Quantification and Costing Flashcards

1
Q

How would you price prelims?

A
Considering the various constraints of the project:
Access
Location
Length of contract
Type of contract
Temporary works
Services
Sectional completion
Construction methodology
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How would you price OH&P?

A

Derived from a properly considered assessment of main contractor’s overheads and profit found on previous building projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How have you priced consultant/design fees on your projects?

A

I haven’t priced consultant fees, they’ve been excluded (client request) however I would use percentage addition similar to previous projects if I had to.

Design fees - similar projects with similar design scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How have you quantified risk on your previous projects?

A

Not a standard percentage, but a properly considered assessment of the risk, taking into account the completeness of the design

Risk types:

  • Design development
  • Construction risk
  • Employer change
  • Employer other
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the full names for NRM1 and NRM2?

A

New Rules of Measurement 1: Order of cost estimating and cost planning for capital building works

New Rules of Measurement 2: Detailed measurement for building works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is NRM1 structured?

A

1 - Context & definitions

2 - Rules for preparing OCE, how to quantify non-measurable works

3- Rules for cost planning, how to quantify non-measurable works

4 - Tabulated rules of measurement

Appendices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is NRM2 structured?

A

1 - Context & definitions

2 - Rules for preparing Bill of Quants, Schedule of Rates, how to quantify non-measurable works such as risk, contractors design works

3 - Tabulated rules of measurement

Appendices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What’s the difference between a cost estimate and a cost plan?

A

Cost plan is an iterative process, updated and tracked as design progresses, to control the development of the design and ensure the client achieves value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does CESMM break down project costs?

A
Class A: general items
B: GI
C: Geotechnical and other specialist processes
D: Demolition and site clearance
E: Earthworks
F: In situ concrete
G: Concrete ancillaries
H: precast concrete
I: Pipework - pipes
J: Pipework fittings and valves
etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What’s the building works estimate?

A
1  - Substructure
2 - Superstructure
3 - Internal Finishes
4 - Fixtures, Fittings & Equipment
5 - Services
6 - Prefabricated buildings and
building units
7 - Works to existing buildings
8 - External works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What’s the works cost estimate?

A
0 - Facilitating works
1  - Substructure
2 - Superstructure
3 - Internal Finishes
4 - Fixtures, Fittings & Equipment
5 - Services
6 - Prefabricated buildings and
building units
7 - Works to existing buildings
8 - External works
9 - Main Contractor's Prelims
10 - Main Contractor's OH&P
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What’s the cost limit?

A
0 - Facilitating works
1  - Substructure
2 - Superstructure
3 - Internal Finishes
4 - Fixtures, Fittings & Equipment
5 - Services
6 - Prefabricated buildings and
building units
7 - Works to existing buildings
8 - External works
9 - Main Contractor's Prelims
10 - Main Contractor's OH&P
11 - Project/design team fees
12 - Other project/development costs
13 - Risk allowances
14 - Inflation
CAN BE INCL OR EXCL INFLATION
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define NIA

A

The usable area within a building measured to the internal face of the perimeter walls at each floor
leve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define GEA

A

The area of a building measured externally at each floor level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define GIA

A

The area of a building measured to the internal face of the perimeter walls at each floor level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What’s a cost/ft2 for a strip out of a London office?

A

C. £7/sqft London office based on experience, not too cellularised

Can vary depending on factors such as cellularisation, access to building etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What would you expect for a cost/sqft London office fit-out shell to cat a?

A

c. £45 - 55 sqft for high end office London

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Cost/ft2 for a 2-bed resi unit in central London?

A

CHECK - NOT MY SPECIALITY - £250K?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What’s BCIS?

A

Building Cost Information Services - Cost and price information is collected by BCIS from across the UK construction industry, then collated, analysed, modelled, interpreted and made available to the industry to facilitate accurate cost planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Where would you get rates from?

A

BCIS, historic in house data, SPONs, build up rates, market test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the RIBA stages?

A
0 - Strategic definition 
1 - Preparation and brief
2 - Concept design
3 - Developed design
4 - Technical design
5 - Construction
6 - Handover and close out
7 - In use
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What purpose does the RIBA PoW 2013 serve?

A
  • Splits project into key project stages w/ defined outcomes
  • Shared framework for design and construction
  • Offers both a process map and a management tool.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How would you go about market testing?

A
  • Hide name of project/client
  • Speak to supplier, give quants, drawings if necessary, get price for materials
  • Speak to subcontractor, give quants, drawings if necessary, get price for labour

GET PARTIES TO SIGN NON-DISCOUSURE AGREEMENT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What’s a non-disclosure agreement?

A

A legal contract between at least two parties that outlines confidential material, knowledge, or information that the parties wish to share with one another for certain purposes, but wish to restrict access to or by third parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the advantages of market testing?

A

Current day cost for works, bespoke to the projects actual requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What are the different waterproofing grades?

A

Grade 1 – Some water seepage and damp is tolerable depending on the intended use. Car parks etc.

Grade 2 – No water penetration is acceptable, some damp is okay. Garages, workshops etc

Grade 3 – No dampness or water penetration is acceptable – Ventilated residential / commercial spaces e.g. apartments and offices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What’s the difference between waterproofing grades and types?

A

Grades = 1 - 3, required level of waterproofing

Type = A - C, method of waterproofing

28
Q

What are the waterproofing types?

A

Type A - “barrier protection” or basement tanking, layer of waterproof concrete. Good for grade 1 level protection

Type B - The structure itself being an integral water resistant shell. A build of reinforced concrete supplemented with a method of controlling water ingress at construction joints (such as a hydrophilic waterbar). Good for grade 2.

Type C - The structure itself provides the initial resistance against water ingress but also incorporates a drained cavity within the basement structure. Drainage system to collect groundwater ingress through the structure and direct it to drains or a sump pump for removal. Good for grade 3.

29
Q

What are the component measures for pile foundations? Incl unit.

A

Piling mat - m2

Piling plant - item

Moving piling rig into position - nr

Piles - unspecified

EO for piling casing - unspecified

Disposal for excavated arisings - m3

EO for breaking through obstructions - nr/m3

Cutting off piling tops - nr

Pile tests - item

Pile caps, ground beams also required

30
Q

What are some of the rules for measuring piles?

A
  • No allowance for bulk (re - material excavated)
  • Linear length of piles etc. taken from CL
  • Curved works are described and stated separately
  • Significant sub-components are to be stated separately (m2, m, nr)
31
Q

What’s excluded from pile measurements (NRM1)?

A
  • Dewatering

- Soil stabalisation

32
Q

What are the component measures for pad foundations? Incl unit.

A

Pad foundations; size & reinforcement - item

EO for disposal of contaminated material to be stated - m3

33
Q

What would you consider when chosing a foundation type?

A
  • Surrounding buildings
  • Requirements for noise restrictions
  • Soil bearing capacity
34
Q

What are the different functional units you could use to estimate the cost of a building?

A

Cost/bed

Cost/pupil

Cost/key

35
Q

What’s the difference between contiguous and secant piling?

A

Secant piles overlap, contiguous leave a gap between each pile which is filled

36
Q

What are the component measures for a steel frame? Incl unit.

A
  • Steel (t)
  • Fittings and fixings (t)
  • Fire protection (t)
  • Paint (t)
37
Q

What is included in steel frame?

A
  • Structural beams, columns, bracing
  • Roof trusses where integral to frame
  • Fire protection
  • Paint
  • Fixtures and fixings
  • Sundries, subby prelims
38
Q

What is excluded in steel frame?

A
  • Secondary steel frames (incl in specialist frames)
  • Lintels
  • Anything that can be separated from the frame (roof, floor beams)
  • Upper floors
39
Q

What are the component measures for a concrete frame? Incl unit.

A

Columns; grade, reinforcement, nr, finish - lm (BUT BREAK OUT INTO COMPONENTS BELOW TOTAL LM)

Beams; grade, reinforcement, nr, formwork finish - lm

Walls; grade, reinforcement, formwork finish - m2

EO for doors/openings to walls - nr

Designed joints; details to be stated - m

40
Q

What’s included/excluded?

A

Incl - everything, concrete, formwork, reinforcement, grouting, finish,

Excl - upper floors, roof slab

41
Q

How would you value a variation?

A

Use contract rates if possible. If not, try to build up cost using contract rates.

If not, agree a reasonable rate with contractor using BCIS, historic data, SPONs

42
Q

What is a CSA?

A

Contract Sum Analysis - breakdown of the contractors tender sum/contract sum in a DB project

Used by QS to compare/analyse tenders, and basis for payments due to contractor post contract

43
Q

What’s the contract sum?

A

The price agreed with the contractor. Stated in the contract.

44
Q

Why was there a GIA limit on your school project in West London?

A

Schools are bound to max areas based on Building Bulletin 103: Area Guidelines for Mainstream Schools

Based on pupil count/school usage

45
Q

How else might you advise to reduce the GIA?

A
  • Make internal spaces external by taking roof off/making open sided with canopy covers
  • Make cycle stores external
  • Put plant on roof
46
Q

What’s the full name for NRM3?

A

New Rules of Measurement - Order of cost estimating and cost planning for building maintenance works

47
Q

What are the valuation rules?

A

Rules for valuing change in a contract

Different rules in different contracts

48
Q

What are the valuation rules in NEC?

A

The effect of the CE upon the:

  • Actual defined cost of the work already done
  • the forecast defined cost of the work not yet done and
  • the resulting fee

Defined cost is defined as the cost of the components in the SSCC/SCC whether the work is subcontracted or not, excluding the cost of preparing quotations.

SSCC includes cost components for
People
Equipment
Plant and Materials
Charges
Manufacture
Design
Insurance
49
Q

What are the valuation rules in JCT IC 2016?

A
  • rates/prices in Contract Documents used where possible
  • Fair allowance will be made if method of works differs to above, based on rates in contract docs
  • Measurement shall be governed by same principles governing preparation of Contract Bills
  • Allowances for percentages or lump sum adjustment
  • Where there is no comparable work, works shall be valued at fair rates and prices
  • Quantity will be determined by approximate quantity if reasonable
  • Omissions will be omitted on the basis of rates and quants in Contract Documents
  • Daywork used to value works not in Contract Docs
50
Q

How do you value CDP?

A
  • Similar to valued in CDP Analysis + allowances for change in conditions under which work is carried out and/or significant change in quantity
  • If there is no similar work in CDP, a fair valuation will be made
51
Q

What are dayworks?

A

a means by which a contractor is paid for specifically instructed work on the basis of the cost of labour, materials and plant plus a mark up for overheads and profit.

52
Q

What do you need to write a cost plan?

A
  • Location
  • Function
  • Area/Drawings
  • Time start on site
53
Q

What do you need to write a cost plan?

A
  • Location
  • Function
  • Area/Drawings
  • Time start on site
  • Quality
54
Q

What is a defined PSUM?

A

A sum provided for work which is not completely designed but for which the following information shall be provided:
– the nature and construction of the work;
– a statement of how and where the work is fixed to the building and what other work is to be fixed thereto;
– a quantity or quantities that indicate the scope and extent of the work; and
– any specific limitations and the like identified

55
Q

What is an undefined PSUM?

A

A sum provided for work that is not completely designed, but for which the information required for a defined provisional sum cannot be provided

56
Q

What is a PSUM?

A

A sum of money set aside to carry out work that cannot be described and given in quantified items in accordance with the tabulated rules of measurement

57
Q

Where are PSUMS defined?

A

NRM2

58
Q

What were the risk allowances on your project in Central London?

A

Reviewed at every stage

Stage 1 - 5% design dev, 2.5% construction, 2.5% client change/other

PTE - Same, but design dev 0%

59
Q

What were the risk allowances on your project in South London?

A

Stage 1 - 7.5% “design reserve and contingency”

60
Q

What would you expect the construction risk to be on new build vs refurb?

A

New build if the site has been cleared will generally be lower risk. No danger of damage/disrupting existing buildings etc.

61
Q

What would you use BCIS for?

A
  • Tender Price Indices
  • Benchmarking
  • Cost estimating
62
Q

What are prime costs?

A

Never used them but:

  • Client will negotiate/agree price with a supplier/subbie before MC appointed
  • MC will include cost of supplier in their Tender Sum as a Prime Cost
  • PC will be replaced with cost incurred by supplier + MC OHP/prelims
63
Q

List items that would be included in prelims.

A
  • Site accommodation
  • Management and staff
  • Site establishment
  • Security
  • Temporary services (scaffolding)
  • Insurance, bonds, guarantees and warranties

Detailed list available in part 4 of NRM1

64
Q

How would you advise on the future inflation costs for a project?

A

Use in house Tender Price Index forecast or BCIS

65
Q

How would you test prelims?

A

Divide allowance by programme, look at rate per week and compare that to benchmarks.

£80m project, £70k - £85K per week

66
Q

How is reinforcement measured in NRM?

A

tonnes