Q

[…] is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

A

Determine Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

[…] is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.

A

Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

[…] is the process of approximating the number of work periods needed to complete individual activities with estimated resources.

A

Estimate Activity Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

[…] is the process of defining and documenting stakeholders? needs to meet the project objectives.

A

Collect Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

[…] is the process of defining how to conduct risk management activities for a project.

A

Plan Risk Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

[…] is the process of determining project stakeholder information needs and defining a communication approach.

A

Plan Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

[…] is the process of determining which risks may affect the project and documenting their characteristics.

A

Identify Risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

[…] is the process of developing a detailed description of the project and product.

A

Define Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

[…] is the process of developing an approximation of the monetary resources needed to complete project activities.

A

Estimate Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

[…] is the process of developing options and actions to enhance opportunities and to reduce threats to project objectives.

A

Plan Risk Responses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

[…] is the process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers.

A

Plan Procurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

[…] is the process of documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans.

A

Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

[…] is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity.

A

Estimate Activity Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

[…] is the process of identifying and documenting project roles, responsibilities and required skills, reporting relationships, and creating a staffing management plan.

A

Develop Human Resource Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

[…] is the process of identifying and documenting relationships among the project activities.

A

Sequence Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

[…] is the process of identifying quality requirements and/or standards for the project and product, and documenting how the project will demonstrate compliance.

A

Plan Quality

18
Q

[…] is the process of identifying the specific actions to be performed to produce the project deliverables.

A

Define Activities

19
Q

[…] is the process of numerically analyzing the effect of identified risks on overall project objectives.

A

Perform Quantitative Risk Analysis

20
Q

[…] is the process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.

A

Perform Qualitative Risk Analysis

21
Q

[…] is the process of subdividing project deliverables and project work into smaller, more manageable components.

A

Create Work Breakdown Structure

22
Q

[…] Process Group: Those processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.

A

Planning

23
Q

Planning Process Group: Those processes required to […] the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.

A

establish

24
Q

Planning Process Group: Those processes required to establish the […] of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.

A

scope

25
Q

Planning Process Group: Those processes required to establish the scope of the project, […] the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.

A

refine

26
Q

Planning Process Group: Those processes required to establish the scope of the project, refine the […], and define the course of action required to attain the objectives that the project was undertaken to achieve.

A

objectives

27
Q

Planning Process Group: Those processes required to establish the scope of the project, refine the objectives, and […] the course of action required to attain the objectives that the project was undertaken to achieve.

A

define

28
Q

Planning Process Group: Those processes required to establish the scope of the project, refine the objectives, and define the […] required to attain the objectives that the project was undertaken to achieve.

A

course of action

29
Q

Planning Process Group: Those processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the […] that the project was undertaken to achieve.

A

objectives