Project Finance Flashcards

1
Q

How would you create a cashflow forecast?

A
  • I would need to have access to the construction programme and contract sum analysis in order to populate the cashflow.
  • The values associated with each element of construction could be forecasted at times to reflect their installation within the programme.
  • I would split the works into the different packages as shown on the contract programme and include individual s-curves for each package.
  • Obtaining drawdown schedules from specialist subcontractors and professional consultants can also assist when populating the cashflow.
  • An alternative approach would be to utilise a previous cashflow from a similar scheme or to use cashflow forecasting software although this may not be as accurate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If your construction budget was £2.5m and proposed construction
period was 25 weeks, would a forecast cashflow expenditure of
£100,000 per week be realistic?

A
  • In reality this would not be very realistic as the cashflow expenditure per week is unlikely to have a flat or regular profile.
  • In reality the expenditure is much more likely to have an S-curve profile where at the start of the scheme, the expenditure per week will be fairly low as the site setup and enabling works are undertaken.
  • As the scheme progresses, items that are of higher value such as the steel frame and M&E installations will be undertaken. The cost expenditure per week at this stage will be much higher than at the start of the scheme.
  • As the scheme draws to a close, minor finishing items such as decoration and cleaning packages will be undertaken again resulting in a lower expenditure cost per week.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the benefit of a cashflow forecast?

A
  • A cashflow forecast allows the employer to gain an understanding of the financial requirements over
    the duration of the project duration and setup any funding requirements for the scheme in advance.
  • It can also act as a check against valuations and provide an early indication of financial difficulties if the
    actual expenditure is lagging behind the forecast.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would you include within a financial report?

A
  • I would typically look to include reference to:
    o a) Contract sum total.
    o b) The value of Instructed variations.
    o c) The value of potential future variations.
    o d) Ongoing claims.
    o e) Provisional Sum Adjustments.
    o e) The anticipated final account total.
    o f) The total of certified payments.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of a financial report?

A
  • To report against budgeted values and act as a working cost check on the project budget.
  • To give the Client an understanding of any savings or additional monies required.
  • To report contract progress compared against pre-contract predictions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are variations?

A

Alterations or modifications to the design, quality or quantity of the contract works or to the site access or working conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why might a variation arise?

A
  • a) change to specification.
  • b) discrepancies between contract documents.
  • c) discrepancies with statutory requirements.
  • d) errors and omissions.
  • e) deficiencies in employer’s requirements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What form must architect’s instructions take?

A
  • It is best practice under the majority of contracts for instructions to be made in writing.
  • The QS is not usually authorised to make additions to the contract sum for instructions that are not in written form.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What about oral instructions?

A
  • The validity of oral instructions depends on whether the form of contract being used contains mechanisms for them to be valid.
  • For example within the JCT Standard Building Contract (SBC):-
    o Where the Contract Administrator issues an instruction otherwise than in writing, it shall be of no immediate effect
    o But the Contractor shall confirm in writing receipt of the verbal instruction within 7 days.
    o If the Contract Administrator does not dissent by notice to the Contractor within 7 days from
    receiving the contractors confirmation, it shall take effect as from the expiry of the latter 7 day
    period.
  • In my opinion it is always best practice to follow up verbal instructions with written instructions as
    soon as possible.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can the contractor object to a variation?

A
  • Some contracts allow the contractor to object to an instruction in special circumstances for example:-
  • In the JCT Standard Building Contract the requirement to comply with a valid instruction is subject to
    certain exceptions, where:-
    o Where the instruction might affect the efficacy of the design of the Contractors Designed
    Portion.
    o Where the instruction might affect the contractor’s compliance with the CDM Regulations.
    o Where the instruction may infringe patent rights.
    o Where the instruction relates to a named specialist, and the contractor is unable to enter into a
    contract with that firm.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What can the architect do if the contractor does not comply with an instruction?

A
  • This depends on the form of contract being used however under JCT Suites if the contractor does not
    follow an instruction, the architect will be required to issue a ‘notice to comply’ to the contractor.
  • If the Contractorstill fails to comply, the architect can instruct another party to carry out the work and
    the contractor will be liable for any additional costs incurred.
  • In this circumstance it is important to record the costs and obtain a range of quotations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What 3 methods are there of obtaining a cost for variations under JCT forms of Contract?

A
  • This depends on the form of contract being used, under JCT SBC, quotations can be made by:-
    o Agreement between the employer and contractor.
    o A schedule 2 quotation.
    o Valuation by the QS under the valuation rules
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the time periods for Schedule 2 quotations under JCT SBC?

A

o The architect should request via issue of an AI.
o The contractor has 7 days to notify that they will not provide one.
o If not, they have 21 days to provide the quotation.
o The architect then has 7 days to confirm in writing the acceptance or rejection.
o The acceptance is called the ‘confirmed acceptance’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What costs does the schedule 2 quotation contain?

A
  • Value of the work.
  • Any adjustment of time.
  • Money in lieu of direct loss and expense.
  • The fair and reasonable cost of preparing the quotation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What costs is the contractor entitled to if the schedule 2 quotation is
rejected?

A
  • The fair and reasonable cost of preparing the quote, as long as the quote itself was fair and reasonable.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the valuation rules under JCT Forms of Contract?

A

There are three rules for measurable work:-
o If it is of a similar character, quantity and in the same conditions as existing work, then the bill
rates should be used.
o If it is of a similar character, but different quantity or conditions, the bill rates should be used as
a basis but a fair allowance should be made to take account of the difference.
o If it is not of a similar character, fair rates and prices should be used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What about non-measurable work?

A
  • This would typically be valued by the dayworks procedure based on the cost of labour, plant and materials that have been incurred.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a star rate?

A
  • A rate that is based on the bill rates but includes a fair allowance.
  • To deviate away from the bill rates there must be a reason as to why the star rate is being adopted.
  • This may be because the conditions on site for installation are more complicated that first envisaged.
19
Q

What are ‘fair rates and prices’?

A
  • A market rate.
  • A rate based on actual costs.
  • A rate in line with current cost data.
20
Q

What are dayworks?

A
  • The prime (actual) cost of all the materials, labour and plant used in carrying out the work, along with a
    percentage additions to each category as set out in the contract.
21
Q

What document should the prime cost be calculated in accordance
with?

A

This should be calculated in accordance with the ‘Definition of the Prime Cost of daywork carried out
under Building Contracts’ published by the RICS.

22
Q

What information is necessary to be able to assess dayworks?

A
  • Vouchers showing the amount of time spent on each activity (dayworks sheets).
  • Names of the workmen.
  • Plant and materials used.
  • This information should be given to the architect or authorised person at the end of the week for
    verification.
23
Q

Can the QS alter hours which he considers to be excessive on a
dayworks sheet that is authorised by the architect?

A
  • No the hours recorded and signed off should be maintained within the variation.
24
Q

What would you do if the contractor submitted 10 dayworks sheets to
you for payment?

A
  • I would verify with the architect that a relevant variation has occurred and is recorded on an Architects
    Instruction.
  • I would check to ensure there is no other contractual method of valuing the variation.
  • Providing the Architects Instruction is in place and no other mechanism for valuation is available I
    would seek verification of the hours and materials.
25
Q

If you and the contractor’s QS could not agree on something how
would you resolve it?

A
  • I would discuss with the partner and client to try and seek a resolution with the contractor.
  • The contractor could take the dispute to adjudication if necessary but all parties should try and resolve the matter by negotiation in the first instance.
26
Q

What is quantum meruit?

A

This translates to ‘what he deserves’ for example fair and reasonable costs that have been incurred.

27
Q

Give an example of where quantum merit might be used

A

If the employer and contractor reach a separate agreement on acceleration, the costs of this may be
based on a ‘fair and reasonable’ basis.

28
Q

What is loss and or expense under JCT Forms of Contract?

A
  • L&E reimburses the contractor for direct loss and/or expense incurred in carrying out additional work
    or from an employer’s breach of contract.
29
Q

What are the relevant matters?

A

There are 5 relevant matters:-
o Variations.
o Instructions.
o Execution of an approximate quantity that was not a reasonably accurate forecast of quantity.
o Suspension by the contractor for non-payment.
o Any impediment, prevention or default by the employer.

30
Q

What is the key thing to remember when assessing loss and expense
claims?

A
  • It should be the actual loss incurred by the contractor.
31
Q
A
32
Q
A
33
Q
A
34
Q
A
35
Q
A
36
Q
A
37
Q
A
38
Q
A
39
Q
A
40
Q
A
41
Q
A
42
Q
A
43
Q
A