Project Management 101 Flashcards

Lessons learned in Project Management 101 chapter of the workbook.

1
Q

PMI Code of Ethics and Professional Conduct

A

Responsibility
Respect
Fairness
Honesty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Operations

A

Support day-to-day business activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project

A

Is a temporary effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project Management is the application of ___, ___, ___ to project activities to meet project requirements.

A

Skills, Tools and Techniques

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The Project Manager has the ultimate responsibility of the project. It is ALWAYS the PM’s ____ and ____.

A

Fault for responsibility and success!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project Constraints

A
Scope
Budget
Schedule
Resources
Risk
Quality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project

A

Specific scope driven by objectives.
Develops and implements plans.
Success is measured by product quality, timeliness, budget compliance and degree of customer satisfaction.
Controls project inter-dependencies to achieve specific benefits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Portfolio

A

Has business scope that changes with strategic goals of the organization.
Utilized to achieve an organization’s strategic plan.
Selects the right programs or projects prioritizing the work and providing needed resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Program

A

Group of related projects

A project may or may not be a part of it, but it will always have projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PMO Type - Supportive Control

A

Low Control providing a consultative role supplying templates, best practices, training, managing lessons learned, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PMO Type - Controlling Control

A

Medium Control; controls compliance to project management frameworks and methodologies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PMO Type - Directive Control

A

High Control; directly manages all projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Functional Organization

A

Stove-piped organizational structure is where the project manager has little to no authority, little to no resources and functions as a part-time resource, coordinating meetings with the functional manager, controlling budget and project tasks. Each department will perform work independently regardless if it is for the same project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Weak Matrix Organization

A

Structure is the same as a Functional Organization except the project manager functions more as a project coordinator or expeditor, but with limited authorization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Balanced Matrix Organization

A

Recognizes the need for a full-time project manager, but without full authority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Strong Matrix Organization

A

Project Manager has moderate to high authority with resources reporting to functional managers in various departments.

17
Q

Projectized Organization

A

Project Manager has almost total independent authority with resources directly reporting.

18
Q

Composite Organization

A

A structure combining two or more structures depending upon project type or requirements.
Based on company’s liking. This is usually not the most common approach, but works for some companies.

19
Q

Organizational Process Assets (OPA)

A

Artifacts, practices or information from any participating entity that is used to perform or manage the project. Two Categories (Process and Procedures and Corporate Knowledge Base)

20
Q

Enterprise Environmental Factors

A

Cultural or physical factors that influence, constrain or direct the project (marketplace and demand).
Governance or Federal Agency who oversees the company.

21
Q

OPA Process and Procedures for Conducting Project Work…

A

Initiating and Planning Process Groups
Executing, Monitoring and Controlling Process Groups
Closing

22
Q

OPA Corporate Knowledge Base

A

Organizational Standards, policies, procedures and project documentation.
Historical Information, lessons learned, and documentation from previous projects

23
Q

List of 5 Process Groups

A
  1. Initiating Process Group - define a new project or phase. Initial scope is defined and initial financial resources are committed. (FRD)
  2. Planning Process Group - Processes performed to identify scope of effort. (DDD)
  3. Executing Process Group - processes performed in PM plan. (Coding)
  4. Monitory and Controlling Process Group - processes performed to track, review, and orchestrate processes and performance of project. (DEV-QA)
  5. Closing Process Group - formally complete the project, phase or contractual obligations (BUS-QA)
24
Q

3 Parts of Project Information aligning with Date, Information, Knowledge and Wisdom Model

A
  1. Work Performance Data - is the raw observation and measurement during the project. [Comes out of executing process]
  2. Work Performance Information - is performance data from various project processes. [Put raw data into budget]
  3. Work Performance Reports - is the physical or electronic view of compiled information [Turn into Facts]
25
Q

When is a project risk highest?

A

The Beginning (because there is no plan yet)

26
Q

When is stakeholder influence greatest?

A

The Beginning (ask what deliverables)

27
Q

When are costs of project changes the highest?

A

Towards the End

28
Q

What are divisions within a project when extra control is required?

A

Project Phases

29
Q

What are natural end points of a project called?

A
Stage Gate
Milestone
Phase Review
Phase Gate
Kill Point
30
Q

When projects have more than one phase and those phases relate either sequentially or by overlapping.

A

Phase-to-phase relationship

31
Q

When project scope, time and costs are established at the beginning of the project

A

Predictive

32
Q

Intentionally repeat activities or phases. Can be performed with a phase-to-phase sequential relationship or overlapping relationship.

A

Iterative and incremental