Project Finance Flashcards
What is the purpose of a cost report?
1
What would you include in a cost report?
2
What is a cash flow forecast?
financial planning tool that shows the predicted flow of cash in and out of a project. This is typically shown month by month, for the duration of works
During construction phase the cashflow projection for contractor payments will typically form a S curve
What could affect a contractor’s cash flow post-contract?
4
How would you put together a cash flow? What is it used for?
5
Talk me through how you would complete an interim valuation from receiving the contractor’s application to issuing the documents, including timescales.
6
What would you advise a Client if a Contractor’s Application for Payment was grossly different to your cash flow forecast?
7
If the contractor has submitted a valuation which is much greater than the forecast final account and the QS doesn’t issue a payment notice, what happens?
8
What are the benefits of plotting actual expenditure against predicted?
9
Why do we have a change control procedure on a project? How does the QS contribute to this?
10
In cashflow forecasting how is retention dealt with?
11
What does the term front loading mean?
12
What could it suggest if the Contractor is applying for interim valuations for far greater value than the cashflow forecast?
13
What shape would you expect a construction cashflow to follow – why
An S curve.
What should you do if a Contractor fails to submit a valuation
15
Explain the process of including Materials Off-Site within your interim application
16
What is a vesting certificate and what is this protecting against
17
What is a payment notice?
A notice to the employer to pay the contractor the amount agreed at the last valuation.
When carrying out a valuation, the previous months Payment Recommendation and Payment Notice are different, which one takes precedence?
The payment notice as this is what has been issued and paid to the contractor by the employer
What are the JCT rules for valuing a variation
20
What are dayworks? What are the risks associated with using them?
21
What is cost reporting?
A document that is produced periodically that sets out the financial position of a project
How do you communicate cost reports?
Email to the client prior to a meeting. Present in a meeting to help understanding or solve queries / questions.
Why cant you use interim valuations instead of a cost report?
Interim valuations only show expenditure to date
If a variation has been instructed but works not complete this will not show.
If works is done in phases, interim valuation may not show the full picture with regards to the cost to the client.
How do you conduct cost reporting pre contract?
Reconciliation between cost plans