Project Time Management Flashcards

2
Q

[…] Management includes the processes required to accomplish timely completion of the project.

A

Project Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

_____________ is the cost estimating technique used most frequently in the early stages of a project.

A

analogous estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Control Schedule is the process of monitoring the […] of the project to update project progress and managing changes to the schedule baseline.

A

status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Control Schedule is the process of monitoring the status of the project to […] project progress and managing changes to the schedule baseline.

A

update

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Control Schedule is the process of monitoring the status of the project to update […] and managing changes to the schedule baseline.

A

project progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Control Schedule is the process of monitoring the status of the project to update project progress and managing […] to the schedule baseline.

A

changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Control Schedule is the process of monitoring the status of the project to update project progress and managing changes to the […] baseline.

A

schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Control Schedule is the process of monitoring the status of the project to update project progress and managing changes to the […].

A

schedule baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Control Schedule is the process of monitoring the status of the project to update project progress and managing changes to the schedule […].

A

baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define Activities is the process of […] the specific actions to be performed to produce the project deliverables.

A

identifying

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Define Activities is the process of identifying the specific […] to be performed to produce the project deliverables.

A

actions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define Activities is the process of identifying the specific actions to be performed to produce the project […].

A

deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Develop Schedule is the process of […] activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.

A

analyzing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Develop Schedule is the process of analyzing […] sequences, durations, resource requirements, and schedule constraints to create the project schedule.

A

activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Develop Schedule is the process of analyzing activity […], durations, resource requirements, and schedule constraints to create the project schedule.

A

sequences

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Develop Schedule is the process of analyzing activity sequences, […], resource requirements, and schedule constraints to create the project schedule.

A

durations

18
Q

Develop Schedule is the process of analyzing activity sequences, durations, […], and schedule constraints to create the project schedule.

A

resource requirements

19
Q

Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and […] to create the project schedule.

A

schedule constraints

20
Q

Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project […].

A

schedule

21
Q

Estimate Activity Durations is the process of […] the number of work periods needed to complete individual activities with estimated resources.

A

approximating

22
Q

Estimate Activity Durations is the process of approximating the […] of work periods needed to complete individual activities with estimated resources.

A

number

23
Q

Estimate Activity Durations is the process of approximating the number of […] needed to complete individual activities with estimated resources.

A

work periods

24
Q

Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual […] with estimated resources.

A

activities

25
Q

Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual activities with […] resources.

A

estimated

26
Q

Estimate Activity Durations is the process of approximating the number of work periods needed to complete individual activities with estimated […].

A

resources

27
Q

Estimate Activity Resources is the process of estimating the […] and quantities of material, people, equipment, or supplies required to perform each activity.

A

type

28
Q

Estimate Activity Resources is the process of estimating the type and […] of material, people, equipment, or supplies required to perform each activity.

A

quantities

29
Q

Estimate Activity Resources is the process of estimating the type and quantities of […], people, equipment, or supplies required to perform each activity.

A

material

30
Q

Estimate Activity Resources is the process of estimating the type and quantities of material, […], equipment, or supplies required to perform each activity.

A

people

31
Q

Estimate Activity Resources is the process of estimating the type and quantities of material, people, […], or supplies required to perform each activity.

A

equipment

32
Q

Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or […] required to perform each activity.

A

supplies

33
Q

Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each […].

A

activity

34
Q

Project Time Management includes the processes required to […] timely completion of the project.

A

accomplish

35
Q

Project Time Management includes the processes required to accomplish […] completion of the project.

A

timely

36
Q

Project Time Management includes the processes required to accomplish timely […] of the project.

A

completion

37
Q

Sequence Activities is the process of […] and documenting relationships among the project activities.

A

identifying

38
Q

Sequence Activities is the process of identifying and […] relationships among the project activities.

A

documenting

39
Q

Sequence Activities is the process of identifying and documenting […] among the project activities.

A

relationships

40
Q

Sequence Activities is the process of identifying and documenting relationships among the project […].

A

activities