Project Finance Flashcards

1
Q

What are the contents of a Cost Report?

A

Executive Summary
Cost Summary
Cash-flow
Variations to Date
Anticipated Variations
Risk Allowances
Forecast Final Account
Report Basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of producing a cost report?

A

To monitor and manage cost throughout the project, giving the client an understanding of potential savings or additional monies required.
To inform the client on actual project cost against the budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why is it important for the client to know the anticipated out-turn cost?

A

It gives them the best possible basis on which to base future project decisions.
As well as for funding purposes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a cash flow forecast?

A

A financial planning tool that shows the predicted flow of cash in and out of a project. Typically shown month by month.
Contractor payments will typically form an S curve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How would you produce a cashflow forecast?

A

It depends on the stage of the project.
Pre-contract I would use an s-curve formula.
Post contract I would use the contractor’s pricing document and their programme.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Should cost reports include VAT?

A

No.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do you do after issuing a cost report?

A

Meet the client in person to review it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are variations?

A

Alterations or modifications to the design, quality or quantity of the contract works or to the site access or working conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why might variations arise?

A

Change to specification.
Discrepancies between contract documents.
Lack of depth to the employer’s requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What form must an instruction take?

A

It is best practice under the majority of contracts for instructions to be made in writing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What about oral instructions?

A

The validity of oral instructions depends on whether the form of contract being used contains mechanisms for them to be valid.
In my opinion it is always best practice to follow up verbal instructions with written instructions as soon as possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the valuation rules for variations under JCT Forms of Contract?

A

There are three rules for measurable work:-
If it is of a similar character, quantity and in the same conditions as existing work, then the bill rates should be used.
If it is of a similar character, but different quantity or conditions, the bill rates should be used as a basis but a fair allowance should be made to take account of the difference.
If it is not of a similar character, fair rates and prices should be used (star rate).
Non measurable work to be valued by dayworks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a star rate?

A

A rate that is based on the bill rates but includes a fair allowance.
This may be used because the conditions on site for installation are more complicated that first envisaged.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are ‘fair rates and prices’?

A

A market rate.
A rate based on actual costs.
A rate in line with current cost data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are dayworks?

A

The actual cost of all the materials, labour and plant used in carrying out the work, along with a percentage additions to each category as set out in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What information is necessary to be able to assess dayworks?

A

Vouchers showing the amount of time spent on each activity (dayworks sheets).
Names of the workmen.
Plant and materials used.
Information should be given to the CA for verification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

If you and the contractor’s QS could not agree on something how
would you resolve it?

A

I would discuss with the partner and client to try and seek a resolution with the contractor.
The contractor could take the dispute to adjudication if necessary but all parties should try and resolve the matter by negotiation in the first instance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is quantum meruit?

A

This translates to ‘what he deserves’ for example fair and reasonable costs that have been incurred.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Give an example of where quantum meruit might be used?

A

If the employer and contractor reach a separate agreement on acceleration, the costs of this may be based on a ‘fair and reasonable’ basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What can an organisational cashflow be used for?

A

It can be used to assess whether a company will be able to adequately cope with the works being considered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are important points when reviewing an organisational cashflow?

A

Overdraft level.
Frequency of overdraft use.
Potential effect of bank removing overdraft.
Potential effect of company losing 1 or more key clients.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What different payment mechanisms are there?

A

Stage payments - milestone
Periodic/Interim valuation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How do the different payment mechanisms effect cashflow forecasting?

A

Stage payments - high predictability of cashflow, low accuracy of value of work done
Payment against activity schedule - reasonable predictability of cashflow, reasonable accuracy of value of works done
Valuation of works done on site to date - Lowest predictability of cashflow, high accuracy of value of works done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Why is it important to consider the form of contract when producing a cashflow forecast?

A

Because different forms of contract have different payment timescales between application and payment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What other considerations should be made when producing a cashflow forecast?

A

Statutory holidays.
Time of year.
Weekend working requirements.
December valuation date is often pushed forwards due to Christmas, therefore January payment date will be earlier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Should you include the rectification period in a cashflow forecast?

A

Yes.

27
Q

How do you value a Provisional Sum?

A

The same way as a variation.
The CA will issue an instruction for its expenditure.

28
Q

How are Provisional Sums dealt with in the Final Account?

A

The provisional sum is included in the contract and then deducted.
The actual value added back as a variation.

29
Q

Why would project cash-flow be behind target?

A

Site conditions.
Adverse weather.
Re-sequencing of works.
Materials being stored off-site.
Materials not being delivered on time.
Inaccurate cash-flow forecast.

30
Q

How does NRM classify risks?

A

Employer change risk.
Employer other risk.
Design development risk.
Construction risk.

31
Q

How do JCT contracts define change?

A

Alteration or modification to the design, quality or quantity of the works.

32
Q

What methods are there of obtaining a cost for variations under JCT forms of Contract?

A

Using bill rates
Using star rates (fair and reasonable allowance
Using Dayworks
A schedule 2 quotation

33
Q

What costs does the schedule 2 quotation contain?

A

Value of the work.
Any adjustment of time.
Money in lieu of direct loss and expense.
The fair and reasonable cost of preparing the quotation.

34
Q

Can a contractor refuse to provide a schedule 2 quotation?

A

Yes. They must notify the CA within a defined time period, disagreeing with the approach of producing a quotation.
They are then not obliged to produce a quotation unless instructed further by the CA.
The usual reason that a contractor would refuse is due to a lack of info.

35
Q

What costs are the contractor entitled to if the schedule 2 quotation is
rejected?

A

The fair and reasonable cost of preparing the quote, as long as the quote itself was fair and reasonable.

36
Q

Can a contractor claim for the cost of preparing a schedule 2 quotation?

A

Yes a fair and reasonable amount can be claimed and paid, even if the quotation is not accepted.

37
Q

What is a Defined Provisional Sum?

A

Contractor is deemed to have made allowance for the works in their programme and prelims.

38
Q

What is an Undefined Provisional Sum?

A

The contractor is not deemed to have made allowance in their programme and prelims.
Contractor may be entitled to an extension of time or additional prelims once the works are undertaken.

39
Q

What is a provisional sum?

A

Generally an allowance or estimate included within the contract that are:-
Not sufficiently defined, designed or detailed to allow for an accurate pricing.
Work that the employer may or may not wish to have carried out.

40
Q

How does the NEC contract incorporate provisional sums?

A

Do not provide the use for provisional sums.
If the work cannot be properly priced, it should be excluded until properly defined.

41
Q

What is change control?

A

Process of dealing with any changes on a project.

42
Q

What are prime cost sums?

A

A sum that the client provides for works yet to be fully defined, and exclude a contractor mark-up.

43
Q

What is the difference between a prime cost sum and provisional sum.

A

A prime cost is limited to the cost of supplying the relevant item and does not include any work that relates to it i.e. installation.
A provisional sum includes an allowance for supplying and all the related work.

44
Q

L1 - What are the techniques for controlling and reporting cost?

A

Producing cost reports which show the forecasted final account of the project. A forecasted cash flow would also give the client an understanding of their outgoings within the period. Beneficial for budgeting purposes.

45
Q

L1 - What is the difference between cost control and cost reporting?

A

The objective of cost control is to manage the delivery of the project within the approved budget. Regular cost reporting will facilitate, at all times, the best possible estimate.

46
Q

L1 - As a QS what should you be doing for your client?

A

Ensure that the project remains in budget and provide updates in terms of cost reporting.

47
Q

L1 - How would the number of changes affect the frequency of reporting?

A

The more changes, the more complex the project. Therefore, the frequency of reporting would increase to provide the client with regular updates on the status of the project.

48
Q

L1 - Would it not be better to prevent/mange the changes rather than just report on them?

A

Yes, it would be beneficial to prevent and manage any changes, although the client would still need to be kept up to date with any potential changes through a reporting process.

49
Q

L1 - How do you compile a risk register?

A

You would sit down with the project team to identify hazards. You would apply a probability % to these hazards to give a score within the risk register. You would also confirm how they will be dealt with and by whom.

50
Q

L1 - How do you quantify risks?

A

You would apply a probability % to each of the hazards. This would be multiplied by a rate to give you an overall cost of the hazard.

51
Q

L1 - What are the key components of a cost/value reconciliation?

A

Used to measure expenditure against budgets, and what the overall profit margin is.

52
Q

L1 - What is the importance of having a project cash flow forecast?

A

It gives the client an understanding of their expenditure throughout a period.
It is used as a tool to predict funding at a given period in time.

53
Q

L1 - What information would you provide in your cost report?

A

Executive Summary
Cost Summary
Cash Flow
Variations
Anticipated Variations
Provisional Sums
Contingency
Claims

54
Q

L1 - What do you understand to be the difference between prime cost and provisional sums?

A

A prime cost is limited to the cost of supplying the relevant item and does not include any work that relates to it i.e. installation.
A provisional sum includes an allowance for supplying and all the related work.

55
Q

L1 - What current challenges is Covid and/or Brexit bringing to Project Finance?

A

Delays and variations to construction work which have to be regularly updated and reported on within cost reports.

56
Q

L2 - Project Zeta – what sort of provisional sums were these?

A

These were defined provisional sums.

57
Q

L2 - What is the difference between a defined sum and undefined and how are they dealt with?

A

An undefined provisional sum is where the contractor is not deemed to have made allowance in their programme and prelims.
They are dealt the same was as variations.
They would be instructed by the CA and priced by the contractor for review.
I would proceed to review the costs and agree the cost with the contractor.
If agreed the cost would be included within the next interim valuation.
An undefined provisional sum may warrant an extension of time and a variation for costs.

58
Q

L2 - When cost reporting how have you dealt with forecasting when the costs may be lagging behind progress?

A

Ill first look into the reasons why costs are lagging behind as this could indicate contractor difficulties/potential insolvency or works are slowing down etc.
I’ll also request from the contractor an updated cash flow and programme to include in the cost report which gives the Client a better understanding of the monthly expenditure

59
Q

L2 - Where have you used a cashflow to manage overall finances?

A

I have used a cash flow on Wythenshawe GMMH to forecast expenditure and provide the client with an understanding of their future spend for budgeting purposes.

60
Q

L3 - Toby Carvery – how often were you reporting to the client and in what format?

A

The programme on the Toby Carvery projects are only short, typically ranging from 4-6 weeks. I would report to the client typically every 2 to 3 weeks at the half way point.
This would be in the form of a financial statement.

61
Q

L3 - Project Zeta – when you updated the risk register how did you evaluate the current position of known risks?

A

They were discussed with the project team during the contractors progress meeting. The discussion in the progress meeting was reflected within risk register.

62
Q

L3 - Project Zeta - What solution did the design team provide?

A

They altered the design of the welfare facility. It was originally a double storey unit, with a large steel staircase. This was reduced to a single storey design, reducing masonry costs, as well as the cost of an external staircase.

63
Q

What measures can be taken to effectively control costs during the construction phase of a project?

A

Proactive risk and contingency management.
Implementing a robust change control process.
Regular cost reporting which is also forward looking.
Rolling final account with closure process for financial impact of change.