Construction Technology and Environmental Services Flashcards

1
Q

what are the different types of foundations?

A

Concrete strip
Raft
Pile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the advantages and disadvantages of strip foundations

A

Advantages
- Quicker to construct
- Cheaper
- Can be adapted to different structures

Disadvantages
- Not suitable for all building
- Not as strong as other types of foundations
- Not suitable with poor shallow soil conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the advantages and disadvantages of raft foundations

A

Advantages
- can be provided where the shallow foundation is necessary but soil condition is poor.
- It resists differential settlement
- can be considered as a floor slab so reduced cost for a floor slab

Advantages
- Edge corrosion
- More expensive that strip foundations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the advantages and disadvantages of pile foundations

A

Advantages
- High bearing capacity making it suitable for structures with heavy loads
-Suitable for areas with weak shallow soil conditions.
- Pile foundations can be adapted to different types of soil, including cohesive, non-cohesive, and mixed soils, allowing for flexibility in construction projects.

Disadvantages
- More expensive
- Noise and vibration
- Not suitable for site with limited access.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the types of external wall systems use on construction projects

A

Cavity Wall
Rainscreem cladding
Curtain wall
Solid walls

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is timber frame construction

A

Prefabricated external and internal stud walls, floor joists and roof trusses to form the super-structure which is a complete structural frame that transfers the vertical and horizontal loads to the foundations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What design aspects did you consider on you heather house project

A
  • A the sizes of change rooms required
  • Fatalities required to be provided
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the requirements by sports England which impacted the design.

A

Ensuring access to disable users

Separation of changing and wet and muddy areas from any social and indoor sports accommodation

Provide well considered entrance and lobbies and make provision for boot cleaning

Good external lighting, security systems and CCTV installation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the construction methodology of a pile foundations

A

Construction of a piling male

CFA - A piling rig soil in excavated a at the same time concrete is being pumped into the ground

Bore Piles - hole is excavated in the ground, a reinforcement change is then put in and concrete is poured

Driven piles - Precast concrete piles are driven in direct into the ground using a piling machine

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

On King Hill - What are the advantages did you advise the client on a still frame over a concrete frame?

A

Advantages
- Speed of construction
- Typical allows for longer spans
- Can be fabricated off site
- Lower embodied carbon

Disadvantages
- Less flexibility - Cannot be altered on site
- Required fire protection
- Insulation required to improve thermal conductivity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you advise the client that a modular building was the most efficient in terms of time and cost?

A

I did a soft market test on the design based on the indication design prepared by the architect. The supplier also advised on the lead time of the unit and I compared tihs against the steel frame proposed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between approve document and building regulations

A

Approve documents provides guidance on ways to meet the building regulations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly