Project Management Flashcards

1
Q

Critical path analysis

A

A planning technique that identifies all tasks in a project, puts them in the correct sequence and allows for the identification of the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Critical Path

A

The sequence of activities that are critical to completing the project on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Network Diagram

A

The diagram used in critical path analysis that shows the logical sequence of activities and the logical dependencies between them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the Critical path analysis show?

A

It identifies the shortest possible time in which a project can be completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the activities that must be completed to achieve the shortest time possible called?

A

The critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Total Float

A

The maximum time an activity can be delayed without delaying the overall project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Free Float

A

The maximum time an activity can be delayed without delaying the next activity in the sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Earliest starting time (EST)

A

The earliest possible time an activity can start relative to the beginning of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Latest finish time ( LST )

A

The latest possible time an activity can finish relative to the beginning of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why do projects fail?

A
Customers not involved 
inadequate resources 
Poor senior management 
specifications keep changing 
Project overtaken by events 
Incompetent project team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Total Float formula

A

LST - Duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Free Float formula

A

EST - duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TIP: Critical activities all have zero float

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly