PMP Formulas Flashcards

Cost Management Formula Communication Management Formula

1
Q

EV

Earned Value

A

Earned Value. % Complete of work done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AC

Actual Cost

A

Actual Cost. How much you’ve spent so far.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

PV

Planned Value

A

Planned Value. Budget/Period $256k/4weeks = $64k per week PV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC

Budget at Completion

A

Budget at Completion. $256k budget so this will be the amount for all 4 weeks period in BAC row.
This value doesn’t change across the span of project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

Cost Variance.

A

[EV - AC]

= 0 on budget :)
> 0 under budget :)
< 0 over budget :(

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV

Schedule Variance

A

[EV - PV]

= 0 on schedule :)
> 0 ahead of schedule :)
< 0 behind schedule :(

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI

Cost Performance Index

A

[EV / AC]

= 1 on budget :)
> 1 under budget :)
< 1 over budget :(

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI

Schedule Performance Index

A

[EV/PV]
This will be a percentage %

= 1 on schedule :)
> 1 under budget :)
< 1 over budget :(

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

ETC - Estimate to Complete

A

(BAC - EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC

Estimate at Completion

A

AC+ (BAC - EV) or AC + ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC

Variance at Completion

A

BAC - EAC

Always equals to CV (cost variance)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI (BAC)

To-Complete Performance Index

A

(BAC - EV) / (BAC - AC)

=1 same to complete,
< 1 easier to complete,
> 1 harder to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Communication Channel Formula

A

N (N-1) / 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

EMV

Expected Monetary Value

A

(P x I = EMV)
Probability x Impact = EMV
Monetary impact & percentage of probability = Impact is negative / Benefit is positive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly