Introducing Project Time Management Flashcards
Activity List
An output of activity definition, and includes all of the activities to be performed within the project. The list must be in line with the project scope.
Activity on Arrow
A network diagramming method where the arrows in the arrow diagramming method network diagram represent the activities within the project.
Activity on Node
A network diagramming method where the nodes in a project network diagram represent the activities.
Activity Sequencing
A process for setting the order of activities within the project schedule.
Analogous Estimating
This relies on historical information to predict estimates for current projects. Analogous estimating is also known as top-down estimating and is a form of expert judgement.
Crashing
This is the addition of more resources to activities on the critical path in order to complete the project earlier. Crashing results in higher project costs.
Critical chain method
A scheduling approach that considers the availability of the resources needed to complete the project work. Unavailable resources may cause the network diagram to be reconfigured or the project duration to take longer than originally planned.
Critical Path Method
The CPM is the most common approach to calculating when a project may finish. It uses a “forward” and “backward” path to reveal which activities are considered critical, and which contain float. If activities on the critical path are delayed, the project end date will be delayed.
Discretionary Dependencies
Discretionary dependencies have activities happen in a preferred order because of best practices, conditions unique to the project work, or external events which project managers should adhere to at their “discretion” and should document the logic behind the ordering.
Fast Tracking
Doing activities in parallel that are normally done sequentially.
Finish-to-Finish
This relationship means Task A must complete before Task B can complete. Ideally, two tasks must finish at exactly the same time, but this is not always the case.
Finish-to-Start
This relationship means Task A must complete before Task B can begin. This is the most common relationship.
Float
Total float is the total time an activity can be delayed without delaying project completion. Project float is the total time the project can be delayed without passing the customer’s expected completion date.
FNET
Finish No Earlier Than is a somewhat unusual constraint which requires the activity to be in motion up until the predetermined date.
Fragnets
Also called ‘subnets’ are portions of a network diagram that branch off the project and are not on the critical path.