Project Time Management Flashcards

2
Q

[…] Management includes the processes required to accomplish timely completion of the project.

A

Project Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

_____________ is the cost estimating technique used most frequently in the early stages of a project.

A

analogous estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Control Schedule is the process of monitoring the […] of the project to update project progress and managing changes to the schedule baseline.

A

status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Control Schedule is the process of monitoring the status of the project to […] project progress and managing changes to the schedule baseline.

A

update

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Control Schedule is the process of monitoring the status of the project to update […] and managing changes to the schedule baseline.

A

project progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Control Schedule is the process of monitoring the status of the project to update project progress and managing […] to the schedule baseline.

A

changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Control Schedule is the process of monitoring the status of the project to update project progress and managing changes to the […] baseline.

A

schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Control Schedule is the process of monitoring the status of the project to update project progress and managing changes to the […].

A

schedule baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Control Schedule is the process of monitoring the status of the project to update project progress and managing changes to the schedule […].

A

baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define Activities is the process of […] the specific actions to be performed to produce the project deliverables.

A

identifying

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Define Activities is the process of identifying the specific […] to be performed to produce the project deliverables.

A

actions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define Activities is the process of identifying the specific actions to be performed to produce the project […].

A

deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Develop Schedule is the process of […] activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.

A

analyzing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Develop Schedule is the process of analyzing […] sequences, durations, resource requirements, and schedule constraints to create the project schedule.

A

activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Develop Schedule is the process of analyzing activity […], durations, resource requirements, and schedule constraints to create the project schedule.

A

sequences

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Develop Schedule is the process of analyzing activity sequences, […], resource requirements, and schedule constraints to create the project schedule.

18
Q

Develop Schedule is the process of analyzing activity sequences, durations, […], and schedule constraints to create the project schedule.

A

resource requirements

19
Q

Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and […] to create the project schedule.

A

schedule constraints

20
Q

Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project […].

21
Q

Estimate Activity Durations is the process of […] the number of work periods needed to complete individual activities with estimated resources.

A

approximating

22
Q

Estimate Activity Durations is the process of approximating the […] of work periods needed to complete individual activities with estimated resources.

23
Q

Estimate Activity Durations is the process of approximating the number of […] needed to complete individual activities with estimated resources.

A

work periods

24
Q

Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual […] with estimated resources.

A

activities

25
Q

Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual activities with […] resources.

26
Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual activities with estimated [...].
resources
27
Estimate Activity Resources is the process of estimating the [...] and quantities of material, people, equipment, or supplies required to perform each activity.
type
28
Estimate Activity Resources is the process of estimating the type and [...] of material, people, equipment, or supplies required to perform each activity.
quantities
29
Estimate Activity Resources is the process of estimating the type and quantities of [...], people, equipment, or supplies required to perform each activity.
material
30
Estimate Activity Resources is the process of estimating the type and quantities of material, [...], equipment, or supplies required to perform each activity.
people
31
Estimate Activity Resources is the process of estimating the type and quantities of material, people, [...], or supplies required to perform each activity.
equipment
32
Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or [...] required to perform each activity.
supplies
33
Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each [...].
activity
34
Project Time Management includes the processes required to [...] timely completion of the project.
accomplish
35
Project Time Management includes the processes required to accomplish [...] completion of the project.
timely
36
Project Time Management includes the processes required to accomplish timely [...] of the project.
completion
37
Sequence Activities is the process of [...] and documenting relationships among the project activities.
identifying
38
Sequence Activities is the process of identifying and [...] relationships among the project activities.
documenting
39
Sequence Activities is the process of identifying and documenting [...] among the project activities.
relationships
40
Sequence Activities is the process of identifying and documenting relationships among the project [...].
activities