PMP Formulas Flashcards
Cost Management Formula Communication Management Formula
EV
Earned Value
Earned Value. % Complete of work done.
AC
Actual Cost
Actual Cost. How much you’ve spent so far.
PV
Planned Value
Planned Value. Budget/Period $256k/4weeks = $64k per week PV.
BAC
Budget at Completion
Budget at Completion. $256k budget so this will be the amount for all 4 weeks period in BAC row.
This value doesn’t change across the span of project.
CV
Cost Variance.
[EV - AC]
= 0 on budget :)
> 0 under budget :)
< 0 over budget :(
SV
Schedule Variance
[EV - PV]
= 0 on schedule :)
> 0 ahead of schedule :)
< 0 behind schedule :(
CPI
Cost Performance Index
[EV / AC]
= 1 on budget :)
> 1 under budget :)
< 1 over budget :(
SPI
Schedule Performance Index
[EV/PV]
This will be a percentage %
= 1 on schedule :)
> 1 under budget :)
< 1 over budget :(
ETC - Estimate to Complete
(BAC - EV)
EAC
Estimate at Completion
AC+ (BAC - EV) or AC + ETC
VAC
Variance at Completion
BAC - EAC
Always equals to CV (cost variance)
TCPI (BAC)
To-Complete Performance Index
(BAC - EV) / (BAC - AC)
=1 same to complete,
< 1 easier to complete,
> 1 harder to complete
Communication Channel Formula
N (N-1) / 2
EMV
Expected Monetary Value
(P x I = EMV)
Probability x Impact = EMV
Monetary impact & percentage of probability = Impact is negative / Benefit is positive