structure of NRM 3

A

Part 1 - General Introduction

Part 2 - New rules of measurement for building maintenance works

Part 3 - Measurement rules for order of cost estimating (Renewal and maintain)

Part 4 - Measurement rules for cost planning of renewal and maintain works

Part 5 - Calculation of annualised costs for renewal and maintain works

Part 6 - Tabulated rules of measurement for elemental cost planning

Appendices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why is it important to measure the works according to industry standards and best practice?

A

To provide consistency and greater accuracy of pricing

To ensure that all parties price on the same basis and therefore reduce the risk of dispute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Is it mandatory for chartered surveyors to follow the procedures set out in NRM?

A

Not mandatory

However in case of allegation of professional negligence court likely to take account of contents of any relevant guidance notes published by RICS in deciding whether surveyor acted with reasonable competence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the key headings for contractors prelims identified in NRM2?

A

Employers Requirements

  • Site accommodation
  • Site records
  • Completion and post completion requirements

Contractor cost items

  • Management and staff
  • Site establishment
  • Temp services
  • Safety and enviro protection
  • Control and protection
  • Mechanical plant
  • Temp works
  • Site records
  • Cleaning
  • Fees and charges
  • Site services
  • Insurances / bonds/ guarantees/ warranties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How is risk dealt with under NRM?

A

Recommends that risk allowances are not a standard % but properly considered assessment of risk
- Considering completeness of design and uncertainties such as extent of site investigations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does NRM define the ‘cost limit’ of the project?

A

Cost Limit - maximum expenditure that the employer is prepared to make in relation to the completed building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can you tell me what you understand by the term benchmarking?

A

The use of historical data from projects of a similar nature

Can be used as a comparison or check for cost planning purposes

Benchmarking can highlight areas of design that are not value for money or if price offered by contractor is in line with market conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would you undertake a benchmarking exercise for your client?

A

Produce clear document which shows the various cost plan elements side by side with the benchmark project(s)

This process will identify items which are considered abnormal

Endeavour to justify cost anomalies for flagged items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a provisional sum?

A

Provisional sums generally allowance or estimate included within contract price that are;

1) Not sufficiently defined, detailed to allow accurate determination of its cost at the time contract is entered into.
2) Work employer may or may not wish to carry out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How are PS expended?

A

CA (JCT Contracts) should issue an instruction for its expenditure

Where contract includes a PS, the final amount payable will be adjusted (the PS is omitted and replaced with actual cost of the work)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How are PS dealt with in the final account?

A

By the time the project has reached its final account stage, the CA will issue instructions to expend all PS.

The instruction will show an add / omit, the instructions are then accounted for in the usual way.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How does NEC contract incorporate PS?

A
  • Unamended NEC contract do not provide for use of PS
  • NEC Approach - if scope of works is unclear and not able to provide price with level of certainty, item should be excluded until it can be properly defined.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What type of provisional sums are there?

A

Defined and Undefined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Whats a defined PS?

A

Contractor is deemed to have allowed for programme and prelims within the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is an undefined PS?

A

The contractor does not allow for planning, programming and prelims implications. This means contractor may be entitled to an EoT and or additional prelims when the actual works are undertaken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Would the contractor be entitled to claim additional prelims and or EoT when expending a defined PS?

A

No, PS is defined, contractor should have allowed for programme and prelims within their price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are Prime Cost Sums?

A

Sum of money included in a unit rate to be expended on materials or goods from suppliers e.g supply only ceramic wall tiles at £36/m2

It is a supply only rate for materials or goods where the precise quantity is unknown.

PC sums exclude all costs associated with fixing or installation, all ancillary and sundry materials and goods required for the fixing or installation of the materials or goods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is the difference between PC sums and Defined PS?

A

Prime cost is limited to cost of supplying item and does not include cost of any work that relates to it

Defined PS includes allowances for supplying item and related work to be performed by contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Can you name some of the pricing documents we might use a tender stage?

A
BoQ
Schedule of rates
CSA
Schedule of work
Priced activity
27
Q

Can you name some of the pricing options for construction contracts?

A
  • Lump Sum
  • Cost Reimbursable
  • Remeasurement
  • Target cost
  • Guaranteed Maximum Price (GMP)
28
Q

What is a lump sum contract?

A

Fixed price or lump sum provides for payment of a set amount.

The amount of the fixed price is determined by a contractor by estimating their cost to provide the work and then adding OH&P

29
Q

Advantages of lump sum contracts?

A

Contractor takes on the pricing risk but stands to benefit from increased profit if actual costs turn out to be below estimated costs

Cost certainty for employer

30
Q

disadvantages of lump sum contracts?

A

presents higher risk to contractor. If contractor underestimates their cost, the profit margin decreases and may disappear altogether

Additional risks faced by the contractor - will increase their tender price

31
Q

What is a cost plus (reimbursable) contract?

A

Involves the employer paying the contractor for the costs incurred during the project, plus a pre agreed percentage of profit.

32
Q

What are the key advantages of cost plus contracts?

A

Cost plus (Reimbursable) contracts are flexible in nature, inaccuracies in the initial bid aren’t as detrimental as they are with lump sum contracts

Allows employers to make design changes along the way, contractors know they’ll be paid for the extra time or materials which those changes incur.

33
Q

what are the disadvantages of cost plus (reimbursable) contracts?

A

Final price is uncertain until the end of the project

Contractor may deliberately incur higher costs to increase profit (no incentive for efficiency)

34
Q

When might a cost plus (reimbursable) contract be appropriate to use?

A

Where the nature or scope of work cannot be properly defined at outset

pricing strategy would suit emergency work such as infrastructure repairs or immediate reconstruction following a fire

35
Q

What is a remeasurement contract?

A

??

36
Q

Advantages of remeasurement contract?

A

Work is tendered on approx quants, the contractor will submit competitive prices in their tender

contractors risk is low compared to a lump sum

37
Q

What is a target price contract?

A

??

38
Q

Advantages of target price contract?

A

Contractor and employer are incentivised to reduce costs

encourages active and equitable risk sharing, based on clearly defined allocation of risk agreed at the outset of the project

39
Q

what are the disadvantages of target price contract?

A

Employer and contractor must share pain and gain, this exposes the employer to greater risk

Complex target price, pain/gain share may not easily be understood by all parties

40
Q

If the employer wanted a target price contract using NEC form, which main option(s) would you use?

A

Option C - Target contract with activity schedule

Option D - Target contract with Bill of Quantities

41
Q

What is guaranteed maximum price contract?

A

sets a limit that the employer will pay their contractor regardless of the actual costs incurred (i.e the contract sum will not exceed a specified max)

42
Q

What happens if the actual cost is higher than that agreed in a Guaranteed maximum price contract?

A

The contractor must bear the additional cost

43
Q

What happens if the actual cost is lower than that agreed in a Guaranteed maximum price contract?

A

The contract should set out which party will benefit from the savings. Usually, the savings will be split between the employer and contractor using a pre-agreed agreed formula or percentage

44
Q

What are the advantages of GMP?

A

Establishes employers maximum financial commitment (subject to employer variations) - If costs exceed target cost only the target cost is paid to contractor

Both the contractor and employer have potential to benefit from savings

45
Q

What are the disadvantages of GMP?

A

Contractor will have to share any savings made while taking on the risk of cost overrun.

46
Q

What are contractor preliminaries?

A

Items which cannot be allocated to a specific element

Prelims are typically items which are necessary for the contractor to complete the works but will not actually become part of the works once project is complete

47
Q

What is included within contractor prelims?

A
Management of staff
site establishment 
temp services
security
safety and environmental protection
insurances
48
Q

When assessing the costs for the contractor prelims (at tender stage) what are the key considerations to determine if they are fair and reasonable?

A
length of contract
type of project
size of project and overall build cost
need for temp works
security requirements
method and sequencing 
extent of contractor design responsibility
49
Q

Can you give me examples of contractor prelims which might be considered abnormal (over and above a standard project)

A

Tower cranes
evening and weekend working
road closures / traffic management
Closing train lines

50
Q

What is the difference between fixed and time related prelims?

A

Fixed prelims are one-off costs whereas time related prelims are dependent on duration

Time related - staff costs / plant hire
Fixed - purchasing site security equipment

51
Q

What is meant by the term ‘functional unit’

A

NRM 1 - means a unit measurement used to represent the prime use of a building. e.g. per bed space, per m2 of retail area, per house.

It includes all associated circulation space

52
Q

Can you explain what GIFA is?

A

NRM 1 - Gross Internal Floor Area

Area of a building measured to the internal face of the perimeter walls at each floor level

53
Q

Can you explain what GEA is?

A

NRM 1 - Gross External Area

Area of a building measured to the face of the external perimeter walls at each floor level

54
Q

What is wall to floor ratio?

A

Calculated by dividing the external wall area by the GIFA.

Indicates the proportion of external wall required to enclose a given floor area

May reveal how efficient a design is and may also help inform the construction cost

55
Q

What is a good wall to floor ratio?

A

?

56
Q

Can you explain what NIA is?

A

NRM 1 - Net Internal Area

The usable area within a building measured to the internal face of the perimeter walls at each floor level

57
Q

What does IMPS stand for?

A

International Property Measurement Standards

IPMS for industrial, office, residential and retail buildings have been drafted by the independent Standards Settings Committee and establishes a consistent methodology for measuring buildings around the world

58
Q

What is a Bill of Quantities?

A

A means of breaking a project down into exact quantities which are measured in an industry wide recognised format

includes all components of a building as well as prelims

Usually based on mature drawings and spec, at tender stage, the contractor inserts their cost or rate against each item

The document then forms a precise tool for pre and post contract cost control (such as managing variations)

59
Q

why would you use a bill of quants instead of a schedule of work?

A

Schedule of work break out the works sections down in less detail than a BoQ and do not contain any quantities for specific work items

BoQ simplifies the tender process because tendering contractors will be pricing the same quantities (rather than taking off quantities from drawings and spec themselves)
— Simplifies the tender analysis

60
Q

What is a schedule of work?

A

?

61
Q

What are the key advantages of using BoQ?

A

Ideal for post contract cost control
Simplified tender analysis
Very detailed and comprehensive
All the tenderers are pricing the same items and quants
Effective document for interim payments and preparing final account

62
Q

What are the key disadvantages of using BoQ?

A

Expensive and time consuming to produce

Potential for errors when measuring the project

63
Q

What are the two key types of BoQ?

A

Firm BoQ
NRM 2 - Reliability of the tender price will increase in relation to the accuracy of the quantities provided
Where there is no design changes, then a firm BoQ would provide a price at tender stage, which would equal the final cost.

Approx BoQ
NRM 2 - Used when there is insufficient detail to prepare firm BoQ or where it is decided by the employer that the time or cost of a firm BoQ is not warranted

64
Q

When would a BoQ with approx quants be used?

A

Since the quants are approx, this type of BoQ is suitable for a remeasurement form of contract