Project Finance Flashcards
What are the contents of a Cost Report?
Executive Summary
Cost Summary
Cash-flow
Variations to Date
Anticipated Variations
Risk Allowances
Forecast Final Account
Report Basis
What is the purpose of producing a cost report?
To monitor and manage cost throughout the project, giving the client an understanding of potential savings or additional monies required.
To inform the client on actual project cost against the budget.
Why is it important for the client to know the anticipated out-turn cost?
It gives them the best possible basis on which to base future project decisions.
As well as for funding purposes.
What is a cash flow forecast?
A financial planning tool that shows the predicted flow of cash in and out of a project. Typically shown month by month.
Contractor payments will typically form an S curve.
How would you produce a cashflow forecast?
It depends on the stage of the project.
Pre-contract I would use an s-curve formula.
Post contract I would use the contractor’s pricing document and their programme.
Should cost reports include VAT?
No.
What do you do after issuing a cost report?
Meet the client in person to review it.
What are variations?
Alterations or modifications to the design, quality or quantity of the contract works or to the site access or working conditions.
Why might variations arise?
Change to specification.
Discrepancies between contract documents.
Lack of depth to the employer’s requirements.
What form must an instruction take?
It is best practice under the majority of contracts for instructions to be made in writing.
What about oral instructions?
The validity of oral instructions depends on whether the form of contract being used contains mechanisms for them to be valid.
In my opinion it is always best practice to follow up verbal instructions with written instructions as soon as possible.
What are the valuation rules for variations under JCT Forms of Contract?
There are three rules for measurable work:-
If it is of a similar character, quantity and in the same conditions as existing work, then the bill rates should be used.
If it is of a similar character, but different quantity or conditions, the bill rates should be used as a basis but a fair allowance should be made to take account of the difference.
If it is not of a similar character, fair rates and prices should be used (star rate).
Non measurable work to be valued by dayworks.
What is a star rate?
A rate that is based on the bill rates but includes a fair allowance.
This may be used because the conditions on site for installation are more complicated that first envisaged.
What are ‘fair rates and prices’?
A market rate.
A rate based on actual costs.
A rate in line with current cost data.
What are dayworks?
The actual cost of all the materials, labour and plant used in carrying out the work, along with a percentage additions to each category as set out in the contract.
What information is necessary to be able to assess dayworks?
Vouchers showing the amount of time spent on each activity (dayworks sheets).
Names of the workmen.
Plant and materials used.
Information should be given to the CA for verification.
If you and the contractor’s QS could not agree on something how
would you resolve it?
I would discuss with the partner and client to try and seek a resolution with the contractor.
The contractor could take the dispute to adjudication if necessary but all parties should try and resolve the matter by negotiation in the first instance.
What is quantum meruit?
This translates to ‘what he deserves’ for example fair and reasonable costs that have been incurred.
Give an example of where quantum meruit might be used?
If the employer and contractor reach a separate agreement on acceleration, the costs of this may be based on a ‘fair and reasonable’ basis.
What can an organisational cashflow be used for?
It can be used to assess whether a company will be able to adequately cope with the works being considered.
What are important points when reviewing an organisational cashflow?
Overdraft level.
Frequency of overdraft use.
Potential effect of bank removing overdraft.
Potential effect of company losing 1 or more key clients.
What different payment mechanisms are there?
Stage payments - milestone
Periodic/Interim valuation
How do the different payment mechanisms effect cashflow forecasting?
Stage payments - high predictability of cashflow, low accuracy of value of work done
Payment against activity schedule - reasonable predictability of cashflow, reasonable accuracy of value of works done
Valuation of works done on site to date - Lowest predictability of cashflow, high accuracy of value of works done
Why is it important to consider the form of contract when producing a cashflow forecast?
Because different forms of contract have different payment timescales between application and payment.
What other considerations should be made when producing a cashflow forecast?
Statutory holidays.
Time of year.
Weekend working requirements.
December valuation date is often pushed forwards due to Christmas, therefore January payment date will be earlier.