Math Flashcards

1
Q

AC is an acronym for…

A

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV is an acronym for…

A

Planned Value &/or Present Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

BAC is an acronym for…

A

Budget At Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

EV is an acronym for…

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV is an acronym for…

A

Cost Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV is an acronym for…

A

Schedule Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI is an acronym for…

A

Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI is an acronym for…

A

Schedule Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC is an acronym for…

A

Estimate At Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC is an acronym for…

A

Estimate To Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC is an acronym for…

A

Variance At Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI is an acronym for…

A

To Complete Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EMV is an acronym for…

A

Expected Monetary Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

FV is an acronym for…

A

Future Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

PERT is an acronym for…

A

Program Evalation And Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

AC =

A

CV / (CPI - 1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

PV =

A

SV / (SPI - 1)

18
Q

BAC =

A

Σ(PV) at project completion

19
Q

EV =

A

% complete at BAC

20
Q

CV =

A

EV - AC (>0)

21
Q

SV =

A

EV - PV (>0)

22
Q

CPI =

A

EV / AC (>1)

23
Q

SPI =

A

EV / PV (>1)

24
Q

EAC =

A

AC / % Complete or BAC / CPI

25
Q

ETC =

A

EAC - AC

26
Q

VAC =

A

BAC - EAC

27
Q

TCPI =

A

Remaining Work / Remaining Budget OR (BAC - EV) / (BAC - AC) or (BAC - EV) / (EAC - AC)

28
Q

EMV =

A

Impact x Probability

29
Q

Qualitative Risk Score =

A

Probability x (Scope + Time + Cost + Quality)

30
Q

Communication Channels =

A

N x (N - 1) / 2

31
Q

1σ =

A

68.26%

32
Q

2σ =

A

95.46%

33
Q

3σ =

A

99.73%

34
Q

6σ =

A

99.999%

35
Q

PV =

A

FV / (1 + r)^n

36
Q

PERT =

A

(O + 4M + P) / 6, where O is Optimistic, P is Pessimistic, M is Most Likely

37
Q

SD of Activity (σ) =

A

(P - O) / 6

38
Q

Variance of Activity =

A

(SD)^2

39
Q

Float =

A

LS - ES = LF - EF, where LS is Late Start, LF is Late Finish, ES is Early Start, and EF is Early Finish

40
Q

EVM is an acronym for…

A

Earned Value Management