Project Finance (Control and Reporting) Flashcards

1
Q

What are the different types of provisional sum?

A

Defined - sufficient information to allow the contractor to include for prelims and programme.

Undefined - contractor has not allowed for prelims and programme, therefore may be entitles to an extension of time / loss and expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is contained within a post-contract cost report?

A

Executive Summary
Cost Report - detailing position, movement, risks and opportunities
Approved and pending changes
Provisional sums
Cashflow - if required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is usually contained within a change control register?

A

Change reference
Date change is raise
Details of the change
Reasoning for change
Cost Impact
Programme Impact
Source of funding
Change status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How would you produce a cashflow?

A

Using a cashflow projection or S Curve tool.

Pre-contract - should be avoided as difficult to predict
Post Contract - request from main contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly