Project Mgmt Processes + Role of the PM Flashcards
What are the 5 process groups
Initiating Planning Executing Monitoring and Controlling Closing
Describe a Project Life Cycle with 4 phases - in this case installing a new phone system
- Deciding which phone system to install
- Installing the phone system
- Testing the Phone System
- Training New Users
All 49 Processes will be used for all 4 phases.
Can product phases overlap?
Yes, the initiating and planning process groups can be started while the monitoring and controlling process group of the previous phase is still going on.
Initiating - what is the point, and what are the outputs?
Authorizing the start of either the phase or the project.
Project Charter and Stakeholder Register are the outputs.
What are the key things that happen in initiation of a project? (7)
1 Authorize the project to start
2 Develop the project charter
3 Assign and set authority for PM
4 Determine why the project is needed
5 Identify high level estimates for time and costs
6 Determine high level risks that can affect the schedule or budget
7 identify high level constraints and assumptions
What are the key things that happen in the planning process group? (8)
1 Create the PM Plan and all of it’s subsidiary plans
2 Identify the efforts and objectives needed to create deliverables
3 Create three baselines of scope, time and cost
4 Collect requirements from Stakeholders
5 Identify risk and create the best response to it
6 Determine what needs to be procured
7 Plan to meet quality requirements
8 Obtain plan approval from designated stakeholders.
How many processes in planning?
24
What are the key things that happen in the executing process group? (9)
1 Satisfy Project Specifications
2 Implement change requests
3 Select and acquire the project team
4 Manage and resolve conflicts among stakeholders
5 Conduct quality assurance
6 Communicate project status with stakeholders
7 Select Vendors/award Contracts
8 Implement responses to identified risks
9 Capture and document lessons learned
Which process group usually takes the longest?
Executing
How many processes in the executing group?
10
what do change requests include?
corrective and preventative actions, and defect repairs
What are the key things that happen in the Monitoring and controlling group? (8)
1 Ensure project work is on track with scope, time, and budget
2 Check to make sure quality requirements are met
3 Control Risk to ensure it doesn’t derail project
4 Ensure Vendors are fulfilling their contracts
5 Ensure stakeholders are being engaged
6 Correct any deviations to the stated plan
7 Get deliverables formally accepted
8 Make sure change requests are approved/denied
How many processes in the monitoring and controlling group?
12
What 2 process groups happen siumultaneously?
Executing and monitoring and controlling
What are the key things that happen in the Closing Group? (5)
1 Contract closures
2 Archive Project Records + update knowledge bases
3 Document reasons a project is terminated before completion
4 Transition Deliverables to customers/sponsors
5 Create a final report on project outcome