Project Financial Control and Reporting Flashcards

1
Q

What are the financial control process pre and post construction?

A

Pre Con

Order of cost estimates
Cost planning
Value engineering

Post Construction
Cost reporting
Valuation
Variations
Final account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is value engineering

A

Review of engineering solution with has already been developed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is value management

A

Review of engineering solutions solution prior to the design stage For example, what is the best mix of different sizes and types of housing units in a residential development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you prepare a cashflow?

A

I would take the estimate cost based on my cost estimate/cost plan, I would then project the anticipated spend against the anticipated programme taking in considering the S curve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you know if a contractor is front loading on a cash flow

A

When there is an abnormally high cost at the beginning stage of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the elements of a cost report

A

Agreed contract Sum, Variation, Loss and expenses, anticipated changes, PS adjustments, valuation summary, cashflow forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purposed of a cashflow

A

So the client can anticipate the level of spend on the project at a period at time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the different categories of risk on a project

A

Design development
Construction risk
Client change risk
Inflation risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the different types of risk on a constriction project

A

Unknown ground conditions
Asbestos
Underground serviced
Neighboring building
Site access

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the types of PS on a project

A

Defined
Undefined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between a defined and undefined PS

A

Defined - Contract ought tot have include the scope in the programme.

Undefined - Not included in programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you instruct a PS

A

Once firm cost has been received from the contractor, I would assess the cost determine if it’s in line with the scope of works and whether the cost is reasonable, I would then issue an instruction as the EA omitting the PS replacing it with the actual cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

On Bilton Road - What would you advise the client if the project cashflow is below the forecast amount

A
  • Inaccurate forecasting from the contractor,
  • The works is behind programme
  • Issues on site impact works progressing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

On Bilton Road - What would you advise the client if you think a change is not a variation

A

I would advise the client that the change request noted are include within the employer’s requirements and has not been excluded by the contractor in the CPs therefore it should not be required as additional cost to the client. I would also notify the contractor the works should be deems included under the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly