Project Schedule Management Flashcards
Smaller projects and schedule management
- Can make defining activities, sequencing activities, estimating activity durations and developing the schedule model one single process
- This is difficult to do with larger projects
Iterative Scheduling with a backlog
- Found in adaptive or hybrid environments
- Rolling wave planning of plans and executing over and over again
Lean Manufacturing
- Backlog of assignments
- As team members become available the assignments go to the next available person
- Not as much planning on who does what
- Everyone must be capable of performing all of the tasks
Scrum Master
Analogous to PM in Adaptive Environment
Acting as a Servant Leader to the team
Theory of Contraints
- Identifying the most limiting factor (ex. time, resources, etc.)
- Improve that constraint until its no longer the limiting factor
- Scientific approach to improvement
- Lean manufacturing
Schedule Management Plan
- First step in Schedule Management
- Defined how the schedule will be developed, managed, executed and controlled
ITTOs: Planning Schedule Management
- Inputs:
- Project Charter
- Project Management Plan
- EEFs
- OPAs
T&T:
- Expert judgement
- Data Analysis
- Meetings
Outputs
- Schedule management plan
What is in the schedule management plan?
- Project schedule model development
- Level of accuracy
- Units of measure
- Organizational procedure links (links to procurement, links to resources)
- Project schedule model maintenance
- Control thresholds
- Rules for performance measurements
- Reporting formats (# of activities on time, or # of activities complete, etc.)
Define Activities
- Activities associated with work packages (taken from the WBS)
- Basis for estimating scheduling and controlling work
- Activity attributes
- Milestone list shows all of the activities leading up to a given milestone
ITTOs: Define Activities
Inputs:
- Project Management Plan
- EEFs
- OPAs
T&T:
- Expert judgement
- Decomposition
- Rolling wave planning
- Meetings
Outputs:
- Activity list
- Activity attributes
- Milestone list
- Change requests
- PMP updates (schedule and/or cost baseline)
8/80 rule
- Rule not to breaking down the WBS too far
- Between 8 hours and 80 hours is how long a work package should take. Anything below 8 hours is too granular. Anything greater than 80 hours is too big
Control Accounts
- Marker in the WBS
-
Planning Packages
- Decisions to be completed for a given Control Account
Rolling Wave Planning
- Imminent work is planned in detail
- Distant work is planned at a high level
- As work approaches, the work is planned in more detail
- Focus on most important
- Example of progressive elaboration
- Possible to do this with phase gate
Activity List
- Separate document
- Lists all project activities
- Scope of work for each activity and an identifier
- Links back to WBS identifier
- Establishes relationships between activities (dependencies)
- Reosourcing requirements
- Imposed dates
- Constraints and assumptions
Lead
- negative time
- when we are allowing time to overlap for multiple activities
Lag time
- positive time
- waiting longer for one tag before completing another
LOE
- Level of effort
- Reporting/Budgeting
- Don’t contribute to project scope but are needed to manage the work
Discrete effort activities
- Required to complete the project scope
- Most activities are discrete effort activities
Apportioned effort
- Project Management work
- QA
- Integrated Change Control
- Communications
Milestones
- marker that show progress
- noting significant events or delivery items
- no duration or resources