Quantification and Costing Flashcards
If you are producing estimates and cost plans, which measurement rules represent industry best practice?
New Rules of Measurment (NRM)
Can you name the 3 documents in the NRM suite?
NRM1 - Order of cost estimating and cost planning for capital building works
NRM2 - Detailed measurement for building works
NRM3 - Order of cost estimating and cost planning for building maintenance works
Provide a brief overview of NRM1
Provides guidance on quantification of building works for the purpose of preparing cost estimates and cost plans.
It is the ‘cornerstone’ of good cost management of construction projects, enabling more effective and accurate cost advice to be given to clients
Provide a brief overview of NRM2
Written mainly for preparing BoQ and quantified schedule of works
Provide a brief overview of NRM3
Guidance on quantification and description of maintenance works for the purpose of preparing initial order of cost estimates.
Rules also aid procurement and cost control of maintenance works
What is the structure of NRM 1
Part 1 - General introduction
Part 2 - Measurement rules for order of cost estimate
Part 3 - Measurement rules for cost planning
Part 4 - Tabulated rules of measurement for elemental cost planning
Appendices
What is the structure of NRM 2
Part 1 - General introduction
Part 2 - Rules for detailed measurement of building works
Part 3 - Tabulated rules of measurement for building works
Appendices
What is the structure of NRM 3
Part 1 - General Introduction
Part 2 - New rules of measurement for building maintenance works
Part 3 - Measurement rules for order of cost estimating (Renewal and maintain)
Part 4 - Measurement rules for cost planning of renewal and maintain works
Part 5 - Calculation of annualised costs for renewal and maintain works
Part 6 - Tabulated rules of measurement for elemental cost planning
Appendices
Why is it important to measure the works according to industry standards and best practice?
To provide consistency and greater accuracy of pricing
To ensure that all parties price on the same basis and therefore reduce the risk of dispute
Is it mandatory for chartered surveyors to follow the procedures set out in NRM?
Not mandatory
However in case of allegation of professional negligence court likely to take account of contents of any relevant guidance notes published by RICS in deciding whether surveyor acted with reasonable competence
What are the key headings for contractors prelims identified in NRM2?
Employers Requirements
- Site accommodation
- Site records
- Completion and post completion requirements
Contractor cost items
- Management and staff
- Site establishment
- Temp services
- Safety and enviro protection
- Control and protection
- Mechanical plant
- Temp works
- Site records
- Cleaning
- Fees and charges
- Site services
- Insurances / bonds/ guarantees/ warranties
How is risk dealt with under NRM?
Recommends that risk allowances are not a standard % but properly considered assessment of risk
- Considering completeness of design and uncertainties such as extent of site investigations
How does NRM define the ‘cost limit’ of the project?
Cost Limit - maximum expenditure that the employer is prepared to make in relation to the completed building
Can you tell me what you understand by the term benchmarking?
The use of historical data from projects of a similar nature
Can be used as a comparison or check for cost planning purposes
Benchmarking can highlight areas of design that are not value for money or if price offered by contractor is in line with market conditions
How would you undertake a benchmarking exercise for your client?
Produce clear document which shows the various cost plan elements side by side with the benchmark project(s)
This process will identify items which are considered abnormal
Endeavour to justify cost anomalies for flagged items
What is a provisional sum?
Provisional sums generally allowance or estimate included within contract price that are;
1) Not sufficiently defined, detailed to allow accurate determination of its cost at the time contract is entered into.
2) Work employer may or may not wish to carry out
How are PS expended?
CA (JCT Contracts) should issue an instruction for its expenditure
Where contract includes a PS, the final amount payable will be adjusted (the PS is omitted and replaced with actual cost of the work)
How are PS dealt with in the final account?
By the time the project has reached its final account stage, the CA will issue instructions to expend all PS.
The instruction will show an add / omit, the instructions are then accounted for in the usual way.
How does NEC contract incorporate PS?
- Unamended NEC contract do not provide for use of PS
- NEC Approach - if scope of works is unclear and not able to provide price with level of certainty, item should be excluded until it can be properly defined.
What type of provisional sums are there?
Defined and Undefined
Whats a defined PS?
Contractor is deemed to have allowed for programme and prelims within the contract
What is an undefined PS?
The contractor does not allow for planning, programming and prelims implications. This means contractor may be entitled to an EoT and or additional prelims when the actual works are undertaken
Would the contractor be entitled to claim additional prelims and or EoT when expending a defined PS?
No, PS is defined, contractor should have allowed for programme and prelims within their price
What are Prime Cost Sums?
Sum of money included in a unit rate to be expended on materials or goods from suppliers e.g supply only ceramic wall tiles at £36/m2
It is a supply only rate for materials or goods where the precise quantity is unknown.
PC sums exclude all costs associated with fixing or installation, all ancillary and sundry materials and goods required for the fixing or installation of the materials or goods
What is the difference between PC sums and Defined PS?
Prime cost is limited to cost of supplying item and does not include cost of any work that relates to it
Defined PS includes allowances for supplying item and related work to be performed by contractor