Contract Practice Flashcards

1
Q

What are the various forms of JCT contracts

A

JCT D&B
JCT SBC
JCT IC
JCT MW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the contractual mechanism of JCT D&B are you aware of

A
  • An Employer may issue an instruction for a Variation/Change under Clause 3.5 (D&B). Should the Contractor not implement the instruction, the Employer has the right to issue a notice to the Contractor which after 7 days allows the Employer to employ others to complete the instruction and the additional costs can be deducted from the Contractor.
  • Retention is by the employers
  • Payment provisions
  • Extension of time
  • Issues in instruction for works not in accordance with the contract
  • Issuing practical completion and no completion certificate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What s a collateral warranties

A

It is a contractual document created between two parties who is are not otherwise party to the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

On Linwood Crescent can you run me through the the proceed of assessing a contractors valuation

A
  • Assess the valuation as soon it it’s been submitted by the contractor
  • Organised a site meeting with the contractor to review the valuation/works on site.
  • Reconciled against previous moth’s valuation to track movement
  • Prepare notes or queries
  • Once one site I will run through any queries with the contractor.
  • Check the works, prelims and materials on site
  • Make any adjustment to the valuation following site visit and seek agreement with the contractor before issuing certificate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

On Linwood Crescent How would you asses the contractors prelims on site

A

I would ensure a draw down provided by the contractor and review the fixed prelims to see if the items are on site. For the time prelims I will compared that against how far the contraction is against programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Queens Road - What has handover information did you expected on the project

A

Electrical commissioning cert
Building control cert
Building warranty cert
As built drawings
Building Manuals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

On HRA Phase 4 what was the procedure for terminating the contract

A

I advised the client a notice must be serve a notice to the contractor specifying the default as stated on clause 8.4.1

Clause 8.4.2 - If the contractor continues a specified default for 14 day form the receipt of the notice, the employer may within 21 day from the expiry of the 14 day period by a notice to the contractor terminate the contractors employment under the contract.

If further notice has not been served referring to in clause 8.4.2 (whether as a result of the ending of a specified default or otherwise) but the contractor repeats a specified default ( whether previously repeated or not), the upon or within reasonable time after such repetition, the employer may by notice to the contractor terminate that employment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

On the Lovelace primary school project - What contractor options did you you discuss with the clients

A

JCT intermediate and JCT Minor works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Lovelace Primary School- why did you recommend the a JCT intermediate contract with contractors design.

A

The minor works contract did not have provision for a collateral warranty

The project also had elements of work which required contractor design input

How well did you know this?
1
Not at all
2
3
4
5
Perfectly