Contract Practice/Admin Flashcards
What is needed for a contract to be formed?
Capacity
Intent
Offer
Consideration
Acceptance
Legality
Can you give an overview of the structure of the NEC?
Core Clause - payment, CE’s, insurances, time
Main Options;
- Option A Priced with Activity Schedule
- Option B Priced with BoQ
- Option C Target With Activity Schedule
- Option D Target with BoQ
- Option E - Cost Reimbursable
- Option F - Management Contract
W Clauses (Dispute Clauses - W1, 2 & 3)
X Clauses (performance bond, PCG, sectional completion, retention, LAD’s)
Y Clauses (National Legislation)
Z Clauses (bespoke amendments)
Can you name some of the contracts in the JCT Suite of contracts?
Standard Building Contract.
Design & Build.
Intermediate.
Minor Works.
PCSA.
Major Projects Agreement.
Measured Term.
Framework Agreement.
What types of pricing options are there?
Lump sum - fixed price agreed at the start.
Target Cost - a price is agreed, then at the end of the project the under spend or overspend is shared between client and contractor.
Cost plus - Contractor paid actual cost they have incurred plus and agreed percentage for OH&P.
Cost Reimbursable - A schedule of rates is agreed, then at the end of each month the contractor will measure what they have incurred.
Guaranteed/ Agreed Maximum Price - Fixed price where the contractor takes risk on overspend and savings.
Can you identify some differences between NEC and JCT?
Different terms for individuals.
Time and cost included in changes under NEC.
Programme is a contractual document in NEC.
NEC has timescales on change control procedures.
Can you outline the payment process and timescales under a JCT D&B?
21 day process in total starting with contractor submitting their application.
Due date is 7 days after this.
14 days from due date is final date for payment.
Payment notice should be issued no late than 5 days from the due date.
Pay less notice should be issued no later than 5 days before final date for payment.
What are the different types of subcontractor?
Domestic - selected through competitive tender.
Named - client provides a list for the main contractor to use for competitive tender.
Nominated - Proposed by the client and must be used.
What are LAD’s?
Damages inserted into the contract that the client can claim in the event of non-completion by the contractor.
What are some of the different suites of contract?
JCT
NEC
PPC2000
How does the structure of JCT contracts differ to NEC?
Under JCT everything forms part of the standard contract whereas under NEC there are core and optional clauses so there is the ability to adapt the standard contract without making amendments.
How do CE’s under NEC differ to variations under JCT?
Time and cost are both dealt with under CE’s.
Under JCT this is split between variations, EoT and loss and expense.
What is Novation?
Transfer of rights and obligations under an existing contract, for example under a D&B contract the design team is novated from the client to the contractor.
What is a Collateral Warranty?
When a contractual link is created between two parties under an existing contract where one does not already exist, for example between client and a subcontractor.
Allows the client to claim from subcontractors in event of a breach.
What is a Letter of Intent?
A non-binding letter which outlines an agreement in principle prior to the contract being executed.
What are the different types of Letter of Intent?
Comfort Letter - provides contractor comfort
Consent to Spend - allows contractor ability to place orders
Recognition of Contract - all terms have been agreed however awaiting final signing of contract
What forms of performance security exist for a client?
Performance Bond
Parent Company Guarantee