Project Mgmt Ch.6 Questions Flashcards
You are the project manager of the JHG Project. This project has 32 stakeholders and will require implementation activities in North and South America. you have been requested to provide a duration estimate for the project. Of the following, which will offer the best level of detail in your estimate?
A. The resource calendar
B. An order of magnitude
C. A requirements document
D. A stakeholder Analysis
A. The resource calendar
The resource calendar is the best choice for this scenario as it is the only activity duration estimating input listed.
Michael is the project manager of the 78GH Project. This project requires several members of the project team to complete a certification class for another project the week of November 2. This class causes some of the project activities of Michael’s activities to be delayed from his target schedule. This is an example of which of the following?
A. Hard logic
B. External dependencies
C. Soft logic
D. Conflict of interest
B. External dependencies
Before the work can being, the certification must be completed.
You are managing an interiror decorating project. The walls are scheduled to be painted immediately after the primer. You have allowed 36 hours between the primer activity and the painting activity to ensure that the primer has cured. This is an example of which of the following?
A. Lead.
B. Lag
C. Soft logic
D. Finish-to-Start relationship
B. Lag
The time between the activities is lag time. The painting activity must wait 36 hours before it can begin.
As the project Manager for the DFK Project, you are reviewing your project’s network diagram (as shown in the following illustration):
Given the diagram, what is the relationship between tasks F and G?
A. FS
B. SS
C. FF
D. SF
A. FS
G is slated to start immediately after F, so this is a finish-to-start relationship. In other words, F must finish so G may start.
You are the project manager for the LLL Project. Steven, a project team member, is confused about network diagrams. Specifically, he wants to know what the critical path is in a network diagram. your answer is which of the following?
A. The critical path is the network that hosts the activities most critical to the project’s success.
B. The critical path is the path with the longest duration.
C. The critical path is always the one path that cannot be delayed or the entire project will be delayed.
D. The critical path is the path from start to completion with no deviation from the project plan.
B. The critical path is always the lognest duration.
What is the difference between PDM and ADM?
A. ADM places activities on arrows, while PDM places activities on nodes.
B. AD is also known as AOA, while PDM is sometimes referred to as GERT.
C. ADM hosts activities on nodes, while PDM hosts activities on arrows.
D. PDM can have two types of relationships between tasks, while ADM can have only one type of relationship between tasks.
A. ADM places activities on arrows, while PDM places activities on nodes.
ADM, the arrow diagramming method, is also known as “activity on arrow,” while the PDm, the precedence diagramming method, places activities on nodes. PDM is also known as “activity on nodes.”
Which network diagram method type can use dummy activities?
A. Project network diagrams
B. Precedence diagram method
C. Activity on the node method
D. Arrow diagramming method
D. Arrow diagramming method
Only the arrow diagramming method uses dummy activities.
Where is a project manager most likely to experience a subnet?
A. WBS
B. Kill points
C. Activity on the node method
D. Arrow diagramming method
D. Arrow diagramming method
Subnets are often included in network templates to summarize common activities in a project.
You are the project manager for the POL Project. This project will use a three-point estimate to calculate the estimates for activity duration. For activity D, you have the following information: P = 9, O = 4, M = 5. What is the result of this estimate?
A. 18 weeks
B. Six weeks
C. 33.33 days
D. Three weeks
B. Six weeks
The formula is (P+4M+O)/3. In this instance, the outcome is six weeks.
You are the project manager for the YKL Project. This project will impact several lines of business at completion. You have elected to schedule each milestone in the project to end so the work does not impact current business cycles. This is an example of which one of the following?
A. Constraint
B. Expert judgment
C. WBS scheduling
D. Soft logic
D. Soft logic
Soft logic alows the project manager to make decisions based on conditions outside of the project, best practices, or guidelines.
You are the project manager for the MNB Project. You and your project team are about to enter into the activity duration estimating process. Which of the following will not be helpful in your meeting?
A. Constraints
B. Assumptions
C. The project charter
D. Identified risks
C. The project charter
The project charter is not an input to the activity duration estimating process.
You are the project manager for a new training program at your customer’s site. This program will require each of the customer’s employees to attend the half-day class and complete an assessment exam. You will be completing the training at the customer’s facility, and will need a trainer for the duration fo the training, which is six moths. This is an example of which of the following?
A. Resource requirements
B. Assumption
C. Cost constraint
D. A human resource issue
A. Resource requirements
The trainer is required for the project for six months.
You are the project manager for a construction company. Your firm has been contracted to complete the drilling of a well for a new cabin in Arkansas. The specification of the well is documented, but your company has little experience in well drilling in Arkansas. The stakeholder is concerned your time estimates are not accurate since the soil and rock in Arkansas are much different than the soil in your home state. Which one of the following can you use to ensure your project estimates are accurate?
A. An order of magnitude
B. A commercial duration estimating database
C. Local contractors
D. Soil samplings from the Arkansas government
B. A commercial duration estimating database
Commercial duration estimating databases are valid resources to confirm or base time estimates upon.
You are the project manager for your organization. You and your project team are in conflict on the amount of time allotted to complete certain activities. Several of the team members want to bloat the time associated with activities to ensure they will have enough time to complete their tasks should something go awry. The law of economics that these tasks may suffer from is which of the following?
A. Parkinson’s Law
B. The law of diminishing returns
C. Hertzber’s theory of motivation
D. Oligopoly
A. Parkinson’s Law
Parkinson’s Law states that work will expand to fulfill the time allotted to it.
You are the project manager for your organization. You and your project team are in conflict on the amount of time allotted to complete certain activites. Several of the team members want to bloat the time associated with activities to ensure they will have enough time to complete their tasks should something go awry. Instead of overestimating their project activities, the project team should use which of the following?
A. Capital reserve
B. Contingency plans
C. Contingency reserve
D. Assumptions of plus or minus a percentage
C. Contingency reserve
Rather than bloat activities, projects should use a contingency reserve. A contingency is a portion of the project schedule allotted for time overruns on activities.