Project Schedule Management Flashcards
What is schedule management?
The process of developing, maintaining and communicating schedules for time and resource
What are the 6 processes in schedule management?
- Plan schedule management
- Define activities
- Sequence activities
- Estimate activity durations
- Develop Schedule
- Control Schedule
What is a schedule?
A schedule is the timetable for a project, programme or portfolio.
What is rolling wave planning?
The work to be accomplished in the near term is planned in detail, whereas the work in the future is planned at a higher level.
What is the purpose of the plan schedule management process?
Provides guidance and direction on how the project schedule will be managed throughout the project.
What is the ITTO for plan schedule management?
Inputs – Project Charter/ Project Management Plan (scope management plan/scope baseline)/Organisational Process Assets/Enterprise Environmental Factors
Tools and Techniques – Expert Judgement/Meetings/Data Analysis
Output – Schedule Management Plan
What is the purpose of the define activity process?
Decomposes work packages into schedule activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
What is the difference between the create WBS process and the define activity process?
The define activities process defines the final outputs as activities whereas the WBS process defines the outputs as deliverables.
What is the ITTO for the define activity process?
Inputs – Project Charter/ Project Management Plan (scope baseline/schedule management plan) Organisational Process Assets/Enterprise Environmental Factors
Tools and Techniques – Expert Judgement/Decomposition/Rolling Wave Planning/Meetings
Outputs – Activity list/activity attributes/milestone list/change requests/updates to project management plan such as changes to schedule and cost baseline
What is the purpose of the sequence activities process?
Defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
Every activity except the first and last should be connected to at least one predecessor and at least one successor activity with an appropriate logical relationship.
The Sequence Activities process concentrates on converting the project activities from a list to a diagram to act as a first step to publish the schedule baseline.
What is PDM?
Precedence Diagram Method - is a technique used for constructing a schedule model to show the sequence in which the activities are to be performed.
What 4 types of dependencies are used in PDM?
Finish-to-Start [FS] - An activity must finish before the successor can start
Start-to-Start [SS] - An activity must start before the successor can start
Finish-to-Finish [FF] - An activity must finish before the successor can finish
Start-to-Finish [SF] - An activity must start before the successor can finish. The successor can finish only after the predecessor starts
What are the attributes of dependencies?
Mandatory dependencies (hard logic) are legally or contractually required or inherent in the nature of the work, often involve physical limitations.
Discretionary dependencies (soft logic) are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired – e.g. in construction electrical work should start after finishing the plumbing work.
External dependencies involve a relationship between project activities and non-project activities. These dependencies are usually outside of the project team’s control – e.g. Procurement delivery of HW.
Internal dependencies involve a precedence relationship between project activities and are generally inside the project team’s control.
What is the Inputs for the sequence activities process?
Project Management Plan (schedule management plan/scope baseline)
Organisational Process Assets
Enterprise Environmental Factors
Project Documents (activity list/activity attributes/assumptions/milestone log)
What is the purpose of the estimate activity durations process?
Provides the amount of time each activity will take to complete.
What are the 4 estimating techniques?
Analogous, Parametric, Bottom Up, Three point estimating.
What is Analogous estimating?
Is based on previous similar projects, fast calculations, not much documentation needed but also not very accurate.
What is Parametric estimating?
Parametric estimating is based on historical records, fast calculation but not very accurate. Slightly more accurate than analogous.
What is Bottom Up estimating?
Is based is a more detailed estimate as it is divided into smaller parts, takes longer to estimate but the estimate is more accurate.