Implementing Project Integration Management Flashcards

1
Q

Assumptions

A

Beliefs considered to be true, real, or certain for the sake of planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Benefit Measurement Methods

A

Used in comparing the value of one project against the value, or benefits, of another; often used in project selection models.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Benefit/Cost Ratios

A

These models examine the cost-to-benefit ratio.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Change Control Board

A

A board that determines the validity and need of (thus approving or denying) project change requests.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Change Control System

A

A system to formally accept, review, and act upon project change requests.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Configuration Management

A

A plan that documents and organizes the stakeholder needs for communication. This plan covers the communications system, its documentation, the flow of communication, modalities of communication, schedules for communications, information retrieval, and any other stakeholder requirements for communications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Constrained Optimization Methods

A

These are complex mathematical formulas and algorithms that are used to predict the success of projects, the variables within projects, and the tendencies to move forward with selected project investments. Examples include linear programming, integer algorithms, and multi-objective programming.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Constraints

A

Any influence on the project that may limit the options of the project team in performing the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Earned Value

A

The value of the work that has been completed and the budget for that work, the equation for which is EV = %complete x BAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Future Value

A

A formula to calculate the future value of present money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Historical Information

A

Information the project may use from previous projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Internal Rate of Return

A

The IRR is a complex formula to calculate when the present value of the cash inflow equals the original investment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Lessons Learned

A

An ongoing documentation of things the project manager and project team have learned throughout the project. Lessons learned are supplied to other project teams and project managers to apply to their ongoing projects. They are documented throughout the project, not just at the end of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Murder Boards

A

Committees full of folks that ask every conceivable negative question about the proposed project. Their goal is to expose strengths and weaknesses of the project–and kill the project if it’s deemed worthless for the organization to commit to.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Net Present Value

A

NPV calculates the present value of monies returned on a project for each time period the project lasts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Payback Period

A

The amount of time it takes to “pay back” the costs of the project.

17
Q

PMIS

A

Project Management Information System (PMIS) is typically a computer program to assist in project management activities, recordkeeping, and forecasting.

18
Q

Present Value

A

A formula to calculate the present value of future money.

19
Q

Project Baselines

A

The accepted plans against which actual results are compared to identify variances.

20
Q

Project Charter

A

The charter authorizes the project, the project manager, and the required resources to complete the project work.

21
Q

Project Integration Management

A

The day-to-day actions of the project manager to ensure that all parts of the project work together. Composed of project plan development, project plan execution, and integrated change control

22
Q

Project Plan

A

The project plan is a collection of documents that is developed with the project team, stakeholders, and management. It is the guide to how the project should flow and how the project will be managed. It also reflects the values and priorities of, and the conditions influencing, the project.

23
Q

Project Scope Statement

A

Defines what the project will accomplish, create, and deliver.

24
Q

Scoring Models

A

These models use a common set of values for all of the projects up for selection. The projects with high scores take priority over projects with lesser scores.

25
Q

Statement of Work

A

This fully describes the work to be completed, the product to be supplied, or both. The SOW becomes part of the contract between the buyer and the seller. The SOW is typically created as part of the procurement planning process and is used by the seller to determine whether it can meet the project’s requirements.

26
Q

Status Review Meetings

A

Regularly scheduled meetings to record the status of the project work. These commonly employed meetings provide a formal avenue for the project manager to query the team on the status of its work, record delays and slippage, and to forecast what work is about to begin.

27
Q

Supporting Detail

A

Any information that supports decisions–including the logic employed and rationales–and the project plan as a whole. Supporting detail can include books, articles, web sites, vendor information, test results, historical information, and many other information sources.