Procurement and Tendering Flashcards
What would you include when issuing a PQQ?
Enquiry letter
Project information schedule
Pre-qualification questionnaire:
- Company details (including legal status).
- Details of insurance cover.
- Financial information (such as recent accounts).
- Relevant experience.
- Information about technical and professional ability.
- Information about capability and capacity.
- Health and safety policy.
- Quality assurance policy.
- Environmental management policy.
- Equal opportunities policy.
- Relevant references.
How is a project structured and delivered in terms of risk allocation and contractual relationships?
Client may be better suited to taking more risk and exposed through more contractual relationships, responsibilities.
Less experienced client that wants to minimise risk may opt for a design and build procurement route, whereby they have a single point of responsibility. The design, programme etc is all taken on my the contractor.
What are the pros/cons of the traditional procurement route?
Advantages:
- Quality of product is generally higher
- Client maintains control of design
- Post-contract changes easy to manage
Disadvantages:
- Longer project duration due to sequential phasing, no overlaps
- Buildability can be poor due to no Contractor involvement
- Design open to abuse
What are the advantages and disadvantages of the D&B procurement route?
Advantages
- Low cost risk as client pays lump sum for Contract, absorbing design/construction risk. Contract Sum will be inclusive of a %age fee to cover design development/risk
- Low time risk: due to the ability to begin construction before design has been completed means this is a fast track procurement route.
- Cost certainty, if a lump sum contract, known early on in the project timeline.
- Early contractor involvement generally is good for buildability
- Single point of responsibility for the client
Disadvantages
- High design risk. Client loses control over design. Contractors will aim to meet ER’s whilst maximising their margins
- Post-contract changes difficult to manage and often are expensive
What are the advantages and disadvantages of management contracting?
Advantages
- Fast track procurement option as early packages can be let whilst later packages are still being designed
- Client maintains design control
- Late changes accommodated so long as that package hasn’t been let
- Good buildability with early appointment of MC
Disadvantages
- MC is paid on a fee basis and doesn’t take project cost risk, leaving the client exposed
- Although procurement is fast, time certainty is poor until the final package is let
- Cost certainty is also poor until the final package is let.
What are the advantages and disadvantages of the construction management route?
Advantages
- Fast track procurement route as design and construction can overlap
- Arguably a cheaper price is obtainable due to cutting out the main contractor’s OH&P costs.
- Accommodates late changes if the package has not been let
- Client maintains design control
- Good buildability with early involvement of Construction Manager
Disadvantages
- Client must be experienced as all parties report to them.
- Time certainty is not known until last package is let
- Construction Manager may not be motivated by cost as he is appointed on a fee basis, resulting in high project cost
Why would you use management contracting over construction management or DB?
You may want reduced exposure/risk than construction management, so opt for management contracating so management contractor acts as buffer between subcontractors and client
You may wish to retain control over design. DB would see design responsibility passing on to contractor.
Which is most risk averse procurement route?
Traditional is very safe/balanced for client, especially w/ BoQ.
Turnkey project is also low risk for client in terms of responsibility, cost and time however only suitable for off-the-shelf products
What contract type would you use for traditional procurement route? (JCT TPN)
Lump Sum
Measurement Contract
Cost reimbursement
What contract would you use for DB procurement route? (JCT TPN)
- Turnkey
- Design and Build
- Contractors design portion in traditional contract
What contract would you use for management procurement route? (JCT TPN)
- Management contract
- Construction manager contract
- Design-Manage-Construct
What methods are there of calculating the contract sum?
- Lump Sum
- (Re-)Measurement (approx quantity contracts)
- Target Cost
- Guaranteed Maximum Price
What is procurement?
The act of obtaining goods or services from an external source
What is tendering?
Tendering is part of the procurement process
It is where a contractor is appointed to the project and a price for the works is obtained
Why would you use two-stage tendering?
- If there is not enough information to obtain a tender price for the works
- To overlap tendering with design period
- To utilise contractor in design period to add buildability
Why does OJEU exist?
EU Procurement Directives established public procurement rules through EU.
Public procurement rules enacted in UK through PC Regulations
What was the purpose of the EU Procurement Directives/OJEU?
Open up public procurement within the European Union and to ensure the free movement of supplies, services and works.
What are the tender options using OJEU?
Open
Restricted (w/ PQQ)
Competitive dialogue
Competitive negotiation
What is competitive dialogue?
PQQ > invited to open dialogue in which solutions developed > at end of process, final number of contractors are invited to tender
What is competitive negotiation?
PQQ > Negotiation > preferred bidder selection.
No formal rules or ending. Preferred bidder can be negotiated with post-appointment.
What are the OJEU value bands?
For Works contracts:
Central Govt + Other Contracting Authorities - £4.7m
Small Lots - £884k
For other contracts it is less.
How long does the OJEU tender process take?
Open Tender 35 days, 30 if electronic submission, 15 if PIN
Describe the tendering method on a project you have worked on (activities, timescales).
[respond with your own answer!]
Mine:
- Construction Framework
- Used medium band (4.5m - 12m
- Competition, 2 stage, DB, JCT DB Contract
- Regional lot London
- ITT = 3 weeks (incl site visit 2.5 weeks prior to deadline)
- Evaluation and appointment = 3 weeks; 60% quality 40% price
- Design development = 6 weeks
PCSA milestone 1 = 50% dd complete
PCSA milestone 2 = 50% dd complete
- Design development gateway = 2 weeks
- Planning submission = 4-5 weeks
- CPs = 8 - 10 weeks
- CP review 7-8 weeks (too much longer)
- Contract finalisation = 3 weeks
How long overall does the DfE Construction Framework tender process take for DB 2-stage? [only relevant if you’ve worked on schools]
Circa 45 weeks.