Project Schedule Management Flashcards

1
Q

Project Schedule Management

A

provide detailed plan for how and then the project will deliver the result defined in project scope; communicating and managing stakeholder expectations and basis for performance reporting; should stay flexible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

schedule baseline

A

schedule developed at the beginning of the project which is formally accepted; can enter into scheduling tool to create model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tailoring for Schedule Management (4)

A
  1. life cycle approach
  2. resource availability
  3. project dimensions
  4. technology support
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

adaptive life cycle schedules

A

short cycles to undertake work; review the results; and adapt schedule as necessary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Schedule Management Trends and Practices (3)

A
  1. adaptive planning
  2. interative scheduling with backlog
  3. on-demand scheduling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Plan Schedule Management

A

establishes policies, procedures, and documentation for planning, developing, managing, and controlling your project schedule; outlines how you will allocate resources and prioritize activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define Actvities

A

identifying and documenting specific actions needed to produce project deliverables; reduces work package into specific activities; create activity list with specific milestones; subject matter experts help identify activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

rolling wave planning

A

interative planning technique in which the near term work to be done is defined in detail while future work is planned at a higher level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

progressive elaboration

A

interative process of increasing the level of detail in a plan as more information becomes available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

decomposition

A

technique used for dividing the project scope and deliverables into smaller, more manageable parts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Sequence Activities

A

create schedules network diagrams so team can execute work with minimal errors; identifies and documents relationships among project activities and show logical sequence of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Precedence Diagramming Method (PDM)

A

technique for constructing a schedule model where activities are graphically linked by one or more logical relationships in which they would be performed
1. finish-to-start
2. finish-to-finish
3. start-to-start
4. start-to-finish
(a successor activity cannot 2 until a predecessor has 1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

dependency determination and integration

A

allow you to sequence activities according to how they are dependent on each other

  1. mandatory - legally/contractually required
  2. discretionary - best practices
  3. external - non-project activites
  4. internal - inside team control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

leads and lags

A

factors to consider when creating a network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

lead

A

amount of time a successor activity can be advanced compared to a predecessor activity (-)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

lag

A

amount of time a successor activity can be delayed with respect to a predecessor activity (+)

17
Q

Estimate Activity Durations

A

clarifies amount of time to complete activity, monitor performance, report delays; establish deadlines and timeline to monitor progress; PM collects data to create estimates; considers resources

18
Q

analogous estimating

A

uses past data from a similar activity; when there is a limited amount of information; less costly/timely but less accurate

19
Q

parametric estimating

A

uses statistical relationship between historical data and other variables to calculate an estimate for activity parameters

20
Q

three point estimating

A

tE = (tO + tM = tP) / 3

(estimated, optimistic, most likely, pessimistic

21
Q

bottom up estimating

A

aggregating the lower-level components of the WBS; work within activity decomposed; detailed durations are estimated and then summed up

22
Q

Develop Schedule (EF)

A

create a model of the schedule and refine in response to changes in activities, resources, constraints, stakeholder demands; planned dates for completing activities
EF=ES+DUR

23
Q

critical path method

A

used to estimate the least possible time to complete the project and to determine the amount of time to complete the project and to determine the amount of flexibility (float) within the schedule; create network diagram, adding legend to each activity, perform forward and backward pass

24
Q

Control Schedule

A

ensuring that your team is completing work in a timely manner; create work performance information, schedule forecasts, and make changes