Planning Processes Flashcards

1
Q

Collect Requirements

A

Gather stakeholder requirements your project is required to satisfy to consider the project complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Activities

A
  • Define exact activities that will need to be created in order to create elements of the Work Breakdown Structure and scope
  • Comes after project scope and the WBS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan Procurements

A

Procurements for the project are based on the needs of the project, the organizational procedures, and the project budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Work Breakdown Structure

A
  • Decomposes project scope

- Comes after the Project Scope Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Determine Budget

A
  • Examine aggregate costs of the individual elements to create a budget and cost baseline
  • Comes after the WBS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define Scope

A

Based on stakeholder requirements, the project scope statement defines what is and is not included in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate Activity Durations

A

Create time estimates for the duration of the project work and the duration of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Develop Resource Plan

A

Establish the ground rules, management, discipline, reawards and recognition system and human resource management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Plan Risk Responses

A

Seven possible risk responses that can be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Identify risks

A

Iterative project management process that examines the project for risks that may threaten any of the project objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate Activity Resources

A

Determines the people, materials, equipment and other necessities to complete the project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Plan Risk management

A

Defines the risk management approach to be used within the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Perform Quantitative Risk Analysis

A
  • Based off of the outputs of the Qualitative Risk Analysis

- In-depth review of the identified risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Plan Communications Management

A

Defines who will get what information and when

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Develop the Project Schedule

A

Examine project team calendars, resource availability, organization calendars, and the duration of the project work to schedule when the work will take place

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Develop the Project Management Plan

A

Creates the overall project management plan to communicate the intent and method of accomplishing the projects objectives

17
Q

Plan Quality Management

A

Define the expectations of stakeholders, requirements of the organization, regulations, and other factors considered to plan for quality management.

18
Q

Estimate Costs

A

Evaluate the costs of the resources and activities for each element in the WBS to predict the cost of the project

19
Q

Sequence the Project Activities

A

Examine the project work and put the activities in the correct order

20
Q

Perform Qualitative Risk Analysis

A

A quick, subjective review of the identified risks to determine which risk events demand additional analysis