Project Planning Flashcards

1
Q

What is the purpose of project planning?

A
  • To persuade people to perform tasks in a timely manner as so not to dely others
  • To make the best of the available resources
  • To provide a framework for decision making in the event of change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the principles of project planning?

A
  • Analysis
  • Determining sequence of activities
  • Assign time/cost values
  • Determine critical path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Gantt Chart Technique

A
  • Simple/ Easy to understand
  • Good for showing progress/delays
  • Doesnt show dependance of activities
  • Not ideal for complicated jobs/ Easily ommit activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Network Planning Technique

A
  • A system of acitivities flowing from left to right

- Show dependency of activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define Activity

A

A task requiredby the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define Path

A

A series of connected activities between any two activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Critical Path

A

A set of activities on the path from the project start to end that if delayed will delay the completion of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Critical Time?

A

The time required to complete all the activities on the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Network Key:

ES | Activity | EF
LS | Duration | LF

A

ES - Latest Earliest Finish Time of preceding activity
EF - ES + Duration
LF - Earliest Latest Start of succeeding activity
LS - LF - Duration
Float = LF-EF or LS-ES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define Total Float

A

Maximum time an acitivity can be delayed without affecting the critical path duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define Free Float

A

The amount of TF that can be used without reducing the following activity’s TF
FF= ES of succeding - EF of Activity