Definitions Flashcards

1
Q

What is meant by the term ‘‘acceptance criteria’?

A

A set of conditions that is required to be met before the deliverables are accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the definition for ‘accepted deliverables’?

A

Products, results or capabilities produced by a project and validated by the project customer or sponsors as meeting their specified acceptance criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is meant by the term ‘accuracy’?

A

Within the quality management system, accuracy is an assessment of correctness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is meant by the term ‘acquire resources’?

A

The process of obtaining team members, facilities, equipment, materials, supplies and other resources necessary to complete project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is meant by the term ‘acquisition’?

A

Obtaining human and material resources necessary to perform project activities. Acquisition implies a cost of resources and is not necessarily financial.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the definition for an ‘activity?

A

A distinct, scheduled portion of work performed during the course of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the definition for ‘activity attributes’?

A

Multiple attributes associated with each schedule activity that can be included within the activity list.

Activity attributes include; activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints and assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the definition for an ‘activity duration?

A

The time between the start and finish of a schedule activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the definition for ‘activity duration estimates’?

A

The quantitative assessments of the likely number of time periods that are required to complete an activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the definition for an ‘activity list’?

A

A documented tabulation of schedule activities that shows the activity description, activity identified and a sufficiently detailed scope of work description so project team members understand what work is to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is meant by the term ‘actual cost’?

A

The realised cost incurred for the work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is meant by the term ‘actual duration’?

A

The time between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the definition of an ‘adaptive life cycle’?

A

A project lifecycle that is iterative or incremental

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the definition for an ‘affinity diagram’?

A

A technique that allows large numbers of ideas to be classified into groups for review and analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the definition for an ‘agreement’?

A

Any document or communication that defines the initial intention of a project.
This can take the form of a contract, memorandum of understanding, letters of agreement, verbal agreements, email etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is meant by the term ‘alternative analysis’?

A

A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project.

17
Q

What is analogous estimating?

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar project or activity.

18
Q

What does the term ‘analytical techniques’ mean?

A

Various techniques used to evaluate, analyse or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables.

19
Q

What is the definition for ‘assumption’?

A

A factor in the planning process that is considered to be true, real or certain without proof or demonstration

20
Q

What is an assumption log?

A

A project document used to record all assumptions and constraints throughout the project life cycle.

21
Q

What is ‘attribute sampling’?

A

Method of measuring quality that consists of noting the presence (or absence)of some characteristics (attributes) in each of the units under consideration.

22
Q

What is the definition for ‘authority’?

A

The right to apply project resources, expend funds, make decisions or give approvals.

23
Q

What is resource leveling?

A

A resource optimisation technique in which adjustments are made to the project schedule to optimise the allocation of the resources and which may affect the critical path.

24
Q

What is a ‘backward pass’

A

A critical path method technique used to calculate the late start and late finish dates by working backward through the schedule model from the project end date.

25
Q

What is a project calendar?

A

A calendar that identifies working days and shifts that are available for scheduled activities.

26
Q

What is a schedule baseline?

A

An approved version of a schedule model that can only be changed through the formal change control process and is used to measure a basis for comparison to actual results.

27
Q

What is benchmarking?

A

The comparison of planned or actual processes, practices, and operations to other comparable organizations

28
Q

What is multi-criteria decision analysis?

A

Decision making tools that can be used to identify key issues and suitable alternatives to be prioritised as a set of decisions for implementation.

29
Q

What is a configuration management plan?

A

A configuration management plan is part of the project plan. It describes how information and items of the project and which information and items will be recorded. The purpose is to ensure the product, service or result of the project are consistent and operative.