Miscellaneous Flashcards

2
Q

The performance measurement baseline consists of which individual baselines?

A

Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The […] consists of the following three elements: Scope, Cost, Time

A

Project Triangle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The Project Triangle consists of the following three elements: […], Cost, Time

A

Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The Project Triangle consists of the following three elements: Scope, […], Time

A

Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The Project Triangle consists of the following three elements: Scope, Cost, […]

A

Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What indicates that a work breakdown structure, otherwise known as the WBS, has been finalized?

A

The WBS dictionary has been completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the criteria for determining whether work packages are sufficiently decomposed?

A

Whether the durations of the work packages fall between 8 and 80 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly