Project Management Flashcards

1
Q

Accept

A

Responding to risk by doing nothing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Addendum, construction document

A

Corrections or revisions made to construction documents after they are sent to bidders but before bidders have officially responded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Adjacency diagram

A

A diagram documenting critical physical proximities of organizational groups, equipment, or support functions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AIA Contract Documents

A

A set of standard contract forms produced by the American Institute of Architects (AIA) for design and construction contracts including the contract administration process. They are generally accepted as fair documents for all parties involved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Architectural drawings/ Engineering drawings

A

A set of technical drawings of a building or engineered item categorized by building trade (e.g., electrical, plumbing) used by architects or engineers to express a design proposal and enable a contractor to proceed with construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Architectural scale/ Engineering scale

A

A set of standard contract forms produced by the American Institute of Architects (AIA) for design and construction contracts including the contract administration process. They are generally accepted as fair documents for all parties involved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Assignable area

A

The portion of a floor or building used to house personnel, furniture and equipment. This is usable area minus secondary circulation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Authorization to proceed

A

A document issued to initiate a project and commence construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Avoid

A

Responding to risk by clarifying or changing plans to omit the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Backward pass scheduling

A

A scheduling technique that begins with a fixed completion date and arranges necessary tasks in order to allow enough time to complete all the project tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Barrier-free design

A

A facility design that employs multiple design considerations to allow the facility to be fully accessible by persons with disabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Bay

A

An area whose boundaries are generally defined by space between four columns (one at each corner).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Bid bond

A

A bond or cashier’s check that bidders provide to customers along with a bid for a capital project to prove that the bid is in earnest and the firm has sufficient capital resources and will provide a performance bond if the bid is chosen. These are only callable (exercised) when a contract is awarded but the bidder fails to perform under the terms in the bid. They are often for 1 percent of the bid value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Blocking plan

A

Illustration of how multiple groups or departments will fit onto a given floor of a building. Also called a blocking diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Bond

A

A bond or cashier’s check that bidders provide to customers along with a bid for a capital project to prove that the bid is in earnest and the firm has sufficient capital resources and will provide a performance bond if the bid is chosen. These are only callable (exercised) when a contract is awarded but the bidder fails to perform under the terms in the bid. They are often for 1 percent of the bid value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Bubble diagram

A

An adjacency diagram that illustrates primary and secondary adjacencies between major work groups or departments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Budget at completion

A

The planned final cost of a task/project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Budget variance

A

The difference between the budget at completion and estimate at completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Building information modeling (BIM)

A

A modeling process and technology for producing comprehensive, measurable, three-dimensional virtual models of buildings to aid in construction and all later phases of a facility’s life cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Building standard

A

Owner/landlord determined baseline for type and quality of materials and finishes to be used in their building and provided as part of base rent paid by the tenant (usually stipulated as an allowance per square meter (square foot)).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Building standard finishes

A

Finishes provided periodically by a landlord to a tenant as part of the tenant’s base rent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Build-out

A

(1) A general term referring to the execution phase of a design and construction project including construction, installation of equipment, and connection of utilities; (2) The new construction or reconfiguration performed on a tenant’s interior space.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Build-to-suit

A

A form of delayed ownership for real estate in which an organization has the developer retain ownership until the construction project is complete and the facility is ready for occupancy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Capital

A

The amount of money in circulation, the speed with which money circulates or is redistributed throughout the economy, and its price and availability. As the money supply is reduced, interest rates rise, and capital investment tends to decrease and move to short-term investments. These events adversely affect real estate funds attributed to facility assets with residual value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Certificate of insurance

A

A document from the insurance company that verifies insurance coverage for contractors on larger jobs. It includes dates that coverage is in effect, and the dollar limits and types of the coverage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Certificate of occupancy

A

A formal document often required by the local building codes as the final step to closeout of construction to allow for occupancy of the facility. Also known as certificate of beneficial occupancy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Change order

A

The written document signed by the contractor, designer and owner that allows for changes involving cost and time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Churn

A

The amount of movement and relocation of occupants within an organization within a specified period. It is the ratio of the number of employees moved annually compared to the total number of employees in an organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Circulation factor

A

A percentage added to work space to allow for circulation patterns of persons or goods in usable space.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Commissioning

A

A planned and integrated systematic process of verifying and documenting that all building systems perform interactively according to the design intent and the owner’s operational needs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Common area

A

Area with common access to all users within a gross space (e.g., public corridors, primary circulation, lobbies, rest rooms, mechanical or utility rooms, and vestibules). Also known as common support area, building core or service area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Common area factor (rentable/usable ratio)

A

The factor used to determine a tenant’s pro rata share of the common area. Also known as core factor, core and service area factor, or loss factor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Completion date

A

A clearly defined date when the project is 100 percent complete including all of the punch list items. Also known as final completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Computer-aided design and drafting (CAD)

A

Computerized drafting software that can manage space, furniture, and equipment, as well as produce drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Construction agreement

A

A written contract between an owner and the general contractor detailing the terms to which the parties agree. The agreement details the deliverable (what is to be built), the compensation, the timeframe, and other factors typical of a legally binding contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Construction drawing

A

Scaled architectural or engineering drawings that include notations on the work required and the materials to be used, showing how to proceed with construction. They are usually provided as part of a larger set of construction contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Contract

A

A legal device used by two or more persons to indicate they have reached an agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Contract time

A

The period of time set forth for completion of construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Core and service area

A

The area with common access (or benefit) to all users within a gross space (e.g., public corridors, rest rooms, mechanical or utility rooms, and vestibules). Also known as common area, common support area, or core area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Core and service area factor (rentable/usable ratio)

A

The factor used to determine a tenant’s pro rata share of the core and service area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Cost variance

A

The amount of money a task is over or under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Cover letter

A

Temporary evidence of insurance. Also known as insurance binder.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Critical path

A

The longest set of sequential tasks in a project, which is the shortest possible planned project duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Critical path scheduling

A

A scheduling technique that is based on identifying predecessors and timeframes. Each process that requires a previous process to be completed before the new one can begin is entered in a time schedule so that the minimum time for overall project completion can be determined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Dead-end corridor

A

A corridor with only one way in or out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Demising wall

A

A wall between one tenant’s area and another as well as a wall between tenant areas and public corridors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Design intent drawings

A

Scaled drawings that form the basis of construction drawings by showing where all construction elements are to be located but omitting engineering calculations. They can be used in variance comparisons with as-built drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Direct negotiation

A

A method for awarding a contract where a single contractor or a small group of selected bidders is subject to negotiation to award the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Elevations

A

Drawings of a structure from a single perspective showing entire-structure flat plane projections of all vertical floors and features facing in the given direction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Errors and omissions insurance

A

Insurance purchased by design professionals to transfer to the insurer the cost of liability claims related to errors or omissions in design and construction documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Estimate at completion

A

A forecast of the final cost of a task/project using the most current data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Fast-tracking

A

A process of concurrently performing as many project tasks or phases as feasible to minimize total project time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Floor plate

A

A common term for floor size or outline of overall size, shape, features of a building basic floor plan/building basic shell plan. For example, they might be used to compare the efficiency of one potential site over another. Depending on the layout and design or features of the building bays or building service/core areas, one building may have less common area and therefore cost less in the long run.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Forward pass scheduling

A

A scheduling technique that takes tasks in sequential order in order to arrive at a realistic and reasonable completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

General and specific terms and conditions

A

A blanket term in contract language to refer to all of the general boilerplate terms and conditions incorporated by reference to a contract as well as the specific terms and conditions relating to the specific project, such as site access restrictions and security requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

General contractor

A

The traditional builder who engages in the complete onsite management of the actual construction project. Performs the work by contracting on their own behalf with subcontractors and suppliers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Glass line

A

A vertical plane indicating the location of the glass on a given wall of the building exterior used as a measurement point for various space measurement systems. Also known as window line.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Grade

A

A method of classifying materials or deliverables that have the same functional use but differences in technical features or perceived value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

Gross area

A

The sum of the floor areas on all levels of a building that are totally enclosed within the building envelope. (Measured to the outside face of exterior walls.) Designed for a tenant’s use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Hard costs

A

Cost for actual moving services, supplies and trucking expenses; costs for move materials, freight elevator and loading dock usage; special security guard services during the course of a move; new stationery, business cards, move notices, etc. Other move costs that might be included are design, food service, graphics, furniture, voice/data costs, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Holdback

A

A percentage of a contract price that an owner or contractor retains or percentage of a loan that a lender retains until the project is finished or all project bills are paid. Usually at least 10 percent of the total amount.

62
Q

Incentives

A

Contractually specified monetary inducements linked to specific performance measurements.

63
Q

Indemnification

A

A clause stating that the owner (officers, directors, employees, etc.) is “held harmless” from any damages or claims resulting from the construction project.

64
Q

Inspection

A

The detection and removal of flaws in deliverables at key milestones or at completion.

65
Q

Integrated project delivery

A

A technique that focuses on early collaboration and data sharing to maximize the final value for the owner in the form of the completed building.

66
Q

Internal rate of return (IRR)

A

The return on investment a company typically realizes (or targets to realize) based on its past track record regarding asset investments. It is the interest rate at which lifetime dollar savings equal lifetime dollar costs, after the time value of money is taken into account.

67
Q

Key plan

A

Small-scale floor plans incorporated into a corner of construction drawings to give a geographic orientation of the location of the construction project.

68
Q

Lead time

A

The delay between when materials or services are requested and when they are available at the right time and place. Lead time includes time for tender/bid processes, selection, contractor execution or production, and transportation.

69
Q

Letter of intent

A

A document issued by the owner to the contractor to allow work to begin prior to execution of the formal contract.

70
Q

Liability insurance

A

Insurance that protects the insured against lawsuits brought in response to supposed acts of negligence that result in injury or loss of property to the public.

71
Q

Licensing

A

(1) Permission to execute a project as granted by local authorities; (2) The act of granting a license that is mandatory for practicing a profession or service in a specific region.

72
Q

Life-cycle cost (LCC)

A

The total cost of acquisition, operation, maintenance, and support of an item throughout its useful life, and including the cost of removal.

73
Q

Limit of retention/retainage

A

The longest time period in which money can be held back for paying a contractor for rendered services to ensure all sub-contractors have been paid.

74
Q

Liquidated damages

A

An amount of damages on a daily basis specified in the contract. This amount will be assessed against the contractor for each day beyond the contract completion date that the project remains uncompleted.

75
Q

Loading capacity

A

A weight per square meter (square foot) measurement in buildings indicating the capacity for a building structure (usually flooring systems) to sustain weight.

76
Q

Maintenance period

A

The time period in which the contractor provides routine maintenance services for a deliverable as part of the contract.

77
Q

Material lien

A

A secured interest in a property to protect against defaults in payments to suppliers of materials used to improve said property.

78
Q

Measuring space

A

Agreed upon methods for measuring the space of a building such as when determining the total square meters (feet) to be charged as part of a lease.

79
Q

Mechanics lien

A

A claim on a property held by a supplier of materials or labor for nonpayment of a debt.

80
Q

MEP

A

Refers to mechanical, electrical and plumbing. Internationally, this term may be referred to as civil drawings.

81
Q

Millwork

A

Construction for custom-made facility furniture including cabinetry, special wood trim, or shelves.

82
Q

Mitigate

A

Adopt or apply preventive measures to reduce probability and/or severity of identified risks.

83
Q

Nonconforming use

A

A use of land that does not conform to the current land use controls imposed by the government.

84
Q

Non-disclosure agreement

A

A legally enforceable contract or clause that requires the contracted resource to treat specified intellectual property as proprietary and not share it with others.

85
Q

Open tender/bidding

A

The process where multiple contractors are invited to tender/bid on a project so that the owner can maximize market pricing and achieve the desired project at the lowest possible cost. Also known as competitive bidding.

86
Q

Partition

A

Inside floor-to-ceiling structures or wall assemblies that enclose a space; can be movable or removable.

87
Q

Payback period

A

The length of time it will take to recoup an initial investment cost. In other words, how long it takes to earn back the funds you spent on a project.

88
Q

Payment bond

A

A bond issued by an insurance company or bank on behalf of a general contractor that guarantees payment to all subcontractors and material suppliers if work is completed within the referenced contract’s set terms and conditions or in the event of default the surety will make the required payments so the project will be free of any liens at completion.

89
Q

Penalties

A

Contractually specified fines linked to specific performance measures.

90
Q

Performance bond

A

A bond issued by an insurance company or bank on behalf of a contractor that guarantees the contractor will perform the contract or in the event of default the surety (party assuming the debt obligation) will either complete the contract or pay monetary damages up to the bond limit. The cost of this usually ranges from 0.25 to 1 percent of a project’s estimated cost.

91
Q

Performance-based contracting

A

The method of contracting which entails structuring all aspects of an acquisition process around the results of work to be performed as opposed to how the work is to be performed. It emphasizes objective, measurable performance requirements and quality standards in developing scope/statements of work, selecting contractors, determining contract incentives, and performance of contract administration.

92
Q

Plans

A

The anticipated use of resources, timelines, and the sequence of tasks necessary to accomplish the goals of a project.

93
Q

Post-occupancy evaluations (POEs)

A

Surveys taken following project completion to assess the occupants’ level of satisfaction with the various aspects of the new working environment, as well as to check the performance against specifications of the major systems.

94
Q

Prescriptive-based contracting

A

A method of contracting that entails specifying how the work is to be performed and the materials that are to be used, as well as the results and objectives to be achieved at each milestone.

95
Q

Prevention

A

The detection and removal of process flaws during execution.

96
Q

Primary circulation

A

The portion of the building that is public corridor or lobby, or required for access by all occupants on a floor to stairs, elevators, rest rooms and/or building entrances.

97
Q

Program evaluation and review technique (PERT)

A

A critical path scheduling model that incorporates the main concepts and techniques of the critical path method but adds a probabilistic method of estimating duration and cost for each task. It incorporates probability by including an optimistic and pessimistic estimate but places the most weight on the most likely estimate.

98
Q

Programming

A

The process that defines the detailed project requirements of the end user that are needed to meet the project objectives and general project requirements. A type of analysis that employs user observation, interviews, and surveys to identify and detail a specific function in an organization, sometimes improving functionality (e.g., when translated into a new design for a space). It is documented as a statement of requirements.

99
Q

Progress payment

A

Payment made for completion of work approved by the owner at a given project milestone.

100
Q

Project

A

Specific units of work that when completed produce an outcome or achieve an objective.

101
Q

Project charter

A

A document used to justify and allow formal authorization of a project and release funds, prove it has a viable business case, list project requirements, link the project to strategy, and name persons responsible for the project including the project manager. Also known as project request form, project documentation or capital project justification.

102
Q

Project management

A

The coordination of people, funds and resources, tasks, and approvals required to accomplish an objective. It includes developing project plans and providing oversight in their execution to assure resources are used as planned, timelines are met, and the desired outcomes are achieved.

103
Q

Project objectives statement

A

A document used to state what the project will (and will not) accomplish in terms of its scope and deliverables. It includes a high-level schedule, budget, and set quality standards. Also known as initial project scope document, project description document or project definition document.

104
Q

Project planning

A

The process of organizing the tasks, resources, and people required to accomplish a unit of work.

105
Q

Project selection

A

A method of listing and ranking potential projects so that a project can be selected and the choice validated as the best possible expenditure of resources over a given time period.

106
Q

Punch list

A

A list of deficiencies, incomplete, or unacceptable work items compiled by the project manager, architect, engineers, and/or designers during final inspection of the project. Also known as snagging list.

107
Q

Quality

A

The process of confirming customer expectations, establishing performance standards and metrics based on those expectations, measuring the degree to which current products and services meet the standards and metrics, and identifying and implementing improvements to satisfy the standards and metrics. It incorporates customer expectations and feedback, the use of standards and metrics, the act of measuring and a commitment to continuous improvement.

108
Q

Quality control

A

A product-oriented set of measurement and analysis tools used to monitor project results and deliverables. It determines if results and deliverables comply with quality standards and seeks to discover the root causes of quality issues.

109
Q

Quick ship

A

A method used by furniture suppliers to produce and ship products from the factory soon after an order has been placed.

110
Q

Raceway

A

Enclosed, accessible channels within system furniture panels for communications, data, and power cabling.

111
Q

Raw space

A

A completed building shell or envelope often intended for subsequent tenant improvement that lacks final HVAC connections, electrical outlets, interior walls, or finish materials. Also known as shell space.

112
Q

Rentable area

A

The gross area minus exterior walls, major vertical penetrations and interior parking spaces. Gross area (exterior walls + major vertical penetrations + interior parking space).

113
Q

Risk

A

The potential for the realization of the unwanted, negative consequences of an event. It is the product of conditional probability of an event and the event outcomes.

114
Q

Scale drawings

A

Drawings that are set to a proportional but smaller size than the actual objects being represented as defined by a supplied key or method of conversion.

115
Q

Schedule variance

A

The amount of time that a task is over or under scheduled time.

116
Q

Schematic plans

A

Scale drawings that include all basic design components of a space or facility such as circulation corridors, partitions, and work space areas, but omit construction details and dimensions.

117
Q

Scope

A

The extent of work or tasks to be done to produce a project’s deliverables (products or services). This can be defined as the end results or deliverables themselves. It implies minimum and maximum limits on deliverables to ensure deliverables satisfy their purpose but omit unnecessary features.

118
Q

Scope creep

A

An extension of the objective(s) of the project by external influences, resulting in undesirable and unplanned changes to a project’s time, cost, and/or quality.

119
Q

Secondary circulation

A

The portion of a building required for access to some subdivision of space (whether bounded by walls or not) that is not defined as primary circulation. i.e. corridors between workstations.

120
Q

Shell plan

A

Scale drawings of a building’s exterior walls and windows, permanent partitions, columns, and service functions. Also known as conceptual design plans.

121
Q

Shop drawings

A

Drawings prepared by the contractor and/or subcontractors that show the specific proposed method for fabricating and erecting in order to achieve the end result outlined in the contract drawings.

122
Q

Slab to slab

A

The distance between floors of a building as measured from the top of the concrete floor slab to the bottom of the concrete ceiling slab; often used to describe walls that span the entire distance.

123
Q

Slack

A

Leeway allowed for starting or ending noncritical tasks sooner or later without affecting the overall schedule. Also known as float.

124
Q

Soft costs

A

Internal costs, such as salary/time of employees involved in managing the move; downtime and loss of productivity of employees being moved.

125
Q

Space programming

A

To determine user needs for amount and configuration/features of physical space based on user role or business unit/department needs.

126
Q

Specification

A

A description of the essential technical requirements for items (hardware and software), materials, and processes that includes verification criteria for determining whether the requirements are met.

127
Q

Stack plan

A

A vertical section drawn through a building showing which organizational groups occupy which floors. Also called a stacking diagram.

128
Q

Statement of requirements

A

A document that provides the interface between the customer (end user) and the people who are responsible for transforming space into a productive work environment (design professionals). Also known as project requirements program or program.

129
Q

Statement of Work (SOW)

A

A listing of the specific tasks the supplier is to perform.

130
Q

Substantial completion

A

A clearly defined checkpoint in the time of construction where the building or renovated space is ready for occupancy with only minor punch list items to be completed. Also known as practical completion.

131
Q

Subtask

A

A division of a task into units that are cohesive and relatively independent from the other subtasks within a given task.

132
Q

Success criteria

A

The combination of conditions that must be met or satisfied for a project, plan, or task to be considered a success. Success criteria are specific, measurable, and agreed upon by stakeholders.

133
Q

Swing space

A

Space available to temporarily house functions/ departments/units during renovation, alterations, and realignments.

134
Q

Systems

A

A set of interrelated, interdependent elements with behavioral patterns that interact with and affect the performance and behavior of the other elements.

135
Q

Systems furniture

A

Furniture that is modularly designed to be assembled in one or more possible configurations. Also called workstations.

136
Q

Task

A

A function to be performed that always consumes time and may consume resources. In contract proposals, a unit of work that is sufficiently well defined so that, within the context of related tasks, readiness criteria, completion criteria, cost and schedule can all be determined. Also known as activity.

137
Q

Tenant improvement (TI) allowance

A

Funds set aside by a landlord in accordance with a building standard for use by a tenant to make the space suitable for occupancy. The size of the allowance can vary by the duration of the lease. Also known as tenant finish allowance.

138
Q

Tenant improvement (TI) building standards

A

Standard building materials and qualities as identified by the landlord that are to be provided as part of the base rent to the tenant to improve tenant premises. Normally defined are items such as partitioning, doors, hardware, ceiling, lighting, window and floor coverings, a specified number of telephone and electrical outlets, and HVAC (heating, ventilation, and air-conditioning systems).

139
Q

Test fit

A

A scale drawing showing a proposed layout of space for business units or departments to determine if the space can adequately address space requirements.

140
Q

Transfer

A

Responding to risk by moving the financial or resource effects of a risk to a third party (e.g., contractor or insurance).

141
Q

Transfer

A

Responding to risk by moving the financial or resource effects of a risk to a third party (e.g., contractor or insurance).

142
Q

Usable area

A

The portion of a building or floor available for occupants. In leased space, this is the area not shared with other tenants. Rentable area – Common area (building core and service area + primary circulation).

143
Q

Value engineering

A

A systematic approach to assessing and analyzing the user’s requirements of a new asset, and ensuring that those requirements are met, but not exceeded. Consists primarily of eliminating perceived “non-value-adding” features of new equipment.

144
Q

Warranty period

A

The time period in which a promise or guarantee of quality workmanship or deliverable quality is enforceable.

145
Q

WBS dictionary

A

A document that itemizes and describes work packages and includes details such as dependencies.

146
Q

Work

A

The construction, equipment, and services described in the construction documents to be provided by the contractor.

147
Q

Work breakdown structure (WBS)

A

A graphical method of dividing a project’s deliverables and work into manageable or logical subdivisions so the project scope can be defined and the required work can be understood and assigned. A hierarchy that branches out from the general to the specific and can be presented as an indented list or in a graphical format.

148
Q

Work letter

A

A document that includes building standards plus any additional items to be paid for by the landlord or by the tenant; the letter specifics who is responsible for each item. Also known as building standard work letter.

149
Q

Work package

A

A division of a subtask into the smallest size unit of work defined in a WBS.

150
Q

Workstation

A

Any space, including furniture and equipment, designated for accomplishing a work function. The space may be assigned to an individual or intended for group or general use but typically excludes private rooms or conference areas surrounded by full height walls.