Banana Skins Flashcards

1
Q

What is acceleration?

A

the process of speeding up the work of a contractor so that a particular activity, or the project as a whole, can be completed before the date required under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why might you use acceleration on a project?

A
  • Client wants site to be handed over or wants EoT to be reduced
  • If the contractor wants to move onto another project
  • If the contractor wants to mitigate inefficiencies and delays
  • If the contractor believes they can save costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can the contractor claim costs from the client for acceleration?

A

Only if it’s “direct acceleration”, aka client driven

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What techniques could be used for acceleration?

A
  • Working overtime.
  • Adding new shifts.
  • Providing additional labour.
  • Additional supervision.
  • Providing additional resources, such as plant and equipment.
  • Re-sequencing work activities (also known as project crashing or fast tracking).
  • Adopting alternative construction methods, such as off-site manufacturing.
  • Changing the design or specification.
  • Reducing the scope of the works (for example ransferring responsibility for some works from the contractor to the client)
  • Early procurement of key items.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is loss and expense?

A

Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can contractors claim for consequential loss?

A

No - only direct loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What’s the difference between loss and expense and prolongation?

A

Loss and expensive - wider term referring to matters client is responsible for, materially affecting the progress of works. This includes matters that disrupt rather than delay the work - causing contractor to adopt inefficient work styles

Prolongation - an element of loss and expense. Prolongation costs are the additional costs that a contractor has incurred as a result of the completion of the works being delayed by an event that is the responsibility of the other party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the procedures/timeline for loss and expense claims?

A
  • Contractor must notify client as soon as it becomes reasonably apparent
  • In NEC, PM has the period for reply identified in the Contract Data to reply.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What’s an EoT?

A

Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor’s fault. (EoT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What’s the EoT timeline?

A
  • Contractor gives notice (letter)
  • CA assesses and accepts/rejects
  • If approved, CA writes letter and issues a change order

Some contracts require contractor to request a specific time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What must a contractor put in an EoT letter?

A
  • Identify the relevant event causing delay
  • EoT required
  • Reasons
  • Referencing contract clauses relevant
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What would you do if client wanted to use bespoke contract?

A
  • Advise on benefits of standard form: everybody is familiar of the clauses, less likelihood of disputes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How did you assess the budget when taking over the project?

A

Benchmarked it against other projects, first had indication of concern re basement

Very early on we started working on the OCE though, to establish a robust budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What unit is used to measure embodied carbon?

A

kg/CO2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What unit is used to measure U value?

A

W/m²K

k = conductivity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What’s the difference between a PTE and a Cost Plan?

A

PTE will mirror what we expect in the tender return

Excludes things like client contingencies, professional fees

17
Q

What’s the gearing ratio?

A

Measurement of the entity’s financial leverage

Equity vs Borrowing

18
Q

What are the 3 pillars of dispute resolution?

A

Negotiation; 2 Mediation (or third party intervention); and 3 Adjudication/ Arbitration/ Litigation

19
Q

What’s the difference between facilitative and evaluative mediation?

A

Facilitation = tries to open negotiation between parties and explore option. No opinion.

Evaluation = mediator gives a recommendation for outcome

20
Q

What court would you hear litigation for a construction case?

A

Technology and Construction Court

21
Q

Is adjudication binding?

A

Yes unless and until they are revised by arbitration or litigation

22
Q

Do CDM regs apply to non-notifiable projects?

A

Yes - CDM still applies to non-notifiable projects.

23
Q

What’s the difference between cost and value?

A

value = what client pays

Cost = cost incurred by contractor

Difference = profit

24
Q

What are the phases of VE?

A
  • Sit with DT, traffic light scope for VE
  • DT prepare proposals
  • We price proposals
  • Client chooses to accept/reject
25
Q

What is change control?

A

The administrative process for implementing the contractual mechanism for instructing changes

26
Q

What soils would you generally find in London?

A

London Clay, Harwich

  • Lambeth Group (the Upnor, the Woolwich and the Reading. Sands, silts, clays and gravels)
  • Thanet Sands

^ From top layer down

27
Q

What does NEC stand for?

A

New Engineering Contract

28
Q

Who creates the NEC?

A

Thomas Telford Ltd, Commercial arm of the ICE

29
Q

When is the Due Date in NEC3?

A

PM certifies payments within 7 days of assessment date.

30
Q

Who is responsible for errors in the ERs and CPs?

A

Generally, the responsibility lies with the person that has formed the documents, but must check Contract amendments

31
Q

What is the process following the identification of a discrepancy in the WI?

A

Contractor notified the PM under clause 17.1 of the ambiguity/inconsistency. PM issues an instruction to resolve it.

This instruction constitutes a CE under clause 60.1(1).

32
Q

What are some of the reasons that a PM may reject a CE?

A

He decides that the event:

  • Arises from the fault of the contractor;
  • has not happened and is not expected to happen;
  • has no effect upon defined cost, completion or meeting a key date;
  • is not one of the CE’s stated in the contract
33
Q

If a tender return is received late, would you accept it?

A

For public projects, no. For private projects, clients must be advised which tenders were late and provide instruction to consider them if they wish.

34
Q

What is the process for reviewing tenders?

A

Check for errors and conflicts
Raise tender queries and conflicts in information
Equalise/normalise the rates and prices - ensure a like-for-like comparison

35
Q

What would be included in a tender report?

A

Equalisation of the tenders
Addition of any other costs necessary to show a full cost estimate (to cover any gaps in the tender not resolved through interviews)
Quantitative and qualitative assessments of the tenders
Recommendation of award

36
Q

What are some criticisms of NEC?

A

Too process driven
Requires specific expertise to operate effectively
Generates too much paperwork
Focus on the accepted programme which can create issues when forecasting time in compensation events

37
Q

How much would it cost to construct a capping beam?

A
Pour concrete = £30 - 40/m3
Fix steel = £400 - 600/t
Formwork = £50 - 75/m2
Concrete material = £90-100/m3 (C40/50)
Reinforcement = £500-600/t
38
Q

Piling costs

A

Bored concrete = £1k+ depending on diameter and depth

Sheet piles = £300ish/m2 incl materials depending on depth. £700/t for materials