Project Mgmt Ch.5 Questions Flashcards
Of the following, which is not part of project scope management?
A. Scope planning
B. Scope verification
C. Quality assurance
D. Create WBS
C. Quality assurance
Quality Assurance is not part of project scope management. It is the quality assurance program of the entire organization.
You are the project manager for the HGD Project and will need as many inputs to the scope planning as possible. Of the following, which one is not an organizational process asset?
A. Organizational procedures
B. Organizational policies
C. WBS
D. Historical information
C. WBS
The WBS is not an organizational process asset.
You are a project manager for your organization. Sarah, a project manager in training, wants to know which project documents can stem from templates? Your answer should be…
A. Risk policies
B. Organizational policies
C. Scope management plans
D. Historical information
C. Scope management plans
Scope management plans can be based on templates. For the record, so can the WBS, and project scope change control forms.
You are the project manager for a technical project. The project product is the complete installation of a new operating system on 4500 workstations. you have, in your project cost and time estimates, told the customer that the estimates provided will be accurate if the workstations meet the hardware requirements of the new operating system. This is an example of which of the following?
A. Risk
B. Assumption
C. Constraint
D. Order of magnitude
B. Assumption
This is an example of an assumption since the workstations must meet the hardware requirements.
You are the project manager for the NBG Project. This project must be completed within six months. This is an example of which of the following?
A. Schedule
B. Assumption
C. Constraint
D. Planning process
C. Constraint
A project that must be completed by a deadline is dealing with time constraints.
Which of the following best describes the project scope statement?
A. The description of the project deliverables
B. The authorizing document that allows the project manager to move forward with the project and to assign resources to the tasks
C. The process of managing all of the required work–and only the required work–to create the project’s deliverables
D. The process of planning and executing all of the required work in order to deliver the project to the customer
C. The process of managing all of the required work–and only the required work–to create the project’s deliverables
During the planning phase of your project, your project team has discovered another method to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of:
A. Risk assessment
B. Alternative identification
C. Alternative selection
D. Product analysis
B. Alternative identification
Alternative identification is a planning process to find alternatives to completing the project scope.
Of the following, which does the scope statement not provide?
A. Project justification
B. Project product
C. Project manager authority
D. Project objective
C. Project manager authority
The project charter provides the project manager with authority.
You are the project manager for the JHN Project. Mike, a project manager you are mentoring, does not know which plan he should reference for guarding the project scope. Which of the following plans does mike need?
A. The scope management plan
B. The scope change control system
C. The scope verification
D. The scope charter
A. The scope management plan
The scope management plan provides details about how the project scope may be changed.
You are the project manager for the JKL Project. This project has over 45 key stakeholders and will span the globe when implemented. Management has deemed that the project’s completion should not cost more than $34 million. Because of the global concerns, the final budget must be in U.S. dollars. This is an example of which of the following?
A. Internationalization
B. Budget constraint
C. Management constraint
D. Hard logic
B. Budget constraint
The budget must not exceed $34 million. In addition, the metric for the values to be in U.S. dollars can affect the budget if most of the product is to be purchased in a foreign country.
You are the project manager for your organization. You need to ensure the customer formally accepts the deliverables of each project phase. This process is known as ____________?
A. Earned value management
B. Scope verification
C. Quality Control
D. Quality assurance
B. Scope verification
Scope verification results in one thing: formal acceptance.
Which of the following is an output of scope verification?
A. WBS template
B. Rework
C. Formal acceptance
D. SOW acceptance
C. Formal acceptance
Scope verification results in one thing: formal acceptance.
Where can the project manager find work package information such as the code of an account identifier, a statement of work, information on the responsible organization, quality requirements and information on the required resources?
A. Project Plan
B. WBS
C. WBS dictionary
D. Project management plan
C. WBS dictionary
The WBS dictionary provides all of this information–along with information on milestones and contract information–and then cross-references each work package with relate work package information.
You are a project manager for a large manufacturer. Your current project is to create a new manufacturing assembly line that will allow your organization to create its products with less downtime and faster turnaround time for its clients. A stakeholder has presented a change request for your project which will likely increase the cost and time needed to complete the project. All of the following components are not part of the Change Control System except for which one
A. Adding more team members to the project to get the project work done faster
B. Outsourcing portions of the project execution to transfer risk
C. Tracking systems for the proposed change
D. Documenting the project and how the manufacturing assembly should work
C. Tracking systems for the proposed change
The only answer that describes a component of the change control system is the tracking system for the proposed change.
A project team member has, on his own initiative, added extra vents to an attic to increase air circulation in the attic. The project plan did not call for these extra vents, but the team member decided they were needed based on the geographical location of the house. The project team’s experts concur with this decision. This is an example of:
A. Cost control
B. Ineffective change control
C. Self-led teams
D. Value added change
B. Ineffective change control
The project team member did not follow the change management plan’s method of incorporating changes into the scope.